All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 07/01/2013
2
RFQ Injector Line (RIL)
3
RIL Highlights – Thin corrector Large exit angle Correctors are running with high current, predominant vertically, at the downstream end of RFQ in order to maximize beam transmission Thanks to BNL for the design and FNAL/TD for building the correctors Corrector installed early June Modest gain in beam current Increased extractor voltage by 1.5kV Yielded 11% more beam at entrance of Linac F.G. Garcia AEM - PIP Report 07/01/2013 Thin corrector Contribution: C.Y. Tan
4
RIL Highlights – Source Swap F.G. Garcia AEM - PIP Report 07/01/2013 FNAL/RIL design posses two sources located side-by-side on a slide platform to allow for easy and quick swap First swap: June 17 Duration: ~ 7 hrs Second swap: June 26 Duration: ~1hr Contribution: D. Bollinger
5
PIP – Linac Activities
6
Linac 200 MHz RF Power System Modulator Upgrade 35kV, Marx-topology modulator to drive triode (or MBK) SLAC – Two cell test stand Simulate the ripple due for 2 cells both in phase (11%) and out of phase (0.9%) Compare 2 cell out-of-phase simulated to measured ripple (1.1%) Determine via simulation the ripple for 5 vernier cells (0.23%) F.G. Garcia AEM - PIP Report 07/01/2013
7
Modulator Upgrade (cont.) 35kV, Marx-topology modulator to drive triode (or MBK) AD/EE – Working on building 9 cell Marx Modulator Able to create any arbitrary wave shape, from trapezoid to square In the future: determine rising and falling edge ripple Built prototype discrete control system Testing second prototype Marx cell under normal load conditions (350 Amps) under short circuit (2000 Amps) Continue fabrication of 9 cell Marx Modulator Linac 200 MHz RF Power System F.G. Garcia AEM - PIP Report 07/01/2013
8
Linac 200 MHz RF Power System MBK201FERMI 7MW pulsed klystron to operate at 200 MHz for use as a power source for the DTL Linac Procurement Received approval from directorate to proceed with the MBK201 prototype New cost/schedule was developed between Fermi and seller Current awaiting PO to be accepted Estimate to be complete this week Activities Initiate gallery floor plan layout in collaboration with AD/MSD Drafter Dept. F.G. Garcia AEM - PIP Report 07/01/2013 Courtesy: D. Hurd
9
Linac Utilities Power Distribution L1 transformer Continue with prep work for the installation of L1 transformer. Electrical conduit relocation complete Lead abatement & relocation steel beam complete Hatch location F.G. Garcia AEM - PIP Report 07/01/2013 Tentative delivery date: Week July 15 th.
10
Linac Laser Notcher Reduce losses in Booster generated by the creation of the notch 3D printer model of the vacuum interface and the optical cavity Good progress with beam shaping optics F.G. Garcia AEM - PIP Report 07/01/2013 Beam size as shown ~ ¾ mm x 5 mm Design beam size 1 mm x 6 mm VerticalHorizontal
11
PIP – Booster Activities
12
Booster Utilities Old Y-BE2 40+years old – beyond expected lifetime Oil-cooled transformer Questionable operation conditions for quite a while o May/2012 investigation revealed noisy current output, over temperature operation conditions… Replaced with “old spare” ~ 1 year ago F.G. Garcia AEM - PIP Report 07/01/2013 New Y-BE2 Installed May 17-18, 2013 Air-cooled transformer Remotely monitor & control Breakers are modular (smaller spare inventory) Improved monitoring (access to currents, voltages, harmonics )
13
Booster Booster shielding assessment Studies concerning beam loss profile and radiation measurement through penetrations were done Discussions and data analysis underway Booster Notcher Progress with time in and commissioning F.G. Garcia AEM - PIP Report 07/01/2013 6 4.5 3 1.5 0 E12 12T - $17 6 4.5 3 1.5 0 E12 12T - $17
14
Booster RF system Cavities Refurbishment 7 of 19 cavities have been refurbished BRF 1,3,5,6,7,8,15 BRF11 has issues with heating on the tuners Need to be re-addressed for 15 Hz operations F.G. Garcia AEM - PIP Report 07/01/2013 Booster Cavity Work Refurbished (15Hz) SS Prototype SS Upgraded Cavity Removed Stats: Last refurbishment : 9.4 weeks last 3 cav. : 10.5 weeks Courtesy: K. Gollwitzer