1 All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule

2 All CMS 30 May07 TSV2 News on the Machine Update on Triplets http://user.web.cern.ch/User/QuickLinks/Announcements/2007/LHCInnerTriplet_4.html From CERN Homepage and Fermilab Today. Proposed to add to each Q1 magnet and each Q3 magnet a set of four cartridges that can absorb the longitudinal force generated during the pressure test. The solution was presented to a team of experts during a review at CERN on April 24 and 25. Since then the design of the cartridge system has been refined and parts needed for the cartridges and their installation have been ordered. The installation of the cartridges in the Q1 and Q3 magnet of at least one inner triplet is scheduled to be complete in early June, in time for the next pressure test. DG, DDG and LHC Project Leader to meet soon. Most likely will be given information soon afterwards.

3 All CMS 30 May07 TSV3 CMS progress UX: 2 DT sectors in YB0 commissioned with cosmics. All 18 EB- SMs inserted, YB0 services installation ongoing (showing ~ 3 week delay). Started installing tracker radial cable trays this week and start cabling of S1 towards the end of this week/beginning next week. HF+ commissioned. Conducting a global run now SX: YB-1 commissioned using cosmics (almost done), RE-2 chambers mounted - testing and commissioning. Cabling of YB-2 will finish soon. RPC HV cabling end-June. Tracker: Cosmics data being taken. Started process of going cold last week. Taking cosmics at 10C. ECAL: EB- installed, 25 SMs integrated (electronics). 20 supercrystals mounted on ‘Dee4’. Over EE 2500 crystals delivered. Finalize schedule for final order (this week).

4 All CMS 30 May07 TSV4 SX: DT Commissioning YB-1 The Minus-end Muon Systems in SX5 being commissioned using cosmics

5 All CMS 30 May07 TSV5 UX: DT Commissioning YB0 Sector 12

6 All CMS 30 May07 TSV6 HF+ in UX Commissioned Bunch crossings, 1bx =25ns Eta towers Phi towers Average response of towers to LED signals Average LED event shape HF+ connected to FEDs in USC

7 All CMS 30 May07 TSV7 EB- Installation Completed (22 May)

8 All CMS 30 May07 TSV8 Tracker “Chilling Out” Thurs 24 May 18:00

9 All CMS 30 May07 TSV9 All 20 Supercrystals mounted on “Dee4”

10 All CMS 30 May07 TSV10 YB0 Services Installation

11 All CMS 30 May07 TSV11 Overall CMS Schedule: v35.3 March April May June July Aug. Sep. Oct. Nov. 1) Detector Installation, Commissioning & Operation First Global Readout Test Barrel ECAL Inserted Tracker Inserted Trigger/DAQ Ready for System Commissioning CMS Ready to Close 2) Preparation of Software, Computing and Physics Analysis HLT exercise complete Pre-CSA07 Computing Software Analysis Challenge 2007 Physics Analyses completed CSA07 All CMS Systems Ready for Data Taking

12 All CMS 30 May07 TSV12 Points for Discussion Discuss new optimized CMS schedule during MB of 11 June - also use for AR, CMS Week and CR (involve wide constituency) Annual Reviews: 13-15 June, agenda sent out this morning. CMS Week: 18-22 June, Plenary sessions in 2 parts. Under construction. SLHC: need to prepare the next steps. Formulate a proposal by June MB ? RPC_RE Workshop: 25, 26 June at CERN - invite all interested parties. SLIMOS shifts - several incidents point to the need to start such shifts - will now actively canvas for volunteers (must not be solely people usually busy at Point 5 or on other critical path activities) Publications Conference Committee Constitution MoA’s