1
NCSR “Demokritos” Institute of Informatics & Telecommunications CROSSMARC CROSS-lingual Multi Agent Retail Comparison Costas Spyropoulos & Vangelis Karkaletsis CROSSMARC Meeting, Paris, July 5-6, 2001
2
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris2 CROSSMARC 2nd meeting Main Goals: WP1: Collection tool specification, Corpus collection task, Ontology WP2: NER DTD, Monolingual NER components WP4: Overall processing stages Workplan by the end of the 1 st year (demo at the peer review meeting) ICN participation Consortium Agreement Management issues
3
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris3 CROSSMARC 2nd meeting – WP1 What has been done by month 4 (June) What has been done by month 4 (June) 1 st version of the collection tool including ICDC module and NCSR module Domain ontology by VeltiNet and NCSR Corpus for English and French by ICDC (needs to be evaluated)
4
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris4 CROSSMARC 2nd meeting – WP1 Schedule by month 7 (end of Sept. 2001) Schedule by month 7 (end of Sept. 2001) July 15: domain typology (the way online retail stores “interface” with the user), presentation layouts of product description pages (also a few statistics) - VeltiNet July 15: RTV and NCSR send urls to ICDC, ICDC sends English and French corpus July 30: specifications of the collection tool, schedule for the implementation of its components, evaluation methodology– ICDC, NCSR, VeltiNet July 30: NCSR announces the 1 st version of the annotation tool to the partners August 15: ICDC sends Greek and Italian corpus August 30: Final version of the annotation tool – NCSR, the annotation task starts for the 4 languages September 30: 2 nd version of the collection tool incl. better evaluation function, new access ways - ICDC, NCSR, VeltiNet September 30: NER annotation task ends
5
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris5 CROSSMARC 2nd meeting – WP1 Schedule from month 8 to month 12 Schedule from month 8 to month 12 October 15: specification of 2 nd domain October 30: report on learning techniques - NCSR November 30: 3 rd version of the collection tool (better performance, new access ways, products’ separation in the same page) – ICDC, NCSR, VeltiNet November 30: Partners send urls for the 2 nd domain to ICDC December 30: Evaluation results on the 2 nd domain urls, ICDC sends 2 nd domain product pages to the partners, Annotation task starts February 28: 4 th version of the collection tool (incl. some learning techniques), Annotation task ends
6
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris6 CROSSMARC 2nd meeting – WP2 What has been done by month 4 (June) What has been done by month 4 (June) 1 st version of NER DTD by EDIN and NCSR Schedule by month 7 (end of Sept. 2001) Schedule by month 7 (end of Sept. 2001) July 22: finalise NER DTD (taking into account Paris discussions)- EDIN July 22: what will be included in the monolingual NER specs for D2.1 – EDIN August 15: partners send NER specs to EDIN August 30: Draft D2.1 is sent to partners for comments – EDIN September 30: Final D2.1 to EC – EDIN
7
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris7 CROSSMARC 2nd meeting – WP2 Schedule from month 8 to month 12 Schedule from month 8 to month 12 October 30: report on first versions of the monolingual NER components November 30: report on first evaluation results December 30: 1 st integrated version January 30: 1 st integrated version with wrappers (for a small number of features) February 28: 1 st demo prototype
8
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris8 CROSSMARC 2nd meeting – WP3 What has been done by month 4 (June) What has been done by month 4 (June) First discussions on FE DTD Schedule by month 12 Schedule by month 12 September 30: specify the limited number of features for demo December 30: 1 st version of wrappers January 30: 1 st integrated version with NER February 28: 1 st demo prototype
9
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris9 CROSSMARC 2nd meeting – WP4 What has been done by month 4 (June) What has been done by month 4 (June) First discussions on overall architecture and interfaces Schedule by month 12 Schedule by month 12 September 30: concrete proposal on the end-user interfaces - mockup October 30: 1 st report on the architecture, Specify the integration methodology November 30: 1 st version of the interfaces December 30: 1 st version of D4.1 to partners for comments February 28: 1 st demo prototype, Final version of D4.1
10
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris10 CROSSMARC 2nd meetingWP5: D5.1 Project presentation Project web site Partners’ progress reports 1 st Quarterly management report Consortium agreement D5.2 Dissemination and use plan
11
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris11 CROSSMARC: budget Total Cost OwnContributionCommunityContribution NCSR667.837333.920333.917 VeltiNet275.401137.702137.699 EDIN417.9410417.941 RTV274.7840274.784 I-CDC648.751324.377324.374 ICN372.518186.259186.259 2.657.232982.2581.674.974
12
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris12 CROSSMARC Work Packages WPLeaderStartEnd WP1. Collection of on-line product descriptions ICDC118 WP2. Multilingual named-entity recognition and matching EDIN126 WP3. Multilingual and multimedia fact extraction NCSR1028 WP4. Prototype development and evaluation VeltiNet130 WP5. Management NCSR130
13
CROSSMARC 2nd Meeting, July 5-6, 2001, Paris13 CROSSMARC Person-months NCSRVeltiNetEDINRTVICDCICNTotal WP166476433 WP2120191712060 WP3170142015066 WP4101511531963 WP5232483242 Total682352573925264