Download presentation
Presentation is loading. Please wait.
Published byFelicia Franklin Modified over 9 years ago
1
Status of Radiation Protection Studies for the Linac4 beam dumps Joachim Vollaire DGS/RP
2
Outline List of beam dumps for L4 commissioning and operation Shielding for12 MeV beam dump Shielding and strategy for 50 – 100 MeV dump Status of main dump shielding analysis (160 MeV) Status of LBS/LBE dumps shielding analysis Conclusions EDMS 11732752L4 BCC meeting # 31, 24/22/2011
3
List of beam dumps for Linac4 EDMS 1173275L4 BCC meeting # 31, 24/22/20113 Temporary beam dumps for commissioning at different energies (12 MeV, 50 MeV and 100 MeV) Main dump shielding with new layout and operational scenario (160 MeV) LBS and LBE dumps (160 MeV) in the L4 transfer line (commissioning and measurements)
4
12 MeV beam dumps EDMS 1173275L4 BCC meeting # 31, 24/22/20114 12 MeV beam (proton instead of H - ) Average current 6.5 A (4.05x10 13 p.s -1 ) Operational scenario (4 weeks 12 h/day) @ 6.5 A (4.06e13 pps) Beam
5
Residual dose rate 12 MeV beam dump EDMS 1173275L4 BCC meeting # 31, 24/22/20115 5 mn cooling time 1h cooling time1day cooling time
6
50 MeV – 100 MeV beam dump EDMS 1173275L4 BCC meeting # 31, 24/22/20116 Re-location of the beam dump from the 50 MeV to the 100 MeV area Move the dump with part of its shielding to limit personnel exposure Best shielding material : lowest residual dose rate and activation of the surrounding structures Operational scenario: 1 Month of operation @ 800 W/1.6 kW for 50 / 100 MeV
7
Geometry and studied configurations (I) EDMS 1173275L4 BCC meeting # 31, 24/22/20117 Shielding on a “Table” Concrete bricks below the table (prevent tunnel activation) Shielding on table would move with the dump…
8
Geometry and studied configurations (II) EDMS 1173275L4 BCC meeting # 31, 24/22/20118 Steel (iron) good for high energy neutrons Borated poly. (5 %) high thermal neutron capture cross section Marble low activation, “shield” the shielding Shielding 1Shielding 2Shielding 3 Configuration 1SteelConcreteMarble Configuration 2SteelBorated Poly.Marble Configuration 3Concrete Marble Configuration 4SteelConcrete Configuration 5Borated Poly. Marble Configuration 6Steel Marble Configuration 7SteelMarble
9
Neutron spectra out of the shielding EDMS 1173275L4 BCC meeting # 31, 24/22/20119 Configuration 2 leads to the lowest number of neutrons escaping the shielding To confirm it is a good shielding looking at residual dose rate around the beam dump
10
Example residual dose rate (8 h cooling) EDMS 117327510 S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 1Configuration 2 Configuration 3Configuration 4 50 MeV commissioning
11
Example residual dose rate (8 h cooling) EDMS 1173275Meeting, Date11 S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 5Configuration 6 Configuration 7 50 MeV commissioning
12
Example residual dose rate (1 Week cooling) EDMS 1173275Meeting, Date12 S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 1Configuration 2 Configuration 3Configuration 4 50 MeV commissioning
13
Example residual dose rate (1 Week cooling) EDMS 1173275L4 BCC meeting # 31, 24/22/201113 S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 5Configuration 6 Configuration 7 50 MeV commissioning
14
Example residual dose rate (8 h cooling) EDMS 1173275L4 BCC meeting # 31, 24/22/201114 S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 1 Horizontal cut Configuration 2 Horizontal cut Configuration 3 Horizontal cut Configuration 4 Horizontal cut 50 MeV commissioning
15
Example residual dose rate (8 h cooling) EDMS 1173275L4 BCC meeting # 31, 24/22/201115 S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 5 Horizontal cut Configuration 6 Horizontal cut Configuration 7 Horizontal cut 50 MeV commissioning
16
Residual dose rate profile (1 day – 1 week) EDMS 1173275L4 BCC meeting # 31, 24/22/201116
17
Residual dose rate profile (1 day – 1 week) EDMS 1173275L4 BCC meeting # 31, 24/22/201117
18
Conclusions on shielding comparison EDMS 1173275L4 BCC meeting # 31, 24/22/201118 Configuration 2 best combination for short cooling times Weight ~ 5000 kg
19
Examples of use of Borated Poly and marble EDMS 1173275L4 BCC meeting # 31, 24/22/201119
20
Dose rate during transport EDMS 1173275L4 BCC meeting # 31, 24/22/201120 Low after week of cooling. Quick disconnection + shielding (lead) to “plug” the opening in the shielding
21
Dose rate after 100 MeV run EDMS 1173275L4 BCC meeting # 31, 24/22/201121 1 month @ 100 MeV + 1 week CT 1 month @ 50 MeV + 1 week CT
22
Status of main dump study EDMS 1173275L4 BCC meeting # 31, 24/22/201122 New operational scenario and core design New fellow since 01/10/2011 (Jan Blaha) working on dump shielding CoreCore + shielding (SS/BP/MB)
23
Some preliminary results available EDMS 1173275L4 BCC meeting # 31, 24/22/201123
24
Contact with RP colleagues in JPARC EDMS 1173275L4 BCC meeting # 31, 24/22/201124 M. Vretenar Chamonix
25
Status of LBE/LBS beam dumps EDMS 1173275L4 BCC meeting # 31, 24/22/201125 Gallery and adjacent building Access from Booster side Work carried out by H. Richter
26
Prompt dose calculations EDMS 1173275L4 BCC meeting # 31, 24/22/201126
27
Residual dose rate calculation and optimization EDMS 1173275L4 BCC meeting # 31, 24/22/201127 Residual H*(10)-rate [µSv/h] after commissioning ( 1h ) No optimization1 m deep dumpMarble plate Report being written
28
Conclusions EDMS 1173275L4 BCC meeting # 31, 24/22/201128 Good progress for the commissioning dumps (12 / 50 / 100 MeV) Main dump shielding still to be specified (assuming 1 core for the entire lifetime of the facility for the time being ?) LBS dump study being documented. LBE study to be performed….
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.