Suvarnabhumi Airport Development CASE STUDY (3) 2003. 8. 15 KOICA(NESDB) Transformation of Gimpo Airport since IIA’s operation.

Similar presentations


Presentation on theme: "Suvarnabhumi Airport Development CASE STUDY (3) 2003. 8. 15 KOICA(NESDB) Transformation of Gimpo Airport since IIA’s operation."— Presentation transcript:

1 Suvarnabhumi Airport Development CASE STUDY (3) 2003. 8. 15 KOICA(NESDB) Transformation of Gimpo Airport since IIA’s operation

2 Gimpo Airport v Don Muang airport Cargo terminal Int’l Terminal 1 Domes.T erminal Int’l Terminal 2 Don-Muang Gimpo Layout plan

3 Air traffic statistics of Gimpo airport Passengers Cargo (tons) Movements 17,092,095 302,240 128,428 Year 2002 Year 2000 (before IIA opened) 36,727,124 1,874,228 236,272 Bangkok Int’l Airport (Year 2002) 32,182,980 1,034,132197,955

4 Overview of Gimpo Airport Before Incheon Airport opened International Terminal 1 International Terminal 2 Domestic Terminal Total Floor Area : 215,695m2

5 Gimpo Airport v Don Muang airport Cargo terminal Int’l Terminal 1 Domes.T erminal Int’l Terminal 2 Don-Muang Gimpo Layout plan

6 Transformation of Gimpo Airport After IIA opened (Mar 29, 2001) International Terminal 1 International Terminal 2 Domestic Domestic Terminal Commercial & International Commercial FEASIBILITY STUDY for using airport’s vacant building & land efficiently : Dec 1999 ~Aug 2000

7 Commercial Area International for emergency Electronic products sales center Remodeling of Terminal 2

8 Floor Area : 49,224 m2 Remodeling period : - Sep ’02 ~ Apr ’03 ( 7months) Date of opening : April 25, 2003 - about 2 years after IIA opened Remodeling of Terminal 2 Private Investment as long term contractor : 12 years

9 Remodeling of Gimpo Airport’s building Korea Airports Corp. & Government building Office building

10 Commentary for Don-Muang airport’s renovation schedule 1. Feasibility study for DonMuang airport’s land use plan until the 1/4 of 2004 2. Organizing task force team for implementing re-use plan of buildings by middle of 2004 3. Bid preparation and award (short/long term) from the end of 2004 to 3/4 of 2005 4. Start renovating of terminal building & etc : the first quarter of 2006

11 Gimpo Airport’s layout plan


Download ppt "Suvarnabhumi Airport Development CASE STUDY (3) 2003. 8. 15 KOICA(NESDB) Transformation of Gimpo Airport since IIA’s operation."