The Schoharie Creek Thruway bridge collapse Group 18 Karen McMorrow David O’Brien Clare Whitely
2
Introduction Design Started in 1949 Completed in October 1954 165m span comprising of 5 simple spans 165m long bridge comprising of 5 simple spans 1955: 100 Year Flood Collapsed in 1987
3
The bridge collapsed during an estimated 50year flood in 1987 Pier 3 collapsed first Followed instantly by spans 3 and 4 This led to the collapse of pier 2 and span 2 Finally 2 hrs later, Pier 1 and Span 1 shifted.
4
Scour: The removal of sediment from a streambed due to water erosive action
5
Shallow footings Sheet-piles removed Riprap was not adequate Foundations on erodible soil Could not resist scour
6
Always perform regular maintenance and inspections Need for clear design objectives Sheet piling should have been left in place Importance of footing depth Design for rare events
7
10 lives were lost in this tragedy, this could have been prevented with regular inspections, better communication and adequate erosion protection