Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 Update on Q2 Main linac starting gradient, upgrade gradient, and upgrade path Results of WG5 discussions after feedback from plenary on Tuesday New Option.

Similar presentations


Presentation on theme: "1 Update on Q2 Main linac starting gradient, upgrade gradient, and upgrade path Results of WG5 discussions after feedback from plenary on Tuesday New Option."— Presentation transcript:

1 1 Update on Q2 Main linac starting gradient, upgrade gradient, and upgrade path Results of WG5 discussions after feedback from plenary on Tuesday New Option 2 (16 MV/m => 28 MV/m) Enhanced upgrade scenario explorations for options 1 & 2

2 2 Three Upgrade Options (with New Names) 1 : (same as last time)”Highest acceptable risk”based on 10% margin Build tunnel long enough (41km) for one TeV, but install only 500 GeV worth of cryomodules in first 22 km of tunnel for 500 GeV phase. 35 MV/m installed gradient, 31.5 MV/m operating gradient for 500 GeV (gradient choice rationale discussed earlier). Fill second part of tunnel (19 km) with 36 MV/m cavities (gradient choice discussed earlier), install more RF/refrigeration 2**: …NEW ”Lower risk”…based on 20% margin 500 GeV phase: Build tunnel long enough for one TeV (41 km). Populate 24.4 km of tunnel with cavities (35 MV/m installed gradient ) Operate cavities at 20% margin (i.e. 28 MV/m). Increase gradient to 31.5 MV/m over Phase I lifetime, energy climbs to 560 GeV. Upgrade : Add 36 MV/m cavities in remaining 16.6 km, and add RF and refrigeration for upgrade. 3 : Half-Tunnel (same as last time) Build first half of tunnel for 500 GeV (22km) and fill it with full gradient cavities (35 MV/m installed gradient, 31.5 MV/m operating gradient, discussed later). Build second half of tunnel (19km) and add 36 MV/m cavities and RF/refrigeration for upgrade.

3 3 Initial cost: best = 3: (half-tunnel); worst = Option 2: (20%margin) –Cryomodules + RF + Refrigeration + 2Tunnel “guiding model” costs –Option 1 = 1.16, Option 2 = (1.6) 1.22, Option 3 = 1.0 –Option 2 is less risky, most flexible for physics through higher initial energy reach Upgrade cost: best = Option 2 (20% margin); worst = Option 3 (half- tunnel). –Option 1 = 0.7, Option 2 = (0.4) 0.63, Option 3 = 0.9 Total cost (initial + upgrade): worst = 3: (20% margin) –. Option 1 = 1.85, Option 2 = (1.97) 1.85, Option 3 = 1.9 Pros/cons of upgrade paths

4 4 But Option 1 and Option 2 are getting closer ! –Cost Model estimates Option 2 (20%margin) ~1.05 x Option 1 (10% margin) ( Linac + RF + Cryo + 2tunnels) –Cost Model estimates Option 1 ~ 1.16 x Option 3 –Option 3 (Half-tunnel): Upgrade viability may be questionable, physics impact of digging new tunnel in vicinity of machine (this is a higher level discussion topic than WG5) WG5 Preferred Choice still is : Option 1 (10% margin)

5 5 A More Optimistic Upgrade Scenario Based on Weeding out Scheme (Still under discussion) 1 :..”Highest acceptable risk”..based on 10% margin Build tunnel (41km 38.5 km) for one TeV, but install only 500 GeV worth of cryomodules in first 22 km of tunnel. 35 MV/m installed gradient, 31.5 MV/m operating gradient for 500 GeV (gradient choice rationale discussed earlier). Upgrade : Fill second part of tunnel (19 km 16.5 km) with 36 MV/m cavities (gradient choice discussed later), install more RF/refrigeration. Replace the lowest performing cryomodules during upgrade with new cryomodules so that all Phase I modules perform at 35 MV/m..anticipate replacing 10% of existing cryomodules. Note : total tunnel length shortened by 2.5 km 2: …”Lower risk”…based on 20% margin Build tunnel long enough for one TeV (38.5 km). Populate 24.4 km tunnel with cavities in phase1 (35 MV/m installed gradient ) Operate cavities at 20% margin (at 28 MV/m) in 500 GeV Phase 1. Increase gradient of installed cavities to 31.5 MV/m over Phase I, energy climbs to 563 GeV. Upgrade : Add 36 MV/m cavities in 14.1 km, and add RF and refrigeration for upgrade. Replace the lowest performing cryomodules during upgrade with new cryomodules so that all Phase I modules perform at 35 MV/m..anticipate replacing 10% of existing cryomodules. Note total tunnel length shortened by 2.5 km

6 6 Estimated Cost Impact Upgrade cost: Option 1 = 0.7 0.66, Option 2 = 0.63 0.57, Option 3 = 0.9 0.82 Total cost (initial + upgrade): Option 1 = 1.85 1.82, Option 2 = 1.85 1.78, Option 3 = 1.9 1.82 (Includes cost of replacement modules)

7 7 Attractive Features of Weeding Concept Low gradient cryomodules identified during Phase I running Keep cavity and cryomodule production factory running at low rate to produce 10% replacement modules over lifetime of 500 GeV Phase –About 100 - 120 modules (1200 - 1500 cavities) Avoids factory production halt and start up problems for upgrade production

8 8 Requests to Other Groups What is the effect of 10%, 20% margin on reliability? What is the effect of 10% or 20% margin on cost? –Guiding model suggests 10% extra margin has initial project cost penalty of 5% (on linac cost only). –All costs need more detail analysis How attractive is the weeding out scheme in feasibility, cost, and upgradability ?


Download ppt "1 Update on Q2 Main linac starting gradient, upgrade gradient, and upgrade path Results of WG5 discussions after feedback from plenary on Tuesday New Option."

Similar presentations


Ads by Google