The Republic of the Union of Myanmar Ministry of Electric Power Electricity Supply Enterprise Kayah State Office Priorities and Detailed Description of Electrification Plan For Kayah State Dated -21.Oct.2015
2
As Per DE Idea after discussion with Local government As the whole Kayah State, we must perform for only submitted village in demoso township with NEP project that a village locate in the distribution line within two miles.Nowaday there is only five village ( wich are situated within two miles ) left according to NEP plan.In currently time, we are distributing the electricity to the quarters fo hpruso and 12Villages neighboruing hpruso with 33/11kV,1.25MVA transformer but we have been Improving to fulfill the demand of electricity for 14villages neighbouring hpruso in 2014- 2015 fiscal year and 44villages neighbouring hpruso in 2015-2016 fiscal year with regional government budget.So, we would like to submit that to change the currently 33/11kV, 1.25MVA transformer as a 33/11kV, 5MVA transformer. At that time, we are ferforming the distribution line and substation. The distribution for 33kV 36.5miles,the substation for 33/0.4kV transformer 7Nos,the distribution line for 11kV 48.5miles, the substation for 11/0.4kV transformer 8Nos and the distribution line for 400V 6.3miles so as to get electricith for 15 village of neighbouring Hoyar in hpruso township with regional government budget. As a matter of fact, we would like to submit to improve 33/11kV,5MVA transformer hpruso township and then to build for 33/11kV 1.25MVA substation surplus transformer of hpruso township for hoyar. We would like to subit that we alreay negotiated with regional grovrnment that the relevant proposal plans and the condition of tasks. 2
3
Priority Electrification Project List for Kayah State NoDistrictTownshipNos of VillageRemark 1Loikaw Demoso5 Within 2 miles Distance from existing grid Line Hpruso57 Upgrad 33/11kV 1.25MVA to 5MVA 33kV Outgoing Switch Bay 1No Hpruso ( hoyar )8 33/11kV, 1.25 MVA 1No Total 70 3
4
NoNo District No of Village To be Electrif ied No of Hous e Hous e hold Popu la tion To be constructed Estima ted cost (Mil Kyates ) Task by regional 400 V Lines (Miles ) Estimat ed cost (Mil Kyates) Cost for 11 kV Line11/0.4 kV Transformer Mile Materi al Cost Trans port Cost Cons truc tion Cost TotalKVANo Materia l Cost Trans port Cost Constr uc tion Cost Total 1 Loikaw Distrit 516918511182 47.8164.7 9.2 61.71 6 250436.7621.88.61247.174108.89 2.3103.5 2 Bawlak he ----- -- --------- -- Total51691851118247.8164.79.2 61.71 6 250436.7621.88.61247.174108.892.3103.5 Detailed Electrification Plan for Kayah State (Within 2 miles from Existing 11 kV Distribution Line) 4
5
Electrification Plan for Villages of Kayah State (Within 2 miles from Existing 11 kV Distribution Line) To be Constructed 33/11kV Transformer 2 Nos 33kV Outgoing Switch Bay 1 No 11kV Distribution Line 2 miles 400V Distribution Line 2.3 mile 11/0.4 kV Distribution Transformer 4 Nos Kayah State No. of Villages - 70Nos Household - 3362 Estimated Cost - 1000.79 (mil kyats) Loikaw District No. of Villages - 70Nos Household - 3362 Estimated Cost - 1000.79 (mil kyats) 5
6
Detailed Electrification Plan for Loikaw District (Within 2 miles from Existing 11 kV Distribution Line) No Town ship No of Villag e To be Electr ified No of Hous e Hous e hold Popu la tion To be constructed Estima ted cost (Mil Kyates ) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Lines (Miles ) Estimat ed cost (Mil Kyates) Mile Mater i al Cost Trans port Cost Constr uc tion Cost TotalKVANo Mater ial Cost Trans port Cost Constr uc tion Cost Total 1 Demos o 516918511182 47.81 6 4.7 9.261.7162504 36.76 2 1.88.612 47.17 4 108.89 2.3103.5 Total516918511182 47.81 6 4.79.261.7162504 36.76 2 1.88.612 47.17 4 108.892.3103.5 6
7
33/11kV ( 5 MVA) Ngwetaung Substation ( Existintg) 33/11kV ( 1.25MVA) Hpruso Substation ( Existing ) Dawsoshae Village 11/0.4 kV(50 kVA) Dawlawkhuthit & Dawlawkhu houng Village 11/0.4 kV(50 kVA) Dawsophya Village 11/0.4 kV(100 kVA) Legend 33/11kV Sub station ( Existing) 11kV Line ( Existing) 11kV Line 2Mile ( Proposal) Village( Proposal) Location Map of Electrification Plan for Loikaw District (Within 2 miles from Existing 11 kV Distribution Line) Soungduywarthit Village 11/0.4 kV(50 kVA) Loikaw District No. of Villages - 5Nos Household - 185 Estimated Cost - 108.89 (mil kyats) 7
8
Detailed Electrification Plan for Loikaw District (Within 2 miles from Existing 11 kV Distribution Line) No Town ship Name of Village To be Electrifi ed No of Hous e Hous e hold Popu latio n To be constructed Estim ated cost (Mil Kyate s) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Lines (Miles ) Estima ted Cost (Mil Kyats) mile Materi al Cost Trans p ort Cost Constr uction Cost TotalKVANo Materi al Cost Tran spor t Cost Cons tructi on Cost Total 1. Demos o Soungdu- ywarthit 3035205 ----- 50 1 8.803 0.45 2.15 3 11.40 6 0.522.5 2. Demos o Dawsoshe 2225153 ----- 50 1 8.803 0.45 2.15 3 11.40 6 0.522.5 3. Demos o Dawsoph a 8085512 ----- 100 1 10.353 0.45 2.15 3 12.95 6 0.522.5 4. Demos o Dawlawkh u 1820120 2.047.8164.79.2 61.71 6 50 1 8.803 0.45 2.15 3 11.40 6 73.1220.836.0 5. Demos o Dawlawkh u thit 1920128 Total16918511182.047.8164.79.2 61.71 6 250436.7621.88.612 47.17 4 108.892.3103.5 8
9
33/11kV ( 5 MVA) Ngwetaung Substation ( Existintg) 33/11kV ( 1.25MVA) Hpruso Substation ( Existing ) Soungduywarth it Village 11/0.4 kV(50 kVA) Dawsoshae Village 11/0.4 kV(50 kVA) Dawlawkhuthit & Dawlawkhu houng Village 11/0.4 kV(50 kVA) Dawsophya Village 11/0.4 kV(100 kVA) Legend 33/11kV Sub station ( Existing) 11kV Line ( Existing) 11kV Line 2Mile ( Proposal) Village( Proposal) Location Map of Electrification Plan for Demoso Township (Within 2 miles from Existing 11 kV Distribution Line) 9
10
Seri al Township To be ConstructedThe effective area Estimated Cost ( Mil Kyates ) Substatio n 66 kV Line(mil e) 33 kV Line (mile) Totall Villages Total House Hold Total Popu lation Materials Cost Construct ion Cost Total 1Hpruso 33/11kV upgrad 1.25 to 5 MVA With 33kV utgoing Switch Bay 1No --57277414414380.024.9404.9 2 Hpruso ( Hoya ) 33/11kV 1.25 MVA --84031791375.0112.0487.0 Total2--65317716205755.0136.9891.9 The additional electrification statement due to newly and upgrading 66/33/11kV substation and related power Line for Kayah State Remark 33/11kV, 1..25MVA transformer ( Hpruso )is going to promate as 33/11kV 5MVA transformer and the surplus 1.25MVA transformer is going to build in Hoyar. 10
11
Location Map for 33/11kV Substation 2Nos & 33kV Outgoing Switch bay at Hpruso Township Upgrad 33/11kV 1.25MVA (Existing) to 5MVA and 33kV Outgoing Switch Bay 1No 33/11KV, 1.25MVA Substation 1No 11
12
NoNo Fiscal Year Staet Capital Budget for ESE ( mil Kyats ) Staet Capital Budget for DRD (mil Kyats ) Electrified Connection Total Cost for 11kV Line & 11/0.4 TR Total Cost for 400V Line TotalOff Grid ON GridOff Grid Villa ge ( Nos ) Consum er ( Nos ) Villag e ( Nos ) Consum er ( Nos ) 1 2014 -2015 Estimate ( BE + RE ) 5901.266702.49 6603.75 6 441.429569231204418 2 2015 -2016 Estimate ( BE + RE ) 9401.5372697.6 12099.1 37 247.251146948441210 3 2016 -2017 Budget Estimate( BE) 456.38 2104.9 6 2561.34801.3251625802671 Grand Total 15759.183 5505.0 5 21264.2 33 1489.97234154962448299 The Statement Fiscal Yearly Budget and Electrified Connection for Kayah State 12
13
Sr No Description Quantitie s Transported Site 133/11 kV,5 MVA Transformer1 No Loikaw District, PMO Office 233kV Outgoing Switch Bay Accessories1 Set Loikaw District, PMO Office 3 33kV Incoming Switch Bay, 33kV Control pannel and 11kV 1 incoming 2 outgoing cubical for 1.25MVA And Accessories 1 Set Loikaw District, PMO Office 411/0.4kV, distribution transformer4 No Loikaw District, PMO Office 510 meter Concrete Pole100 Nos Loikaw District, PMO Office 6A C S R 95 mm 2 4.2 Tons Loikaw District, PMO Office 711kV Pin Insulator with Spindle230 Nos Loikaw District, PMO Office 811kV Disc Insulator with fittinggunset72 Set Loikaw District, PMO Office 9Other Materials1 Lot Loikaw District, PMO Office Main Materials List Transported to Loikaw District Office 13