STATUS UPDATE FOR CPRA January 26, 2011.  Study combines Cong. Boustany Recon with LCA Chenier Plain Effort  Cost Share Agreement signed in Jan. 2009.

Similar presentations


Presentation on theme: "STATUS UPDATE FOR CPRA January 26, 2011.  Study combines Cong. Boustany Recon with LCA Chenier Plain Effort  Cost Share Agreement signed in Jan. 2009."— Presentation transcript:

1 STATUS UPDATE FOR CPRA January 26, 2011

2

3  Study combines Cong. Boustany Recon with LCA Chenier Plain Effort  Cost Share Agreement signed in Jan. 2009  Scoping meetings held in Mar. 2009  Feasibility Scoping Meeting – June 2010  Study GOAL = a Comprehensive Restoration and Protection Plan for Southwest Coastal LA

4  We continue to refine the vision of the State Master Plan for Southwest Louisiana  Measure screening and evaluation is underway  Ecosystem benefits and Engineering cost for measures are being developed  H&H Modeling is underway  The Project Delivery Team meets weekly

5

6  Measure types under consideration include:  Shoreline stabilization  Unique natural features restoration  Marsh creation/restoration  Hurricane risk reduction  Hydrologic and salinity control  The study team will combine the best performing and cost effective restoration and risk reduction measures into alternatives

7

8

9

10

11

12

13  Feasibility report guidance is more risk adverse than at study initiation  Review plan changes  Sea level rise requirements  Project Management Plan may be revised once H&H modeling is complete  President’s Budget for FY 2011 does not include funds for Southwest Coastal

14 SCHEDULE Tentatively Selected Plan – Oct 2011 Alternative Formulation Briefing – June 2012 Draft Feasibility Report – Sept 2012 The Report will be actionable: a quality authorization document

15 Contact Information = norwyn.johnson@la.gov 225-342-0924 Paul.A.Varnado@usace.army.mil 504-862-1808


Download ppt "STATUS UPDATE FOR CPRA January 26, 2011.  Study combines Cong. Boustany Recon with LCA Chenier Plain Effort  Cost Share Agreement signed in Jan. 2009."