Download presentation
Presentation is loading. Please wait.
Published byPhillip Woods Modified over 9 years ago
1
US Army Corps of Engineers BUILDING STRONG ® Value Engineering the Termination of the Blue River Flood Conveyance Channel Alan Schlindwein, PE US Army Corps of Engineers Kansas City, Missouri June 14, 2012 Robert Prager, PE Strategic Value Solutions, Inc Independence, Missouri
2
BUILDING STRONG ® Battle of Westport AKA: The Gettysburg of the West
3
BUILDING STRONG ® The Real Brush Creek (after USACE project)
4
BUILDING STRONG ® 1 st & 2 nd Battles of the Big Blue at Byram’s Ford
5
BUILDING STRONG ® Byram’s Ford
6
BUILDING STRONG ® Blue River Flood Conveyance Channel 35,000 cfs Flood Control Channel New Bridges Remapping of Floodplain
7
BUILDING STRONG ® 3 rd Battle of Byram’s Ford Concrete Grade Control Structure
8
BUILDING STRONG ® Proposed Grade Control Structure
9
BUILDING STRONG ® Byram’s Ford Industrial Park
10
BUILDING STRONG ® Stated Goals Prevent the headcutting at the battlefield location Limit maximum flood elevation to pre- project conditions Control velocity upstream to manage scour along the riverbanks
11
BUILDING STRONG ® Design The structure was designed to stop head- cutting and control flood elevations upstream to pre-project conditions which in turn aided in managing scour at the battlefield location and along the riverbanks by controlling velocity.
12
BUILDING STRONG ® Externalities Construction of the grade control structure would affect the channel upstream of this project and create pre-project conditions, i.e., flooding in areas that had not experienced flooding since the channel project began would now be flooded again.
13
BUILDING STRONG ®
15
The Value Ah Ha! The current flood levels can be maintained to limit maximum flood elevation to below pre-project conditions Grade controls can be distributed along the river rather than at a concrete waterfall Perfection Cost Functions 0% 100% Poor Value Best Value
16
BUILDING STRONG ®
17
Stated Goals PROTECT THE CHANNEL PRESERVE THE BATTLEFIELD By Mimicking Natural Processes
18
BUILDING STRONG ® Work with River Continuum Riffle Pool Sequence Place at end of Bend
19
BUILDING STRONG ® River Profile - Newbury & Proposed GCS
20
BUILDING STRONG ® Grade Control at KC Zoo
21
BUILDING STRONG ® Rock Grade Control Structure
22
BUILDING STRONG ® 2000 cfs flow
23
BUILDING STRONG ®
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.