Download presentation
Presentation is loading. Please wait.
Published byWarren Harrington Modified over 9 years ago
1
PACS IHDR MPE, 12/13 Nov 2003 Overall Schedule1 Otto H. Bauer MPE Garching
2
PACS IHDR MPE, 12/13 Nov 2003 Overall Schedule2 AVM/CQM Schedule Areas of Concern Test Cryostat: 4K level temperature and hold time problem, still not at MPE Filters available, but no documentation: critical for PhFPU Mirrors: gold layer loose in 3 out of 13 lots, Astrium found no real reason 2.5 weeks delay of FPU integration PhFPU and Ge:Ga detector arrays on critical path PhFPU STM cryovibration at CSL failed: 2 broken Kevlar wires separate qualification program for PhFPU STM and modified Cooler STM (Titanium body) Grating STM cryoqualified, but CQM failed: loose spring washer several weeks delay Distribution Boards: several weeks delay due to misunderstanding between Project PA/QA and KT: poor manufact. quality possibly another 4 to 6 weeks delay Delivery to ESA: mid June 04, AVM WE two weeks earlier
3
PACS IHDR MPE, 12/13 Nov 2003 Overall Schedule3 Duration AVM ctd Test and CQM+AVM Instrument Integration
4
PACS IHDR MPE, 12/13 Nov 2003 Overall Schedule4 CQM ILT Programme ("Blue" means range of parameter settings reduced or test modified) F1.1FPU integration with test cryostat and OGSE3, alignment F1.2Electrical continuity check F1.3Functional test exercising all mechanisms, temperature sensors, sources and detector array read-outs F1.4Cool down to LHe F1.5Functional test exercising all mechanisms, temperature sensors, sources and detector array read-out Q2.1FPU Thermal behaviour Q2.2Focus definition Q2.3Relative alignment check spectrometer vs. photometer arrays after vibration respectively thermal cycling Q2.4sensitivity Q2.5spatial performance Q2.6spectral performance E1.1 Instrument EMC tests C3.1Absolute flux calibration, linearity C3.2Flat field C3.3Point spread function C3.4Distortion, grating alignment C3.5Relative Spectral Response Funct. C3.6Wavelength-calibration using TUFIR replaced by vapour absorption cell C3.7Instrumental profile (grating) measured with TUFIR replaced (however, some initial profile information from absorption line measurements are planned. C3.8Ghosts (search for spectral ghosts) TUFIR only, maybe Ge laser? (C3.9)Stray light (ghosts) with Ge laser? C3.10Detector time response, stability (C3.11) Definition of PACS pass bands with TUFIR (not possible with Ge laser) (C3.12) AOT try out
5
PACS IHDR MPE, 12/13 Nov 2003 Overall Schedule5 Duration CQM+AVM Instrument Test Sequence
6
PACS IHDR MPE, 12/13 Nov 2003 Overall Schedule6 PFM Schedule FPU structure manufacture started Early delivery of several subunits Areas of Concern –BOLC and Ge:Ga detector arrays on critical path oILT: PhFPU FM will be tested with BOLC QM2 oBOLC FM will only be delivered in Sep 05 Delivery to ESA: end June 05
7
PACS IHDR MPE, 12/13 Nov 2003 Overall Schedule7 Duration PFM Instrument Integration and Cryovibration
8
PACS IHDR MPE, 12/13 Nov 2003 Overall Schedule8 Duration PFM Instrument Test Sequence
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.