MediaCentre Planning Workshop Monday January 14 th, 2013.

Similar presentations


Presentation on theme: "MediaCentre Planning Workshop Monday January 14 th, 2013."— Presentation transcript:

1 MediaCentre Planning Workshop Monday January 14 th, 2013

2 Agenda of the day - Monday Monday, 14 Jan Day 1 10:00-12n 2 hrsIan/Andy/Eric/MichaelWorkshop setupCore Team Noon -1p Lunch Brought in 1-3p 2 hrsBob B/Mark G Project Overview, Objective & Goals, Week Overview (for upper mgmt, Programming) Core team, LA & UK Mgmt team, Programming (UK,CE,SP,AF, RU?) 3-3:15p Break 3:15-4:00p.75 hrsMichaelRFP Process Overview and Discussion Core team, LA & UK Mgmt team, Programming (UK,CE,SP,AF, RU?) 4-4:15p Break 4:15-5:45p 1.5 hrsEric/Kelly/Ian Library & Acquired Program setup within the BMS/MAM (capture specific data requirements) Programming and Core Team 5:45-6:30p.75 hrsCore TeamRest of week review - RecapCore Team 6:30p END OF SESSION

3 Presentation Place Holder Project Overview, Objective, & Goals

4 Break

5 MediaCentre RFP Where we are, Where we are going

6 Agenda Where we are now Where we have been RFP Overview What’s not in the RFP Selection Process Team Discussion Report Back Wrap-up

7 Many details will be settled during detailed design after Greenlight. However, we need to wrap up some lose ends before greenlight Final Vendor Scope (RFP) & Selection and Refine Overall Project Scope Final Vendor Scope (RFP) & Selection and Refine Overall Project Scope Project Greenlight Launch Project & Detail Design Where we are now… Question for this Session: Do we have everything we need to move forward with the vendors to do a final selection and final cost? Question for this Session: Do we have everything we need to move forward with the vendors to do a final selection and final cost? MediaCentre Requirements (within RFP scope) MediaCentre Requirements (within RFP scope) Business Systems Requirements (outside RFP scope) Business Systems Requirements (outside RFP scope)

8 How the MediaCentre RFP relates

9 The RFP Story… So Far…  March 2012 – TSL consultant provides Workflow and Content Process analysis, content flow numbers, and recommendations.  June 2012 – RFP written and distributed  January 2013 – Involve Procurement, Legal, Risk Management, InfoSec  January 2013 – Validation & Review of Functional Design  Jan-Mar 2013 – Decision Process to select vendor Current Goal: Decision by April 1 st Analysis Mar 2012 RFP Release Jun 2012 Final Decision Process Jan – Mar 2013 Final Selection Apr 2013

10 Importance of the Worklows The value of the workflows to the effort cannot be understated. The entire RFP and wider effort is based on these. Huge thanks to the entire team for their time, knowledge, and effort to make these comprehensive touchstones.

11 Initial Downselection Sony Professional Services and TSL both are capable of doing the project successfully Initial responses returned Some vendors excluded due to high costs and poor technical solution RFP distributed Went out to 5 vendors (Sony Professional Services, TSL, Globecomm, BCE, & IBM) Who was given the RFP

12 RFP Overview - 5 Major Areas in the RFP Technical Buildout Technical Buildout Content & Workflow Management System (Workflows) Content & Workflow Management System (Workflows) Regional Requirements Project Management Requirements Project Management Requirements Supporting Information A compilation of specific technical requirements, workflow diagrams, functional specifications, scenario descriptions, planning assumptions, and project guidelines.

13 Reference & Test Signals Status & Alarm Monitoring Signal Monitoring & Measurement Reference & Test Signals Status & Alarm Monitoring Signal Monitoring & Measurement Technical Buildout – Central Technical Area “Things that bolt into racks and have LED lights” Comms/TalkbackExternalFeedsComms/TalkbackExternalFeedsAutomated QC QCSignalRoutingAutomated SignalRouting Disk & DatatapeStorage With HSM Transcoding Disk & DatatapeStorage With HSM Transcoding Technical Buildout Technical Buildout

14 Technical Buildout – Key Items 6 New QC/Version Edit RoomsNew Traffic Area for 8 people New Playout Area for 3 people Technical Buildout Technical Buildout

15 Technical Buildout – Key Items New Storage Infrastructure 180 terabytes of spinning disk storage 2.1 petabytes of datatape storage New data network Approx 1 TB inbound data per day Transfer of 1.25TB of new content to playout per day 365 GB of content to non-linear platforms per day Extensive Transcoding Capabilities Approx 1 TB of transcoded data created per day Technical Buildout Technical Buildout

16 Technical Buildout – Key Items Existing OAP Edit Suites/Seats Existing Graphic/Audio/VO Rooms Post areas will remain connected to their own dedicated shared storage. The CWM system will connect and help manage the existing post production areas to improve the process workflow. Technical Buildout Technical Buildout

17 CWM helps manage all aspects of preparing content for air. Content and Workflow Management System Ingest Voiceover QC Playout Distribution Localisation Compliance On-Air Graphics On-Air Graphics Promo Production Content & Workflow Management System “Getting the raw content ready for air” Content & Workflow Management System (Workflows) Content & Workflow Management System (Workflows)

18 CWM Key features and benefits Automates transcoding to needed formats Central tracking of all assets Common system for all content preparation Automation of file movement Coordination of the QC process Manages ingest of all files from the variety of sources Push to playout systems Direct integration with Vision/BMS/Landmark Content & Workflow Management System Content & Workflow Management System (Workflows) Content & Workflow Management System (Workflows)

19 Regional Requirements “What happens in Budapest & Madrid” Content preparation for linear & digital would occur at the MediaCentre, as requested by channel office personnel using the CWM Opportunity to share content and resources across the region Standardized workflows in place at channel offices managed by the CWM Regional Requirements

20 Project Management Requirements “Best Practices and doing it the Sony Way” Supporting Information “Large amounts of complicated workflows and spreadsheets” Program and Management RequirementsStandards, Formats, & SpecificationsConsulting/Design RequirementsInstallation Requirements Volumetric information on Program, Commercial, and Promo elements Project Management Requirements Project Management Requirements Supporting Information

21 Tweaks to plan not reflected in the RFP Majority of MediaCentre equipment & racks to be hosted at a datacenter location Removed playout monitoring/DR playout suite Playout centres will remain in London The Singapore transition is delayed Various changes to routing, videotape equipment, multiviewer, and talkback capability modifications Not In RFP

22 What’s not in the RFP Business Systems / SPE Enterprise Systems Detail GPMSEAGL/DMRCineShareDigital BackboneVisionBroadcast MasterLandmarkCrackleOver The Top MediaCentre (within the RFP) Content Workflow Management Technical Buildout MediaCentre is part of the larger effort toward improvement. Multiple interfaces with existing systems are required but this effort is intentionally not in the RFP. Not In RFP

23 Implementation Partner Selection Approach Current Decision Date: April 1 st Provide a Transparent, objective, fact driven approach Utilize RFP response evaluation tools and methods (see next page) Involve other key Sony resources such as: Procurement, Legal, Risk Management, Information Security

24 DRAFT: Selection Process Going Forward Identifies requirements to be evaluated Team members complete scorecard Some experts on specific areas may not complete entire scorecard Rates requirements on a 0-4 scale 4.0 Excellent / Exceeds Expectations 3.0 Good 2.0 Average / Meets Expectations 1.0 Fair 0.0 Poor / Does Not Meet Expectations Scores averaged and weighted Generates a more consensus driven evaluation Helps identify show-stopper issues Avoids Bias Scorecard Tool Finalize scope changes Document RFP amendments Involve Procurement, Legal, Risk Management, Information Security Develop scenario & use test cases Develop evaluation requirements Contact vendors Present amendments Solution Demos Review Responses Utilize Scorecard Tool

25 EXAMPLE: Scorecard Method – A Tale of Two Toasters CategoryWeightCommentsRatingScore 1Size of toaster20.0Average2.010.0 2Controls20.0Good3.015.0 3Speed of toasting20.0Rapid3.015.0 4Browning20.0Uneven1.05.0 5Price of toaster20.0Average2.010.0 Total (Actual)100.055.0 Total (Possible)100.0 Percentage/Weighted Score55.0% CategoryWeightCommentsRatingScore 1Size of toaster20.0Small3.015.0 2Controls20.0Good3.015.0 3Speed of toasting20.0Average2.010.0 4Browning20.0Superb4.020.0 5Price of toaster20.0High1.05.0 Total (Actual)100.065.0 Total (Possible)100.0 Percentage/Weighted Score65.0% Toaster #1Toaster #2

26 Team Discussion What was addressed well in the RFP? What areas of the RFP would benefit from additional clarification? (to allow us to accurately scope the project for Greenlight and to write accurate SOWs with the selected Vendor?) – What sections would you want to make sure address in more detail this week? – What assumptions were made that you think we should revisit or were not addressed – What critical information or workflow process are we missing? What do we risk if we don’t get this additional detail What other Sony groups can benefit from the MediaCentre project and need to be included? – How do you see them being benefited? What are your key points about how to best move the selection process is conducted going forward? – What do you want to make sure happens? – What do you believe will be the key differentiating selection criteria?

27 Report Back What was addressed well in the RFP? What areas of the RFP would benefit from additional clarification? (to allow us to accurately scope the project for Greenlight and to write accurate SOWs with the selected Vendor?) What other Sony groups can benefit from the MediaCentre project and need to be included? What are your key points about how to best move the selection process forward?

28 Wrap-up and Review What do we need to address in the RFP What of these additional questions are can be addressed by the

29 Break

30 LIBRARY & ACQUIRED PROGRAM SETUP WITHIN THE BMS/MAM

31 Introduction – Library & Acquired Program setup within the BMS/MAM Programme Setup within the proposed workflow.

32 Overview – Library & Acquired Program setup within the BMS/MAM Key areas regarding setup and the BMS(Vision) – Contracts & Rights – Programme Data Currently Held in BMS – Interfaces

33 Contracts & Rights – Library & Acquired Program setup within the BMS/MAM Contracts & Rights – Data entered by different people dependant on channel target region. Africa – London Based Acquisitions Manager Eastern Europe – Budapest based Acquisitions Team Germany – Director of Programming & Acquisitions UK, Italy, Baltics, Western Europe & Middle East – London Based Schedule Managers – Acquisition Managers & Programme Managers provide the details of the deal in a grid to those above and traffic between 1 year & 3weeks from 1st TX. This timeline differs as some regions confirm deals closer to TX than others. – Contracts are entered once deals have been confirmed (often before the terms and rights have been finalised). Data held in Vision Contract – Contract Reference – Contract Type (Acquired etc) – Contract Status (New, Signed, Expired) Rights – License Start Date – License End Date – Allowed Number of Plays – TX per Play – Transmission Period

34 Programme Data – Library & Acquired Program setup within the BMS/MAM Programmes, Episodes Versions & Materials data is entered into Vision by the Traffic team. High level Programme data is provided by the person who closes the deal and Episode level is taken from the internet IMDB, Wikipedia etc. Mandatory Programme Data fields are: -Programme Title -Programme Status -Slot Duration -Programme Type -Episode Title -Episode Number -Default Version -Version Title -Material Part -Material Barcode/TX ID -Material Timecode & Durations Other information that is currently entered includes: -Titles (for EPG Listings) -Genre -Billings & Synopsis -Cast & Credits -Aspect Ratio values -Source details -Certification -Classification

35 Programme Data Continued – Library & Acquired Program setup within the BMS/MAM Majority of data entered at Programme Level filters down to Episode and Version Level. All Material data is entered at the Version Level. Vision can also hold Subtitle, Dubbing and Music information against programmes and episodes however this is not currently utilised. There is currently no Series Level included within Vision however there is an enhancement planned to add this.

36 Interfaces – Library & Acquired Program setup within the BMS/MAM Interfaces -Playlists: Built for playout/automation purposes contain minimal metadata. -Break & Spot: Integration point with ad sales systems for the importing of 3 rd party commercial data. -Listings: Used for EPG & Web Reports, more flexible point of export but doesn’t contain access to all metadata. Known performance issues when pulling larger ranges of data. -VIL: Not currently used in EMEA but used successfully in LATAM. Access to 90% of data however can impact on production performance.

37 Questions

38 Agenda for the rest of the week Tuesday, 15 Jan Day 2 9:00-9:15a.25 hrsCore TeamOverview of the dayProgramming and Core Team 9:15-11:15a 2 hrsEric/Ryan/Ian/Kelly Business Systems overview (data movement) - Vision / Landmark / Broadcastmaster / GPMS / EAGL / Digital Networks / B2B Core Team, Scheduling, Traffic 11:15-11:30a Break 11:00-1:00p 2 hrs Adam/Andy/Gary B/Mark J Spencer Non Linear + VOD/OTT/Digital - Metadata structure - delivery process to CDN - Industry OTT trends/strategy Programming, scheduling and Core Team 1:00 -2:00p Lunch Brought in 2:00-4:00p 2 hrsAdam/AndyProgram Ingest / Import WorkflowProgramming, traffic and Core Team 4:00-4:15p Break 4:15-6:00p 1.75 hrsAdam/Andy Technical QC & Version Creation & ComplianceProgramming, traffic and Core Team 6:00-6:30p.5 hrsCore TeamCore Team RecapCore Team 6:30p END OF SESSION Wednesday, 16 Jan Day 3 9:00-9:15a.25 hrsCore TeamOverview of the dayCore Team 9:15-10:00a 0.75 hrsCore Team Project Overview, Objective & Goals, Week Overview (for OAP, Scheduling, Traffic) Core team, OAP, Traffic, Schedulers (UK,CE,SP,AF, RU?) 10:00-10:15a Break 10:15-11:15a 1 hrAdam/Andy Program Language Workflow & Metadata Localization Programming, traffic and Core Team 11:15a-12:15p 1 hrAdam/AndySubtitle Workflow & Metadata LocalizationProgramming, traffic and Core Team 12:15-1:15p Lunch Brought in 1:15-3:15p 2 hrsAdam/Denes/JM/Eva C Ad sales integration into MC system (including asset delivery) - UK/Spain/Budapest OAP, Traffic, Scheduling & Core Team 3:15-4:45p 1.5 hrsJess/Adam/AndyOAP, On-Air Graphics, Presentation items workflowOAP, Traffic, Scheduling & Core Team 4:45 -5:00p Break 5:00-6:00p 1 hrAdam/AndyRECAP: Linear TX assets to playout vendors 6:00-6:30p.5 hrsEric/Ryan RECAP: Data Movement Overview - Vision / Landmark / Broadcastmaster / GPMS / EAGL / Digital Networks / B2B Core Team, Scheduling, Traffic 6:30p END OF SESSION

39 Agenda for the rest of the week Thursday, 17 Jan Day 4 9:00-9:15a.25 hrs Overview of the day 9:15-10:45a 1.5 hrsMichael/Andy/Adam Recap and Prioritization of Functional / Workflow Implications / Downstream Data / Potential show- stoppers Core Team 10:45-11:00a Break 11:00-12:30p 1.5 hrsAdam/Jess/Andy/Mark G Storage volumetric validation - Planning Assumptions Overview-storage/archive, etc Core Team 12:30-1:30p Lunch Brought in 1:30-2:30p 1 hrMark A/Paul A Infrastructure Overview - Business Continuity discussion Core Team 2:30-4:30p 2 hrsEric/Ryan/Kelly/Ian Content Organization and Content Identifiers "deeper-dive" (internal & external IDs) Core Team 4:30 -4:45p Break 4:30-6:30p 2 hrsMark A/Spencer/Glen/Ryan Application, Systems & Infrastructure Overview- concept, App functional architecture - landscape - how systems will "talk" - Harris status/roadmap Core Team 6:30p END OF SESSION Friday, 18 Jan Day 5 9:00-9:15a.25 hrs Overview of the day 9:15-11:00a 1.75 hrsMark G/Ryan/team Transition Planning and Support Organization (what ops will look like in the MC world) - dual running period Core Team 11:00-11:15a Break 11:15-12:30p 1.25 hrsEric /Mark G/MichaelScope Changes and Vendor ImplicationsCore Team 12:30 -1:30p Lunch Brought in 1:30-2:00p.5 hrsChris R Pilot and POC Opportunities / Interim In-house - parking lot, brainstorming session Core Team 2:00-3:30p 1.5 hrsEric/Mark G Budget & Schedule Overview, Cost, right-sizing Discussion Core Team 3:30-5:00p 1.5 hrsEric/Mark G Overview of Project Benefits - Next Steps:Scope, RFP, Greenlight, follow-up homework, deliverables / Wrap-up Core Team/UK Mgmt team 5:00p END OF SESSION

40 Team Feedback What went well – Interaction after overview was good – Productive day and good engagement – List of terms What we can improve – Manage the timing and communication – Nibbles for breakfast – Quick intro (tomorrow) – Name cards out – Name list printed out – Do we have all of the right people in the room What we need to follow-up on …. – List of questions - Include and questions raised today for tomorrow’s sessions – Make sure that everyone understands the project (both in and out of scope) – Find a home for business process questions – Ongoing feedback from now to the broader group (Maybe monthly update) – Pub tomorrow!!!!!!! – Probably need a follow-up at some point on the earlier side to test drive some of the system (conference room pilot or prototyping) – Set-up sharing folder – Send validation to Kate and Lyle about the key deliverables (regroup) What we need to manage – Scope creep and expectations – The concern that the media center will be more complicated then what they do today – make sure people understand that we don’t plan in create double entry – Continue to facilitate the buyin and inclusion of the broader team – Careful with the term bespoke – Help drive the confidence in the project delivery