G RAND R APIDS P UBLIC S CHOOLS P HASE I P ROJECTS
3
Henry Elementary/Martin Luther King Leadership Academy Alger Middle School Sibley Elementary School Harrison Park Elementary and Middle School Madison Park/Gerald Ford Middle School Palmer School (Elementary) Burton Renaissance/ Elementary School Dickinson School (Elementary) Hall School (Elementary) 1
4
3
5
4
6
H ENRY E LEMENTARY S CHOOL 5 Old School Building
7
6 M ARTIN L UTHER K ING L EADERSHIP A CADEMY Grade Level: PK to 8th Capacity: 500 Area: 69,000 Sq Ft Project Cost: $ 10.9 m Completed : 2006
8
7 M ARTIN L UTHER K ING L EADERSHIP A CADEMY
9
8 M ARTIN L UTHER K ING (F LOOR P LANS ) 1 st Floor Plan2 nd Floor Plan3 rd Floor Plan
10
A LGER M IDDLE S CHOOL Old School Building 9 Grade Level: 6 th to 8 th Capacity: 600 Area: 88,860 Sq Ft Project Cost: $14.2 m Completed 2006 New School Building
11
10 A LGER M IDDLE S CHOOL
12
11 A LGER M IDDLE S CHOOL 1 st Floor Plan2 nd Floor Plan3 rd Floor Plan
13
S IBLEY / S TRAIGHT S CHOOL Straight School Sibley Elementary School 12
14
13 S IBLEY E LEMENTARY S CHOOL Grade Level: PK to 5 th Capacity: 586 Area: 67,000 Sq Ft Project Cost: $ 10.6 m Completed: 2006
15
14 S IBLEY E LEMENTARY S CHOOL 1 st Floor Plan2 nd Floor Plan3 rd Floor Plan
16
H ARRISON P ARK S CHOOL (1924) School Building before renovation 15
17
16 H ARRISON P ARK E LEMENTARY AND M IDDLE S CHOOL ( AFTER M AJOR R ENOVATION ) Grade Level: PK to 5 th Capacity: 547 Area: 72,715 Grade Level: 6 th to 8 th Capacity: 542 Area: 88,875 Sq Ft Total Project Cost: $ 24.2 m Completed: 2007
18
17 H ARRISON P ARK E LEMENTARY AND M IDDLE S CHOOL ( AFTER R ENOVATION )
19
18 H ARRISON P ARK E LEMENTARY AND M IDDLE S CHOOL ( AFTER R ENOVATION ) 1 st Floor Plan2 nd Floor Plan
20
M ADISON P ARK S CHOOL 19 Old School Building
21
20 G ERALD F ORD M IDDLE S CHOOL Grade Level: 6 th to 8 th Capacity: 554 Project Cost: $ 16.1 m Area: 86,250 Sq Ft Completed: 2007
22
21 G ERALD F ORD M IDDLE S CHOOL
23
22 G ERALD F ORD M IDDLE S CHOOL 1 st Floor Plan2 nd Floor Plan3 rd Floor Plan
24
P ALMER S CHOOL Old School Building 23 Grade Level: PK to 5 th Capacity: 400 Renovation Area: 33,755 Sq Ft Project Cost: $ 5.2 m Completed: 2006
25
24 P ALMER S CHOOL 1 st Floor PlanSite Plan
26
B URTON E LEMENTARY AND MIDDLE S CHOOL Old School Building 25
27
26 School Building under Renovation Grade Level: PK to 5 th Capacity: 600 Area: 74,400 Sq. Ft Grade Level: 6 to 8 th Capacity: 600 Area: 90,395 Sq. Ft Total Project Cost: $ 28.5 m To be completed : 2008 B URTON R ENAISSANCE / E LEMENTARY S CHOOL
28
27 B URTON R ENAISSANCE / E LEMENTARY S CHOOL School Building under Renovation
29
D ICKINSON S CHOOL 28 Old School Building.
30
29 D ICKINSON S CHOOL New School Building under Construction Adjacent to Old Building Grade Level: PK to 5 th Capacity: 450 Area: 56,645 Sq Ft Project Cost: $ 9.6 m To be completed: 2008
31
H ALL S CHOOL (O LD ) 30
32
31 H ALL S CHOOL (N EW ) Ground Floor Plan Third Floor Plan Second Floor Plan Grade Level: PK to 5 th Capacity: 500 Area: 60,000 Sq Ft Project Cost: 11.5 m To be completed: 2009
33
32 H ALL S CHOOL (N EW ) Site Plan