Presentation is loading. Please wait.

Presentation is loading. Please wait.

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.

Similar presentations


Presentation on theme: "Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed."— Presentation transcript:

1 Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed water to counting houses 2.cooling station transfer lines 3.stations construction Future works 4. VELO concentric lines construction 5. rack cooling and fire extinction network

2 1. Primary systems around barracks CRIOTEC -installation of pneumatic lines and actuators finished (cabling to valves and control components from DSS) -pressure tests performed successfully (one leak detected, connection repaired) -not fully tight valve changed today, system ready for operation, commissioning to TS/CV/OP asap Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

3 2. DC stations transfer lines under construction INEO ALPES -transfer lines for IT, TT, OT, RICH stations under construction, to be finished in week 43 (before the 28 th ) -piping to IT/TT safety chiller to be soon designed and installed according to same schedule -on LHCb demand: isolation valves on four lines installed on RB84 side, bypass dismantled on same side, brackets near to barracks stairs on RB86 modified -cavern wall on RB86 to be tidied up for pipes installation (neon light, cables)

4 3. DC stations construction INEO ALPES Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

5 4. VELO concentric lines construction SIMIND Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 -schedule: beginning Nov 28 th or Dec 05 th duration 10 working days -preliminary yard visit on 14/10 -PPSPS drawing up ongoing -requests to LHCb: crane truck with operator, 2/3 nights for pressure tests (pneumatic, 125 bar)

6 5. Rack cooling lines at mixed water, fire extinction network, chilled/mixed water pipes modification on RB84 IT to be drawn up Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 Fire prevention lines integration completed, on RB84 spurs almost defined, lines drawing up on RB86 priority. Tests on rack exchangers and Wiener power supplies ongoing (Detraz, Bobillier)

7 Others Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 - ventilation system for Muon station M1/3 design under definition, ES approval in 3 weeks, TS/CV to supply components, installation from Muon collaboration - CV works required in SX8/R-003 (007, 008) to be defined with F.Levrier - air conditioners maintenance around barracks performed by R.Mollay in week 42


Download ppt "Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed."

Similar presentations


Ads by Google