Download presentation
1
Ambassador Sherali Jononov
Embassy of the Republic of Tajikistan to the Islamic Republic of Pakistan "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov
2
Energy Profile Power Projects Prospective -Hydro Prospective-Thermal Regional Initiatives - OHL
3
Tajikistan Energy Profile
Potential for generate 527 billion. KW. hours per year The installed capacity of power plants of 5400 MW Of these, 95% hydro and 5% thermal power stations The annual generation more than 17 billion. KW. hour Excess of hydropower in the summer months (from 3 to 5 billion. KW. hour) Winter energy shortages more than ,5 billion. KW. hour 본문
4
Power Projects Implementation
Completed Projects 1.7 billion. USD Ongoing Projects 268 million. USD on design and preparation stage 938,3 million. USD Projects
5
Power Projects Implementation
Completed Projects 1.7 billion. USD EMERGENCY BAYPAZA HPP LANDSLIDE STABILIZATION RECONSTRUCTION OF DUSHANBE CITY ELECTRICAL NETWORKS CONSTRUCTION OF MHPP IN RURAL AREAS OF THE REPUBLIC OF TAJIKISTAN CONSTRUCTION OHL-500kV SOUTH-NORTH CONSTRUCTION OHL-220kV ADDITIONAL WORKS OF CONSTRUCTION OHL-500/220kV SOUTH-NORTH & LOLAZOR-KHATLON REHABILITATION OF ENERGY SECTOR OF THE REPUBLIC OF TAJIKISTAN REGIONAL POWER INTERCONNETION TRASMISSION PROJECT RECONSTRUCTION OF 220kV SWITCHYARD AT NUREK HPP CONSTRUCTION OF 220KV OHL HUJAND-AYNI ESTABLISHMENT OF UNIFIED POWER SYSTEM OF THE NORTH OF TAJIKISTAN REGIONAL POWER TRANSMISSION PROJECT ENERGY LOSS REDUCTION PROJECT IN DUSHANBE CITY CONSTRUCTION OF SANGTUDA HPP-1 CONSTRUCTION OF SANGTUDA HPP-2
6
Power Projects Implementation
Ongoing Projects 268 million. USD Reconstruction of 500kV Switchyard at Nurek HPP Regional power transmission project Rehabilitation of 500kV Regar substation Energy loss reduction project Energy loss reduction project in Sughd Region
7
Power Projects Implementation
Projects on design and preparation stage 938,3 million. USD Golovnaya 240 MW HPP rehabilitation project Rehabilitation of 220kV Ravshan substation Construction of 2x50 MW second phase of Dushanbe TPP 2 Rehabilitation of Kayrakum HPPP Wholesale Metering and Transmission Reinforcement Project CASA-1000
8
Our Development Partners
SECO 15,2 mln. USD– grant Sangtuda HPP-2 40 mln. USD – Taj. Gov. 318,8 mln.USD – Iran Gov. ADB 63,27 mln. USD – loan 366, 77 mln. USD –grant WB 63 mln. USD – loan 17,2 mln. USD - grant IDB 52,73 mln. USD – loans KfW 18,0 mln. Euro–loan 7,0 mln. Euro-grant KFAED 3, 600 mln. KD–loan OPEC 8,5 mln. USD – loan BT co-financing 63,63 mln. USD China Eximbank 801,43 mln. USD –loan EBRD 70 mln. USD – loan 11,7 mln. USD - grant Sangtuda HPP-1 174,6 mln. USD – Taj. Gov. 524 mln. USD – Rus. Gov
9
Prospective Projects Hydro
ROGUN HPP (3600 MW) SHUROB HPP (850 MW) NUROBOD HPP– 1 (460 MW) NUROBOD HPP– 2 (400 MW) FONDARYO HPP (300 MW) AYNI HPP (160 MW) SANOBOD HPP (125 MW) ZARAFSHON HPP (150 MW)
10
Prospective Projects -Thermal
DUSHANBE-2 TPP 2х150 MW – SECOND PHASE (300 MW) SHUROB TPP (300 MW) FON YAGNOB TPP (600 MW)
11
Regional Initiatives - OHL
CASA-1000 PROJECT 500kV OHL TAJIKISTAN-AFGHANISTAN- TURKMENISTAN IRAN (through Vakhan corridor) 500kV OHL TAJIKISTAN - PAKISTAN TUTAP PROJECT
12
500kV line that will connect
Project CASA-1000 500kV line that will connect Kyrgyzstan-Tajikistan-Afghanistan-Pakistan (1200 km) Construction of 500kV OHL Tajikistan-Pakistan through Vakhan corridor (length – 750 km) Construction of 500kV OHL Tajikistan-Afghanistan-Turkmenistan (length -650 km) Construction of 500kV OHL Tajikistan-Afghanistan-Iran (length-715 km)
Similar presentations
© 2025 SlidePlayer.com. Inc.