Presentation is loading. Please wait.

Presentation is loading. Please wait.

CASUALTY LOSS RESERVE SEMINAR SESSION 2 SEPTEMBER 10, 2001 CONTRACT SURETY CASE RESERVES STEPHEN J. TRECKER SENIOR VICE PRESIDENT XL SURETY PHILADELPHIA,

Similar presentations


Presentation on theme: "CASUALTY LOSS RESERVE SEMINAR SESSION 2 SEPTEMBER 10, 2001 CONTRACT SURETY CASE RESERVES STEPHEN J. TRECKER SENIOR VICE PRESIDENT XL SURETY PHILADELPHIA,"— Presentation transcript:

1 CASUALTY LOSS RESERVE SEMINAR SESSION 2 SEPTEMBER 10, 2001 CONTRACT SURETY CASE RESERVES STEPHEN J. TRECKER SENIOR VICE PRESIDENT XL SURETY PHILADELPHIA, PA

2 CLAIMS PROCESS Investigation of the Financial Condition of the Principal  Reasons to Investigate Claims Made Against the Bonds by the Beneficiaries of the Bonds Requests for Financial Assistance Requests from Underwriting

3 CLAIMS PROCESS Investigation of Surety’s Liabilities Under Bonds  Performance Bonds ”Excess” Completion Cost Delay Damages (Actual & LD’s) Marginal Legal, Architectural and Engineering Fees  Labor and Material Payment Bonds Replace Lien Rights on Public Projects Indemnify Subcontractors, Suppliers, Laborers Delay Damages

4 CLAIMS PROCESS Methods of Satisfying Performance Bond Obligations  Financing - Infuse Capital to Avert a Default  Takeover - Become the Contractor of Record  Tender - Arrange for Others to Complete  Owner Completion - Allow Owner to Complete  Deny Liability - Litigate

5 CLAIMS PROCESS Labor and Material Payment Bond Claims  Subcontractors, Suppliers, Laborers, Unions  Delay Damages  Claim for Extra Work  Pay if Paid  Ratification

6 CLAIMS PROCESS Investigation Summary  Amount of Money Left in Contracts  The Estimated Cost to Complete the Work  The Amount of Unpaid Subcontractors and Suppliers  Quality of Work  Condition of Books and Records  Salvage Possibilities

7 CLAIMS PROCESS Basic Case Reserve Calculation Contract 1 Contract 2 Original Contract Price$1,000,000$2,000,000 Approved Change Orders $125,000 $100,000 Revised Contract Price$1,125,000$2,100,000 Paid by Obligee to Principal $625,000 $500,000 Contract Balance $500,000$1,600,000 Cost to Complete the Work $700,000$1,300,000 ($200,000) $300,000 Labor and Material Payment Bond Claims $175,000 $100,000 Surplus/Deficit ($375,000) $200,000 Contingency %

8 CONTRACT SURETY RESERVES ISSUES Accuracy - Adequate and Not Redundant Gross or Net - Contract Balances and Cash Collateral Date of Loss - Insolvency of Principal

9 ACCURACY OF RESERVES Completion Method Issues  Financing Cost to Complete is Principal’s Optimistic Estimate Variable Home Office and Field Overhead Employee Morale Managerial/Technical Weaknesses Ability and Willingness of Obligee to Pay Timing Differences in Cash Flow

10 ACCURACY OF RESERVES Takeover  Must Collect the CB’s  Ability to Pay  Bond Penalty Tender  Clean, Pay Net Damages Owner Completion  Clean, but Lose Control, Pay Net Deny Liability  Litigation  ALAE  Owner Damages

11 ACCURACY OF RESERVES Contract Payment Methods  Unit Price Contracts Quantities are Only Estimated Until Final Completion Excavation Contracts - Cubic Yards Sewer & Water Pipe - Linear Feet Over/Under Runs Not Known Until Final Completion and Measurement  Cost + Fixed Fee or % Final Cost is Not Known Until Final Completion Stairstepping as Costs Increase

12 ACCURACY OF RESERVES Cost + Fixed Fee with GMP  GMP Moves with Remedial Work  GMP Close to Fixed Price Fixed Price  Remedial or Corrective Work is Cost +  Successive Defaults

13 ACCURACY OF RESERVES Quality of Principal’s Work  Construction Defects Patent Latent –Not Included in Completion Price –May Require other Work to be Torn Out and Re-Done –Time Sensitive (Delay Damages)

14 ACCURACY OF RESERVES Integrity of the Principal  Access to Book and Records  Access to Key Project People  Candor of Management and Technical People  Admission of Errors and Problems  Fraudulent Transfers

15 ACCURACY OF RESERVES Bankruptcy  Time - Automatic Stay  Trustee Fighting for CB’s  Assumption/Rejection of Contracts  Fraudulent Transfers

16 ACCURACY OF RESERVES Condition of Books & Records  A/P Posting  Accurate Updated Cost Records  Legitimate Back Charges (A/P Reduced)?  Held Checks (A/P and Cash Reduced)?  Change Orders Only in System if Approved

17 ACCURACY OF RESERVES Size of Contractor  Geographical Diversification of Contracts  Complexity of Work  Number of Contracts in Process  Overhead

18 GROSS OR NET Contract Balances Collateral Completion Options Cash Flow Negative Reserves RCP$1,000,000 Paid by Obligee to Principal $700,000 Contract Balance $300,000 Cost to Complete $500,000 $200,000 Labor and Material Payment Bond Claims $150,000 Net Reserve $350,000

19 DATE OF LOSS ISSUES Loss is Not Fortuitous Risk is Insolvency Claim File Opened Before Date of Loss Reserve Date When is Principal Solvent Systems Problems, Effective Date and Expiration Date of the Bond


Download ppt "CASUALTY LOSS RESERVE SEMINAR SESSION 2 SEPTEMBER 10, 2001 CONTRACT SURETY CASE RESERVES STEPHEN J. TRECKER SENIOR VICE PRESIDENT XL SURETY PHILADELPHIA,"

Similar presentations


Ads by Google