Download presentation
Presentation is loading. Please wait.
Published byAmbrose Carpenter Modified over 9 years ago
1
Utility Engineers, PC
2
Generation Transmission Distribution
3
Generation - electric energy generation takes primary energy (fuel resources) to create a secondary form of energy (electricity). Transmission – process of transferring electric energy from one location to another in an electric power system. Distribution - final stage in the delivery of electricity to end users. Carries electricity from the transmission system and delivers it to consumers.
4
Safety Customer Service Reliable Cost-effective Sufficient Short Term Long Term Planned Loads Unplanned Loads
5
Safety- No electrical hazards ◦ Customers ◦ Utility personnel
6
Multiple utility power sources ◦ Supplying multiple connection paths to the loads served. Selecting quality electrical equipment and conductors Using the best installation methods. System alarms ◦ monitoring ◦ diagnostics
7
Budget - key factor in assessing competing designs. ◦ Initial cost of installation Material Labor In House Outside Contractors ◦ Life cycle cost
8
System design to accommodate changes. Future expansion ◦ Additional load Justification with trending and historical data. Transformers ◦ increase capacity ◦ fan cooling ◦ pump cooling Circuits ◦ Capacity ◦ Quantity
9
System redundancy – Ability to take electrical equipment out of service without dropping loads. ◦ Dual Transformers ◦ Transfer Bus ◦ Circuit Ties ◦ Redundant Equipment
10
Transformer Evaluation Transformer Choices Remanufactured Rebuilt New Evaluate operating losses Higher first cost compared to life cycle cost Utility energy charge applied for the losses in the transformer considering initial cost and cost of money (life cycle cost)
11
Substation Structure ◦ Aluminum50+ Years ◦ Steel40 Years Power Transformers40 Years Distribution Transformers25 Years Distribution Switch25 Years Circuit Breakers40 Years Instrument Transformers45 Years Relay and Control15 Years Communications 10 Years SCADA15 Years
12
Fencing20 Years Distribution Lines40 Years Street Lighting20 Years Meters, Mechanical20 Years Meters, Solid State12 Years Poles ◦ Steel55 Years ◦ Concrete55 Years ◦ Wood45 Years Towers50 Years Underground Conduit50 Years Underground Conductors25 Years Fiber Optic20 Years
13
Design Standards Construction Standards Loading Maintenance ◦ Policy ◦ Procedure ◦ Practice Operating Practice
14
Environment ◦ Switching ◦ Lightning and Surges ◦ Location
15
◦ System Location ◦ Temperature ◦ Moisture ◦ Protection ◦ Load factor ◦ Power factor
16
Scheduled Maintenance Diagnostic Maintenance Predictive Maintenance
17
Per Manufacturer Recommendations Manage Risk with Predictive Maintenance ◦ Testing ◦ Diagnostics ◦ Monitoring
19
Substation Structure ◦ Aluminum50+ Years ◦ Steel40 Years
20
Power Transformers 40 Years
21
Unit Substation Transformers40 Years
22
Distribution Transformers25 Years
24
Distribution Switch25 Years
25
Group Operated Air Break Switch 25 Years
26
Circuit Breakers40 Years
27
Instrument Transformers45 Years
28
Relay and Control15 Years
29
Communications10 Years
30
SCADA15 Years (Supervisory Control and Data Acquisition)
36
Power transformers are the most significant portion of municipal system assets representing 35 percent of typical substation costs. Major concern to every electric utility. All transformers are not the same. ◦ Materials ◦ Construction ◦ Cooling
40
After Failure - ◦ When equipment fails it is repaired or replaced. Outage Maintenance - ◦ Equipment is de-energized and maintenance is performed. Predictive Maintenance – ◦ Based on early indications, equipment is maintained.
41
Acceptance Test – Verifies that equipment supplied is functional and within specifications. Diagnostic Test – Detection of specific issues or problems. Predictive – Identifies early indications of potential issues.
44
Open Construction
45
Armless Construction ◦ 3 covered conductors on fiberglass supports.
46
Hendrix Cable Construction ◦ Hendrix Cable - 3 covered conductors supported by a messenger and separated and by spacers.
47
Underground
48
15 KV Cutout ◦ Solid Blade ◦ Fusible First Line of Protection for Faults
49
Surge Arrester Load Break Cutout Termination
50
Surge Arrester
51
Group Operated Air Break Switch
52
Recloser
53
Sectionalizer
54
Lighting Security Meter Replacement
55
Utility Engineers, PC
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.