THEMIS MCRR GSFC 2/4/2004 THEMIS Mission Confirmation Readiness Feb 4 2004
2
THEMIS MCRR GSFC 2/4/2004 AGENDA 8:30 IntroductionF. Snow, GSFC 8:40 Science OverviewV. Angelopolous,UCB 9:00 Mission OverviewP. Harvey, UCB 9:40 Probe & Probe CarrierM. Cully, Swales 10:00 SMO AssessmentM. Goans, SRO 10:30 RAO Cost EstimateC. Fryer, SMO 11:00 DiscussionGPMC
3
THEMIS MCRR GSFC 2/4/2004 THEMIS Science Overview Dr. Vassilis Angelopolous Principal Investigator Space Sciences Laboratory University of California, Berkeley
4
THEMIS MCRR GSFC 2/4/2004 T IME H ISTORY OF E VENTS AND M ACROSCALE I NTERACTIONS DURING S UBSTORMS (THEMIS) RESOLVING THE PHYSICS OF ONSET AND EVOLUTION OF SUBSTORMS Principal Investigator Vassilis Angelopoulos, UCB EPO Lead Nahide Craig, UCB Program Manager Peter Harvey, UCB Industrial Partner SWALES Aerospace SCIENCE GOALS: Primary: “How do substorms operate?” – One of the oldest and most important questions in Geophysics – A turning point in our understanding of the dynamic magnetosphere First bonus science: “What accelerates storm-time ‘killer’ electrons?” – A significant contribution to space weather science Second bonus science: “What controls efficiency of solar wind – magnetosphere coupling?” – Provides global context of Solar Wind – Magnetosphere interaction
5
THEMIS MCRR GSFC 2/4/2004 THEMIS determines where and how substorms are triggered. Science Overview SEC Roadmap: “Understand energy, mass and flux transport in Geospace” SEC Roadmap: “How does solar variability affect society?” NRC, National Academy: A strategic question in space physics (1995). Substorms are… …important to NASA: Aurora Current disruption Reconnection Auroral eruptions are recurrent (~3-6hrs) Magnetospheric substorms are responsible for auroral eruptions. Fundamental mode of magnetospheric circulation Important for geo-storms have societal implications. Rich in new types of basic space plasma physics.
6
THEMIS MCRR GSFC 2/4/2004 Events Occuring During a Substorm Current Disruption Auroral Eruption Reconnection Current Disruption Model timeEvent 0 secCurrent Disruption 30 secAuroral Eruption 60 secReconnection Reconnection Model timeEvent 0 secReconnection 90 secCurrent Disruption 120 secAuroral Eruption ?
7
THEMIS MCRR GSFC 2/4/2004 Mission Elements Probe conjunctions along Sun-Earth line recur once per 4 days over North America. Ground based observatories completely cover North American sector; can determine auroral breakup within 1-5s … … while THEMIS’s space-based probes determine onset of Current Disruption and Reconnection each within <10s. : Ground Based Observatory
8
THEMIS MCRR GSFC 2/4/2004 Science Objectives THEMIS HAS FOCUSED MINIMUM (TO BASELINE) OBJECTIVES: Time History of Events… –Auroral breakup (on the ground) –Current Disruption [CD] (2 probes at ~10R E ) –Reconnection [Rx] (2 probes at ~20-30R E ) … and Macroscale Interactions during >5 (>10) Substorms (Primary): –Current Disruption and Reconnection coupling Outward motion (1600km/s) of rarefaction wave Inward motion of flows (1000km/s) and Poynting flux. –Ionospheric coupling Cross-tail current reduction (P5u/P4) vs flows Field aligned current generation by flow vorticity, pressure gradients ( P/dz, P/dx). –Cross-scale coupling to local modes Field line resonances (10R E, 5 min) Ballooning modes, KH waves (1R E, 1min) Weibel instability, cross-field current instability, kinetic Alfven waves (0.1R E, 6Hz) Production of storm time MeV electrons (Secondary) Control of solar wind-magnetosphere coupling by the bow-shock, magnetosheath and magnetopause (Tertiary)
9
THEMIS MCRR GSFC 2/4/2004 Probe conjunctions well understood BASELINE: >10 substorms achieved w/ 5 probes in 2 yrs & 50% margin. MINIMUM: >5 substorms achieved in 1yr w/ 4 probes. – computations include lunar, solar, drag, J2 terms – Y P1/2/3/4/5 <±2R E ; Z P3,4,5/NS <±2R E ; Z P1,2/NS <±5R E Ascent design is optimal for science – maximizes conjunctions, minimizes shadows … immune to launch insertion errors – small, piece-wise Vs increase placement fidelity … and immune to probe insertion errors. – Can withstand insertion error of V=80cm/s on any probe Actual conjunction times in 1 st year
10
THEMIS MCRR GSFC 2/4/2004 Mission overview: Fault-tolerant design has constellation and instrument redundancy D2925-10 @ CCAS Instrument I&T UCB Mission I&T Swales Encapsulation & launch BGS Operations UCB Probe instruments: ESA: Thermal plasma SST: Super-thermal plasma FGM: Low frequency B-field SCM: High frequency B-field EFI: Low and high frequency E-field Ground SST ESA EFIa EFIs FGM SCM T spin =3s
11
THEMIS MCRR GSFC 2/4/2004 Identical instrumentation provides high science margins and fault tolerance Instrument redundancy: –SST-ESA energy overlap –FGM-SCM frequency overlap –P1/P2 redundant instrumentation (only directional flux needed in one of two). Each probe has: FGM ESA 2SSTh (2heads) SCM 2EFIa (2axials) 4EFIs (4spin plane) Selected instruments built en masse Instruments required to achieve Primary Mission Objective Measurement goalsP1P2P3P4P5 Time History of Events P3,4&5 monitor CD P1,2 bracket Rx t res <30s, Y<±2R E FGM 2SSTh 2EFIs FGM ESA 2SSTh 2EFIs FGM ESA 1SSTh FGM ESA 1SSTh FGM ESA 1SSTh Macroscale Interactions Track rarefaction wave, inward flows, Poynting with B<1nT, V/V~10% FGM ESA FGM ESA FGM ESA FGM ESA Radial/cross-sheet pressure, velocity and current gradients require P/P~ V/V ~ B/B ~10%, non-MHD FGM ESA FGM ESA 2EFIs FGM ESA 2EFIs FGM ESA 2EFIs Cross-tail pairs measure FLRs, KH, ballooning on B, V, P @ 10s and fast modes on B xyz and E xy @ 6Hz FGM ESA SCM FGM ESA SCM 4EFIs 2EFIa FGM ESA 2EFIs FGM ESA SCM 4EFIs 2EFIa
12
THEMIS MCRR GSFC 2/4/2004 Mission profile is robust Pre-Launch (6hrs) Launch (25min) Check-out & ascend (60days) Science ops (2yrs) Re-entry Checkout Countdown 2 nd stage burn Spin-up 3 rd stage burn Spin-down Probe dispense Bus check-out Dply mags/check instr. Orbit place. Total of: - 6 side thrustings - 6 reor/fire/reor sequences Deploy EFI Minor ctrl ops (all): – 22 side-thrustings – 2 inclination changes Minor ctrl ops (Side-thrusts, finish by EOM+9mo) - 8 side-thrustings Passive re-entry thereafter (1-10yrs) Fuel consumption, maneuvers and contacts during ascend: validated with GMAN.
13
THEMIS MCRR GSFC 2/4/2004 First bonus: What produces storm-time “killer” MeV electrons? Affect satellites and humans in space Source: – Radially inward diffusion? – Wave acceleration at radiation belt? THEMIS: –Tracks radial motion of electrons Measures source and diffusion Frequent crossings –Measures E, B waves locally ANIK telecommunication satellites lost for days to weeks during space storm
14
THEMIS MCRR GSFC 2/4/2004 Second bonus: What controls efficiency of solar wind – magnetosphere coupling? Important for solar wind energy transfer in Geospace Need to determine how: – Localized pristine solar wind features… – …interact with magnetosphere THEMIS: – Alignments track evolution of solar wind – Inner probes determine entry type/size
15
THEMIS MCRR GSFC 2/4/2004 Mission design meets requirements Mission profile –Two year mission design easily met in this high Earth orbit –Launch: D2925 from CCAS (40min window any day) –Simple probe carrier (3 rd stage fixture) w/ release built by an experienced team –Science & routine ops and multi-object tracking has ample heritage at UCB –Simple RCS, heritage sfw & ground-cmd and GSFC/GNCD support benefits MOC Probe design –Simple, passive thermal design w/ thermostatically controlled backup heaters –Survival at all attitudes under worst shadow conditions –Simple data flow / automated routine science ops minimize cost and risk Store/Forward 375Mbit/orbit (256Mbyte capability permits multi-orbit storage) –Orbit control & knowledge exceed placement rqmts by factor of 10 –Early EMC/ESC mitigation as per heritage practices (e.g. FAST, POLAR)
16
THEMIS MCRR GSFC 2/4/2004 Active trade studies constantly reduce risk Phase A main trade studies: Direct inject with passive PCA reduces schedule and ops risks PCA dispense simplified: improves clearances, reduces risk Increased fuel tank capacity Added solar panels at bottom face ACS solution simplified with micro-gyros replacing accelerometers Connected RCS propulsion pods Phase B main trade studies: Exercised alternate path for SST instrument Tuned Phase A orbit design to reduce differential precession; enhanced 2 nd year science products Changed BAU processor to reduce software complexity motivated by GSFC experience Increased tank size to take full advantage of mass to orbit capability, yet at lower cost Increased thruster size to reduce finite arc inefficiency and Msn Ops complexity Repackaged SST and SCM electronics along with IDPU Removed ESA attenuator (simplified instrument) with minimal effect on bonus science Included redundant actuators and surge protection in instrument designs An integrated team of scientists and engineers constantly optimize mission design and resources, reducing risk.
17
THEMIS MCRR GSFC 2/4/2004 Descope list and science-related risk mitigation factors Can do baseline science even after inadvertent complete instrument failures Re-positioning allows recovery from failure of critical instruments on some probes Graceful degradation results from partial or even full instrument failures –Instrument frequency and energy range overlaps –Complete backup option for EFI radials (need 2 in most probes but have 4) –Relaxed measurement requirements (1nT absolute is not permitted to drive team, but rather a nicety) –Substorms come in wide variety; can still see large ones with degraded instruments Minimum mission can be accomplished with a reduced set of spacecraft requirements –EMC and ESC requirements important for baseline but less severe for minimum mission –Observation strategy can be tuned to power loss (turn-on/off) and thermal constraints (tip-over/back) –Fuel and mass margins for 1 st year (minimum) are 30% larger than for a two year (baseline) mission
18
THEMIS MCRR GSFC 2/4/2004 Minimum mission provides definitive answer to the substorm question. P1 P2 P3 P4 P5 Simultaneous observations in the key regions Ideal geometries for tens of substorms Data rates / time resolution exceed requirements Analysis tools available from Cluster, ISTP, FAST Experienced co-Is are leaders on both sides of substorm controversy Minimum mission accomplished within 8 months from nominal launch date
19
THEMIS MCRR GSFC 2/4/2004 THEMIS Mission Overview Peter R. Harvey Project Manager Space Sciences Laboratory University of California, Berkeley
20
THEMIS MCRR GSFC 2/4/2004 Salient Features Science –Purpose To understand the onset and macroscale (1-10 Re) evolution of magnetospheric substorms. –Capabilities Will provide the first measurements of substorm starting location Will provide the first measurements of substorm evolution –Collaborating Institutions University of California (UCB, UCLA) Swales Aerospace Inc. (SAI) Goddard Space Flight Center (GSFC) University of Colorado (LASP) Technical University of Braunschweig (TU-BS) Institut fur Weltraumforschung der OAW (IWF) CETP CESR University of Calgary University of Alberta NOAA University of Saint Petersburg Tokyo Institute of Technology
21
THEMIS MCRR GSFC 2/4/2004 Salient Features Mission Parameters –Launch Vehicle:Delta II, Eastern Range Injection:1.1 x 12 Re, 9 degrees inclination Date:August 2006 ( unrestricted ) –Space Segment Spacecraft:5 Spinning probes with fuel for orbit/attitude adjust Orbit Period(s):1, 2 and 4 days Orientation:Ecliptic normal –Ground Segment Observatories:20 Stations for All Sky Imaging and Mag Field –Operations Phases:L&EO (2 mo), Campaigns (Dec-Mar), De-Orbit Lifetime:2 years
22
THEMIS MCRR GSFC 2/4/2004 Standard Delta 10 ft. Fairing Static Envelope 3712 PAF Probe Carrier Assembly (PCA = 5 Probes + Probe Carrier) on L/V Probe Carrier Assembly (PCA = 5 Probes + Probe Carrier) on L/V THEMIS Launch Configuration Probe Carrier Assembly (PCA) on Delta 3 rd Stage Launch Configuration Dedicated launch accommodated within standard Delta 7925-10 vehicle configuration and services 10’ Composite Fairing required to accommodate five Probes on the Probe Carrier in the “Wedding Cake” configuration PC stays attached to Delta 3 rd stage after probe dispense Each probe dispense from the PCA is coordinated with but independent of the other probes No single probe anomaly precludes dispense of remaining probes Star 48 3 rd Stage
23
THEMIS MCRR GSFC 2/4/2004 Probe Bus Design Power positive in all attitudes with instruments off (launch, safe hold modes) Passive thermal design using MLI and thermostatically controlled heaters tolerant of longest shadows (3 hours) –Spin stabilized probes orbit within 13° of ecliptic plane have inherently stable thermal environment S-Band communication system always in view of earth every orbit at nominal attitude. In view for greatest part of orbit in any attitude Passive spin stability achieved in all nominal and off-nominal conditions Monoprop blow down RCS (propulsion) system is self balancing on orbit
24
THEMIS MCRR GSFC 2/4/2004 Instrument Payload
25
THEMIS MCRR GSFC 2/4/2004 PAF Adapter Ring/Tube & Attach to Launch Vehicle Main Deck Center Spool (4) Lower Probe Standard Separation Fittings (1) Upper Probe Standard Separation Fitting (8) External Struts Probe Carrier (PC) Probe Carrier Design Simple probe carrier utilizes –Machined aluminum structure –Standard heritage payload attach fittings for Probes utilize pyro- actuated clampband –Straight-forward umbilical interconnect harness –Multi layer insulation blanketing as required Detailed design supported by comprehensive analysis –NASTRAN model used to recover material stresses and fundamental frequencies –Base drive analysis used to verify strength and recover component loads –Preliminary Coupled Loads Analysis completed for our Delta II ELV Probe layout on carrier maximizes static and dynamic clearances –Design is the best balance between deployment clearances and probe structural mass First Axial Mode: 48.27 Hz First Lateral Mode: 18.29 Hz Probe Carrier Fundamental Natural Frequencies: Displacements Not to Scale
26
THEMIS MCRR GSFC 2/4/2004 ADAMS Dispense Model Dynamic Simulation Image Split screen Probe Separation Design study and analysis results –Deploy sequence of P1 then P2-P5 simultaneously –15 rpm nominal PCA spin rate –Probe separation velocity of.35 m/s Results of evaluating off-nominal conditions –No collisions or close approaches due to combinations of ‘stuck’ Probes, timing errors and tip-off –Reasonable nutation and pointing angles that Probe ACS can easily accommodate –Separation initiation is two fault tolerant Visualization –Used actual output files from ADAMS to make the animation Flexibility for tuning deployment later in the design process includes; carrier spin rate, deployment spring stiffness, deployment order, and timing
27
THEMIS MCRR GSFC 2/4/2004 Ground System Block Diagram
28
THEMIS MCRR GSFC 2/4/2004 ResourceNot to Exceed (NTE) Current Best Estimate (CBE) Margin Probe Carrier Assembly Dry Mass (kg) 606.5 1 458.4 32.3% Delta V (m/s) 700574 21.9% Orbit Average EOL Power (W) 38.228.1 35.8% Science Data Storage (MB) 256187.5 2 36.5% Probe TLM Data Storage (MB) 1611 45.5% Notes: 1. Probe Carrier Assembly Dry Mass NTE = LV Capability (800 kg) - 5 x Fuel (38.7 kg) = 606.5 kg 2. Current Best Estimate 750Mbits/orbit + 1 day contingency = 1500Mbits = 187.5MB RF Link Margin - Science Downlink (1024 kbps at perigee)4.2 dB - H&S Downlink (4 kbps at apogee)6.0 dB - Command Uplink (1 kbps at apogee)6.2 dB System Margins
29
THEMIS MCRR GSFC 2/4/2004 Power Generation Power Margin and Current Best Estimate History since PDR –Issues identified after PDR dropped potential power generation capability of baseline design significantly –Solutions have been identified and are being implemented PDRDecemberCurrent Design EOL Power 42.634.438.2 CBE 27.330.228.1 Margin56.1%13.7%35.8%
30
THEMIS MCRR GSFC 2/4/2004 Power Generation Work-aroundEffectNotes Extra cells+5.1%Conservative 3 strings lost due to Mag Booms, 1 string loss > 60 deg due to EFI Snout. Increased area +9.4%A number of layouts are being evaluated. Increased area represents most conservative option to date. No mass increase anticipated. Issues Identified since PDR –Effect of shadowing from EFI Snout and Mag Booms greater than expected –Losses due to Electrostatic Cleanliness (ESC) Implementation (ITO coating and interconnects) greater than anticipated –Cell cosine loss assumptions were more optimistic at PDR than actual data –PDR calculation assumed power would be produced at higher incidence angle than current specification Solutions being implemented –Added cells around EFI snout to mitigate shadowing –Increased total photon collecting area IssueEffect Shadowing-14% ESC-7% Cosine loss-2.9% Incident angle-5.7%
31
THEMIS MCRR GSFC 2/4/2004 Organization Mission Manager Frank Snow, GSFC Mission Manager Frank Snow, GSFC Financial Mgr K. Harps, UCB Financial Mgr K. Harps, UCB Launch Vehicle G. Skrobott, KSC Launch Vehicle G. Skrobott, KSC Project Scientist D. Sibeck, GSFC Project Scientist D. Sibeck, GSFC THEMIS PI V. Angelopolous, UCB THEMIS PI V. Angelopolous, UCB Project Manager P. Harvey, UCB Project Manager P. Harvey, UCB Science Co-I’s EPO N. Craig, UCB EPO N. Craig, UCB Subcontracts J. Keenan, UCB Subcontracts J. Keenan, UCB Scheduling D. Meilhan, UCB Scheduling D. Meilhan, UCB Quality Assurance R. Jackson, UCB Quality Assurance R. Jackson, UCB Mission Systems E. Taylor, UCB Mission Systems E. Taylor, UCB Mechanical/ Thermal Systems P. Turin, UCB C. Smith, UCB Mechanical/ Thermal Systems P. Turin, UCB C. Smith, UCB Mag Cleanliness C. Russell, UCLA Mag Cleanliness C. Russell, UCLA Probe/Probe Carrier Management UCB Oversight: D. King Swales Mgr: M. Cully Probe/Probe Carrier Management UCB Oversight: D. King Swales Mgr: M. Cully Instruments P. Berg, UCB Instruments P. Berg, UCB Ground Segment M. Bester, UCB Ground Segment M. Bester, UCB Software Systems D. King, UCB Software Systems D. King, UCB Mission I&T R. Sterling, UCB Mission I&T R. Sterling, UCB
32
THEMIS MCRR GSFC 2/4/2004 Organization Instrument Development Instruments P. Berg Instruments P. Berg Electric Field Instrument (EFI) J. Bonnell Electric Field Instrument (EFI) J. Bonnell ElectroStatic Analyser (ESA) C. Carlson ElectroStatic Analyser (ESA) C. Carlson Solid State Telescope (SST) D. Larson Solid State Telescope (SST) D. Larson Instrument Data Processor Unit (IDPU) M. Ludlam Instrument Data Processor Unit (IDPU) M. Ludlam Fluxgate Mag (FGM) U. Auster Fluxgate Mag (FGM) U. Auster Search Coil Mag (SCM) A. Roux Search Coil Mag (SCM) A. Roux Forrest Mozer Greg Delory Art Hull Bill Donakowski Greg Dalton Robert Duck Mark Pankow Dan Schickele Stu Harris Hilary Richard Forrest Mozer Greg Delory Art Hull Bill Donakowski Greg Dalton Robert Duck Mark Pankow Dan Schickele Stu Harris Hilary Richard Robert Abiad Peter Berg Heath Bersch Dorothy Gordon Frank Harvey Selda Heavner Jim Lewis Jeanine Potts Chris Scholz Kathy Walden Robert Abiad Peter Berg Heath Bersch Dorothy Gordon Frank Harvey Selda Heavner Jim Lewis Jeanine Potts Chris Scholz Kathy Walden M. Marckwardt Bill Elliott Ron Herman Chris Scholz M. Marckwardt Bill Elliott Ron Herman Chris Scholz Robert Lin Davin Larson Ron Canario Robert Lee T. Moreau Robert Lin Davin Larson Ron Canario Robert Lee T. Moreau Hari Dharan Y. Kim Tien Tan Bill Tyler Hari Dharan Y. Kim Tien Tan Bill Tyler TUBS/IWF Uli Auster K.H. Glassmeier W. Magnes TUBS/IWF Uli Auster K.H. Glassmeier W. Magnes CETP Alain Roux Bertran de la Porte Olivier Le Contel Christophe Coillot Abdel Bouabdellah CETP Alain Roux Bertran de la Porte Olivier Le Contel Christophe Coillot Abdel Bouabdellah LASP Robert Ergun Aref Nammari Ken Stevens Jim Westfall LASP Robert Ergun Aref Nammari Ken Stevens Jim Westfall Mag Booms Mag Booms
33
THEMIS MCRR GSFC 2/4/2004 Organization Ground Systems Development Ground Segment Mission Ops Science Ops (Mission Planning) Mission Ops Science Ops (Mission Planning) Ground Based Observatories Manfred Bester Mark Lewis Tim Quinn Sabine Frey Tai Phan John Bonnell Laura Peticolas Manfred Bester Mark Lewis Tim Quinn Sabine Frey Tai Phan John Bonnell Laura Peticolas Stephen Mende Stu Harris Steve Geller Harald Frey Stephen Mende Stu Harris Steve Geller Harald Frey UCLA Chris Russell Joe Means Dave Pierce UCLA Chris Russell Joe Means Dave Pierce All Sky Imagers All Sky Imagers Ground Magnetometers Fielding & Operation (UC&UA) Fielding & Operation (UC&UA) UC Eric Donovan UC Eric Donovan GSFC/GCND David Sibeck Mark Beckman Bob DeFazio David Folta Rick Harman GSFC/GCND David Sibeck Mark Beckman Bob DeFazio David Folta Rick Harman UA J. Samson UA J. Samson
34
THEMIS MCRR GSFC 2/4/2004 Agreements Contracts & Agreements Status
35
THEMIS MCRR GSFC 2/4/2004 60 days Funded Schedule Reserve Included
36
THEMIS MCRR GSFC 2/4/2004 Schedule Key Features Instrument Development –EM Instrument I/F Testing with EM Probe I/F –Integrate Instrument Complement at UCB Prior to S/C Integration –Instrument Complement F1 Tested First Followed by Pairs –All Instrument Complements are Complete before S/C I&T Begins –Instrument I&T Team Will Be Focusing Upon S/C I&T –Added Some Facilities for Qualifying Instruments in Parallel Spacecraft Development –Integration and Test of Probe1 Completed Prior to Probes 2-5 –Sufficient Manpower and Equipment for Parallel I&T Ground Development –Development and Deployment of 5 GBOs 2 in 1Q05 –Development and Deployment of all 20 GBO’s in 1Q06
37
THEMIS MCRR GSFC 2/4/2004 Schedule Metrics Milestone Comparisons to HESSI Sufficient Definition –23 Schedules involving 3977 tasks Slack –Instruments have 4.5-6 months slack to Earliest I&T with Probes –Instruments have 6.5-9.5 months slack to Expected I&T with Probes –Integrated Probes/Probe Carrier have 2 months to LV Integration
38
THEMIS MCRR GSFC 2/4/2004 Schedule Relevant Prior Schedule Performance FAST Instruments (EFI, ESA, MAG, IDPU) –Hopped in Front of SWAS –Delivered Complement on Time POLAR / CLUSTER I & II (EFI) –Polar EFI Delivered 8 months ahead of time –Cluster EFW I & II Delivered > 45 Flight Units to WEC in time. HESSI (Management, IDPU) –Phase B to JPL Environmental Tests (Est. 23 mo, Act. 23.2 mo) –Re-Confirmation to VAFB Delivery (Est. 6 mo, Act 6.3 mo)
39
THEMIS MCRR GSFC 2/4/2004 Schedule Instrument Heritage Maintained thru PDR
40
THEMIS MCRR GSFC 2/4/2004 Cost Cost Estimate (src CSR Figure3)
41
THEMIS MCRR GSFC 2/4/2004 Cost Cost Reasonableness THEMIS Phase B/C/D Costs Compare Well to HESSI Actual Costs –THEMIS Instruments Require Less Development than HESSI THEMIS Phase E Mission Operations Suitably Larger –Handling 5 Probes Instead of 1; Cost Estimated at 3x
42
THEMIS MCRR GSFC 2/4/2004 Cost Relevant Prior Cost Performance POLAR / CLUSTER I & II (EFI) –Polar EFI Delivered at 37% Under Budget –Cluster EFW I Delivered 40% Under Budget. –Cluster EFW II Was Built using Reserve from EFW I HESSI (Management, IDPU) –Completed Spacecraft & Ground Systems at 8% Under Budget –Re-Built Spacecraft 39% Under Budget HESSI UCB Actual Cost v Plan
43
THEMIS MCRR GSFC 2/4/2004 Cost Total Project Cost Performance v Budget
44
THEMIS MCRR GSFC 2/4/2004 Summary Experienced Teams are In Place Management, Systems Engineering, Quality Assurance (HESSI, Chips, EUVE, Image, FAST, Cluster, Polar, Firewheel,…) Cost is Reasonable Compares to Prior Missions, On-Budget thru Phases A/B Schedule is Consistent with Previous Projects HESSI, Polar, Cluster
45
THEMIS MCRR GSFC 2/4/2004 BACKUP SLIDES
46
THEMIS MCRR GSFC 2/4/2004 Baseline L1 Requirements S-1 Substorm Onset Time –Determine substorm onset time and substorm meridian magnetic local time (MLT) using ground ASIs (one per MLT hr) and MAGs (two per MLT hr) with t_res<30s and dMLT<1 degree respectively, in an 8hr geographic local time sector including the US. (M-11, GB-1) S-2 Current Disruption (CD) Onset Time –Determine CD onset time with t_res<30s, using two near-equatorial (within 2Re of magnetic equator) probes, near the anticipated current disruption site (~8-10 Re). CD onset is determined by remote sensing the expansion of the heated plasma via superthermal ion flux measurements at probes within +/-2Re of the measured substorm meridian and the anticipated altitude of the CD. (M- 9, IN.SST-1, IN.SST-4, IN.FGM-1) S-3 Reconnection (Rx) Onset Time –Determine Rx onset time with t_res<30s, using two near-equatorial (< 5Re from magnetic equator) probes, bracketing the anticipated Rx site (20-25Re). Rx onset is determined by measuring the time of arrival of superthermal ions and electrons from the Rx site, within dY=+/-2Re of the substorm meridian and within <10Re from the Rx altitude. ….. (M-9, IN.EFI-2, IN.ESA-1, IN.SST-2, IN.SST-3, IN.SST-4, IN.FGM-1) S-4 Simultaneous Observations –Obtain simultaneous observations of: substorm onset and meridian (ground), CD onset and Rx onset for >10 substorms in the prime observation season (September-April). Given an average 3.75hr substorm recurrence in the target tail season, a 2Re width of the substorm meridian, a 1Re requirement on probe proximity to the substorm meridian (of width 2Re) and a 20Re width of the tail in which substorms can occur, this translates to a yield of 1 useful substorm event per 18.75hrs of probe alignments, i.e, a requirement of >188hrs of four-probe alignments within dY=+/-2Re. (M-1, M- 12, IN.FGM-1)
47
THEMIS MCRR GSFC 2/4/2004 S-5 Earthward Flows –Track between probes the earthward ion flows (400km/s) from the Rx site and the tailward moving rarefaction wave in the magnetic field, and ion plasma pressure (motion at 1600km/s) with sufficient precision (dV/V=10% or V within 50km/s whichever is larger, dB/B=10%, or B within 1nT whichever is larger, dP/P=10%, or P within 0.1nPa whichever is larger) to ascertain macroscale coupling between current disruption and reconnection site during >10 substorm onsets (>188hrs of four- probes aligned within dY of +-2Re). (IN.ESA-1, IN.SST-3, IN.FGM-1) S-6 Pressure Gradients –Determine the radial and cross-current-sheet pressure gradients (anticipated dP/dR, dP/dZ ~0.1nPa/Re) and ion flow vorticity/deceleration with probe measurement accuracy of 50km/s/Re, over typical inter-probe conjunctions in dR and dZ of 1Re, each during >10 onsets. The convective component of the ion flow is determined at 8-10Re by measurements of the 2D electric field (spin- plane to within +-30degrees of ecliptic, with dE/E=10% or 1mV/m accuracy whichever is larger) assuming the plasma approximation at t_res<30s. (IN.EFI-1, IN.ESA-1, IN.ESA-2, IN.SST-3, IN.FGM-1) S-7 Cross-Current Sheet changes –Determine the cross-current-sheet current change near the current disruption region (+/-2Re of meridian, +-2Re of measured current disruption region) at substorm onset from a pair of Z-separated probes using the planar current sheet approximation with relative (interprobe) resolution and interorbit (~12hrs) stability of 0.2nT. (IN.FGM-1, PB-42, PB-43, PB-44) S-8 non-MHD plasma –Obtain measurements of the Magneto-Hydrodynamic (MHD) and non-MHD parts of the plasma flow through comparisons of ion flow from the ESA detector and ExB flow from the electric field instrument, at the probes near the current disruption region, with t_res<10s. (IN.EFI-1, IN.ESA-1, IN.SST-3, IN.FGM-1) … continued: Baseline L1 Requirements
48
THEMIS MCRR GSFC 2/4/2004 S-9 Cross-Tail Pairs –Determine the presence, amplitude, and wavelength of field-line resonances, Kelvin-Helmholz waves and ballooning waves on cross-tail pairs (dY=0.5-10Re) with t_res 10 substorm onsets. (IN.ESA-1, IN.SST-3) S-10 Cross-Field Current Instabilities –Determine the presence of cross-field current instabilities (1-60Hz), whistlers and other high frequency modes (up to 600Hz) in 3D electric and magnetic field data on two individual probes near the current disruption region for >10 substorm events. (IN.EFI-3, IN.ESA-3, IN.SCM-1) S-11 Dayside Science –Determine the nature, extent and cause of magnetopause transient events (on dayside). (IN.ESA-4, IN.SST-6) … continued: Baseline L1 Requirements
49
THEMIS MCRR GSFC 2/4/2004 Minimum L1 Requirements (from L1’s) 4.1.2.1 Substorm Onset Time –Determine substorm onset time and substorm meridian magnetic local time (MLT) using ground MAGs (at least one per MLT hr) with t_res<30s and dMLT<6 degrees respectively, in a 6hr geographic local time sector including the US. 4.1.2.2 Current Disruption (CD) Onset Time –Determine CD onset time with t_res<30s, using two near-equatorial (within 2Re of magnetic equator) probes, near the anticipated CD site (~8-10 Re). …(same as baseline) 4.1.2.3 Reconnection (Rx) Onset Time –Determine Rx onset time with t_res<30s, using two near-equatorial (<5Re of magnetic equator) probes, bracketing the anticipated Rx site (20-25Re). … (same as baseline) 4.1.2.4 Simultaneous Observations –Obtain simultaneous observations of: substorm onset and meridian (ground), CD onset and reconnection onset for >5 substorms in the prime observation season (September-April). Substorm statistics discussed in S-4 point to a requirement of >94hrs of four probe alignments. 4.1.2.5 Energetic ion and electron fluxes –SST to measure near the ecliptic plane (+/-30 o ) superthermal i + and e - fluxes (30-100keV) at t_res<30s. 4.1.2.6 Earthward Flows –Track between probes the earthward ion flows (400km/s) from the reconnection site and the tailward moving rarefaction wave in the magnetic field, and ion plasma pressure (motion at 1600km/s) with sufficient precision precision (dV/V=10% or V within 50km/s whichever is larger, dB/B=10%, or B within 1nT whichever is larger, dP/P=10%, or P within 0.1nPa whichever is larger) to ascertain macroscale coupling between current disruption and reconnection site during >5 substorm onsets.
50
THEMIS MCRR GSFC 2/4/2004 Instrument Cost Instrument Mass.v. Cost Modeling –Categorized Each Component by its Complexity EBOX : Electronics Box (src EFI & HESSI) MECH : Mechanism with Few Electronics Parts (src Cluster) SENSOR : Mixed Mechanical and Electronic Parts (src FAST) –Computed Mass of Flight & Spare Units Grass Roots Budget is 6% Over Model So Budget is Sufficient
51
THEMIS MCRR GSFC 2/4/2004 Instrument Cost Heritage Instruments Costs.v. THEMIS –Typical NASA Instrument Contracts Have Greater Scope of Effort Science, Management, Systems Engineering, Quality Assurance Mission Operations and Data Analysis Significant Instrument Design and Development Instrument Sensors Instrument Main Electronics Instrument Flight Software –THEMIS Sensor Costs Include Engineering for Interface-driven Modifications Include Sensor Fabrication and Test in Quantity Other Efforts are Costed in WBS 1 (Science, Management, Systems Engineering, Quality Assurance), WBS 2.1.1 (IDPU, FSW), WBS 4 (MODA)
52
THEMIS MCRR GSFC 2/4/2004 Descope Cost Available Descope Options Modest Requirements Allow Flexibility in Instrumentation Cost Savings are Available