Presentation is loading. Please wait.

Presentation is loading. Please wait.

Software project management (intro)

Similar presentations


Presentation on theme: "Software project management (intro)"— Presentation transcript:

1 Software project management (intro)
STEP WISE An approach to planning software projects

2 ‘Step Wise’ - aspirations
Practicality tries to answer the question ‘what do I do now?’ Scalability useful for small project as well as large Range of application Accepted techniques e.g. borrowed from PRINCE etc

3 ‘Step Wise’ - an overview
0.Select project 2. Identify project infrastructure 1. Identify project objectives 3. Analyse project characteristics Review 4. Identify products and activities Lower level detail 5. Estimate effort for activity For each activity 6. Identify activity risks 10. Lower level planning 7. Allocate resources 8. Review/ publicize plan 9. Execute plan

4 A project scenario Hardware/software engineering company (C++ language of choice) teams are selected for individual projects - some friction has been found between team members HR manager suggests psychometric testing to select team

5 Project scenario - continued
Software package to be used to test staff MS Access suggested as a vehicle for implementation usability is important - decision to carry out usability tests

6 Step 1 establish project scope and objectives
1.1 Identify objectives and measures of effectiveness ‘how do we know if we have succeeded?’ 1.2 Establish a project authority ‘who is the boss?’ 1.3 Identify all stakeholders in the project and their interests ‘who will be affected/involved in the project?’

7 Step 1 continued 1.4 Modify objectives in the light of stakeholder analysis ‘do we need to do things to win over stakeholders?’ 1.5 Establish methods of communication with all parties ‘how do we keep in contact?’

8 Back to the scenario Project authority Stakeholders
should be a project manager rather than HR manager? Stakeholders project team members to complete on-line questionnaires: concern about results? Revision to objectives provide feedback to team members on results

9 Step 2 Establish project infrastructure
2.1 Establish link between project and any strategic plan ‘why did they want the project?’ 2.2 Identify installation standards and procedures ‘what standards do we have to follow?’ 2.3. Identify project team organization ‘where do I fit in?’

10 Step 3 Analysis of project characteristics
3.1 Distinguish the project as either objective or product-based. Is there more than one way of achieving success? 3.2 Analyse other project characteristics (including quality based ones) what is different about this project?

11 Step 3 continued Identify high level project risks
‘what could go wrong?’ ‘what can we do to stop it?’ Take into account user requirements concerning implementation Select general life cycle approach waterfall? Increments? Prototypes? Review overall resource estimates ‘does all this increase the cost?’

12 Back to the scenario Objectives vs. products Some risks
use paper questionnaire then input results of the analysis? Some risks team members worried about implications and do no co-operate project managers unwilling to try out application design difficult to implement in MS Access Answer? - evolutionary prototype?

13 Step 4 Identify project products and activities
4.1 Identify and describe project products - ‘what do we have to produce?’ Usability testing A product breakdown structure (PBS) Selected subjects Testing arrangements Test results Change requests Booked machine Questionnaire design Completed questionnaire Analysis report

14 Products The result of an activity Could be (among other things)
physical thing (‘installed pc’), a document (‘logical data structure’) a person (‘trained user’) a new version of an old product (‘updated software’)

15 Products The following are NOT normally products:
activities (e.g. ‘training’) events (e.g. ‘interviews completed’) resources and actors (e.g. ‘software developer’) - may be exceptions to this Products CAN BE deliverable or intermediate

16 Product description (PD)
Product identity Description - what is it? Derivation - what is it based on? Composition - what does it contain? Format Relevant standards Quality criteria Create a PD for ‘test data’

17 Step 4 continued 4.2 document generic product flows Testing plan
Selected subjects Questionnaire design Booked machine Completed questionnaire Test results Questionnaire analysis Change requests

18 Step 4.3 Recognize product instances
The PBS and PFD will probably have identified generic products e.g. ‘software modules’ It might be possible to identify specific instances e.g. ‘module A’, ‘module B’ … But in many cases this will have to be left to later, more detailed, planning

19 4.4. Produce ideal activity network
Identify the activities needed to create each product in the PFD More than one activity might be needed to create a single product Hint: Identify activities by verb + noun but avoid ‘produce…’ (too vague) Draw up activity network

20 An ‘ideal’ activity Select subjects Plan testing Design questionnaire
Conduct tests Analyse results Draft change requests Book machine

21 Step 4.5 Add check-points if needed
Design module A Code module A Design system Design module B Code module B Test system Design module C Code module C put in a check point Design module A Code module A Design system Design module B Check-point Code module B Test system Design module C Code module C

22 Step 5:Estimate effort for each activity
5.1 Carry out bottom-up estimates distinguish carefully between effort and elapsed time 5.2. Revise plan to create controllable activities break up very long activities into a series of smaller ones bundle up very short activities (create check lists?)

23 Step 6: Identify activity risks
6.1.Identify and quantify risks for activities damage if risk occurs (measure in time lost or money) likelihood if risk occurring 6.2. Plan risk reduction and contingency measures risk reduction: activity to stop risk occurring contingency: action if risk does occur

24 6.3 Adjust overall plans and estimates to take account of risks
e.g. add new activities which reduce risks associated with other activities e.g. training, pilot trials, information gathering

25 Step 7: Allocate resources
7.1 Identify and allocate resources to activities 7.2 Revise plans and estimates to take into account resource constraints e.g. staff not being available until a later date non-project activities

26 Gantt charts Week commencing Jean-Paul Nita Percy Ali Franz Dylan
APRIL 2 MARCH 12 19 26 9 16 5 Jean-Paul Design module A Des. mod B Nita Code module A Percy Code module C Code module B Ali Design module C Design mod D Franz Code Module D Dylan Test module C

27 Step 8: Review/publicise plan
8.1 Review quality aspects of project plan 8.2 Document plan and obtain agreement Step 9 and 10: Execute plan and create lower level plans


Download ppt "Software project management (intro)"

Similar presentations


Ads by Google