St. Cloud High School Phased Comprehensive Construction Project April 28, 2009 1
2
Design – Phase 1 Early Work Demo Building 3 Building 4 Building 5 Misc Modular Building 15 Building 6 3,4 6 5 15 April 28, 2009 2
3
Design – Phase 1 New Buildings New Building 3 Story Classroom + Media Central Plant New Gym 7 New Cafeteria 9 Remodel Outdoor Dining 28 Admin 22 3 Story Classroom + Media Remodel Admin 22 Dining New Cafe. 9 Demo Building 10 Gym 7 Central Plant Remodel Admin 28 Demo Bldg. Build 10 April 28, 2009 3
4
Design – Phase 2 Work New Building New Performing- Arts 2 New Vocational 5 New 2 Story 8 Demo Building 1,2,7,8, 9,11,12,13,14 Remodel 21 Science 25 Classroom Demo Dining Food 2 1 New Performing Arts 2 Arts 2 Remodel Admin 22 Dining Cafeteria 9 12,13 Classroom New 2 Story Classroom 8 From Previous Phase 3 Gym 7 Central Plant Science 21 New Vocational 5 7 9 11 Classroom 25 8 14 April 28, 2009 4
5
Final Master Plan Design Classroom - 3 65,000 SF Existing Class. - 25 17,190 SF Vocational - 5 12,800 SF Existing Lab - 21 15,474 SF Gym - 7 38,800 SF Total Gross SF 279,341 Admin - 1 21,917 SF Auditorium - 2 Music 35,360 SF Dining / Kitchen - 9 26,800 SF Classroom - 8 46,000 SF April 28, 2009 5
6
Project Curriculum Classroom - 3 65,000 SF Existing Class. - 25 17,190 SF Vocational - 5 12,800 SF Existing Lab - 21 15,474 SF Gym - 7 38,800 SF Total Gross SF 279,341 Admin - 1 21,917 SF Auditorium - 2 Music 35,360 SF Dining / Kitchen - 9 26,800 SF Classroom - 8 46,000 SF April 28, 2009 6
7
Project Curriculum April 28, 2009 7
8
Design Images Auditorium, North Elevation April 28, 2009 8
9
Design 3 story Classroom & Media Center, East Elevation April 28, 2009 9
10
Design Cafeteria/ Kitchen + Phase 3 Classroom Building, West Elevation April 28, 2009 10
11
3,4 6 5 15 Schedule – Phase 1 Early Work + Site work Demo Building 3 Building 4 Building 5 Misc Modular Building 15 Building 6 Schedule Early Works May, 2009 Aug, 2010 Site / Civil Work & Underground Infrastructure Wet Retention Ponds April 28, 2009 11
12
Schedule – Phase One New Buildings New Building 3 Story Classroom + Media Central Plant New Gym 7 New Cafeteria 9 Remodel Outdoor Dining 28 Admin 22 3 Story Classroom + Media Remodel Admin 22 Dining New Cafe. 9 Demo Building 10 Gym 7 Central Plant Remodel Admin 28 Demo Bldg. Build 10 EWP Phase 1 June, 2009 Schedule Aug, 2010 April 28, 2009 12
13
Schedule – Phase 2 New Building New Performing- Arts 2 New Vocational 5 New 2 Story 8 Demo Building 1,2,7,8, 9,11,12,13,14 Remodel 21 Science 25 Classroom Demo Dining Food 2 Demo 1 New Performing Arts 2 Arts 2 Remodel Admin 22 Dining Cafeteria 9 Demo 12,13,14 Classroom New 2 Story Classroom 8 Demo 7,8,9,11 From Previous Phase 3 Gym 7 Central Plant Science 21 New Vocational 5 EWP Phase 1 Phase 2 June, 2010 Aug, 2011 Schedule April 28, 2009 13
14
Schedule – Phase 2, Student Access New Building New Performing- Arts 2 New Vocational 5 New 2 Story 8 Demo Building 1,2,7,8, 9,11,12,13,14 Remodel 21 Science 25 Classroom Demo Dining Food 2 Demo 1 New Performing Arts 2 Arts 2 Remodel Admin 22 Dining Cafeteria 9 Demo 12,13,14 Classroom New 2 Story Classroom 8 Demo 7,8,9,11 From Previous Phase 3 Gym 7 Central Plant Science 21 New Vocational 5 EWP Phase 1 Phase 2 June, 2010 Aug, 2011 Schedule STUDENT ACCESS April 28, 2009 14
15
Schedule – Phase 2, Student Access New Building New Performing- Arts 2 New Vocational 5 New 2 Story 8 Demo Building 1,2,7,8, 9,11,12,13,14 Remodel 21 Science 25 Classroom Demo Dining Food 2 Demo 1 New Performing Arts 2 Arts 2 Remodel Admin 22 Dining Cafeteria 9 Demo 12,13,14 Classroom New 2 Story Classroom 8 Demo 7,8,9,11 From Previous Phase 3 Gym 7 Central Plant Science 21 New Vocational 5 EWP Phase 1 Phase 2 June, 2010 Aug, 2011 Schedule April 28, 2009 15 STUDENT ACCESS
16
Schedule – Completed Master plan Classroom - 3 65,000 SF Existing Class. - 25 17,190 SF Vocational - 5 12,800 SF Existing Lab - 21 15,474 SF Gym - 7 38,800 SF Admin - 1 21,917 SF Auditorium - 2 Music 35,360 SF Dining/Kitchen - 9 26,800 SF Classroom - 8 46,000 SF EWP Phase 1 Phase 2 Aug, 2011 Schedule May, 2009 April 28, 2009 16