M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.

Similar presentations


Presentation on theme: "M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be."— Presentation transcript:

1 M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be reinstalled when alignment fibers in Alignment system Installed Sept-Oct as parts arrive Gas system installation beginning, expect completed by end of Sept. HV distribution system In fab, install with FEE Magnet buss modification In-progress, by Charlie. Needs to be complete by ~October Manpower required Couple hours for St. 1

2 M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status NORTH ARM: Necessary to begin work this shutdown if we want it to be ready for data taking by 2002 Work required: Magnet preparation-few months of work slated for this shutdown Chamber installation - 2001 shutdown Status of work for this shutdown: Drawings for templates for magnet drilling completed by mid October Chambers Designs completed Procurement of parts beginning now Expect completed chambers by Summer 2001

3 M. Brooks DC Meeting, 15-Sep-00 MuTr FEE Status--Assembly Hall SOUTH ARM: Already completed cable tray installation internal support structure installation test-installation of most of the CRAs scaffolding installation/fixes test-installation of St. 1 FEE plate prototype mount of Glink/Clink crates Rack platform installed Racks filled and stands completed (LV, HV, calibration system, slow controls, ARCNet hub, patch panel, … all ready) In progress: Production of all Glink/Clink mounts Plumbing and power for racks Plumbing for FEE cooling water and dry air To Come: Installation of populated CRAs and FEE plate, cable routing, testing

4 M. Brooks DC Meeting, 15-Sep-00 MuTr FEE Status--Assembly Hall SOUTH ARM: Manpower required Couple weeks of crane, tech support (Ray) to install CRAs inside magnet Day or two to install Station 1 FEE plate Physicists, students run cables, debug, …

5 M. Brooks DC Meeting, 15-Sep-00 MuTr FEE Status Mechanical Hardware All chassis, CRAs, Station 1 FEE plate assembled, plumbed and pressure/leak tested Ready for board installation and testing Test stands Test stands for several different board types essentially complete Test plans for stuffed CRAs, FEE plate completed Boards and cables All board orders out Backplane--first item received and go ahead given for full production 8-Sep. Should receive full production Oct. 6 Control Board--20 boards already received and tested o.k. Full production expected Sep. 29 CROC--36 boards shipped, full production expected Sep. 22 Glink/Clink boards--first items expected next week full production expected Oct. 20 Analog cables--already received 480, full shipment by Nov. 1 LV cables--fabricated and tested Glink/Clink cables--expected First CRA expected complete end of Sept / beginning of Oct All electronics completed end of November--Still expect to be able to meet this deadline, but no contingency