Download presentation
Presentation is loading. Please wait.
Published byRoderick Sullivan Modified over 9 years ago
1
The Lower Mon Project William A. Karaffa, P.E. Project Manager Briefing to Waterways Association of Pittsburgh April 14, 2004
2
The Lower Mon Project Demolition of Old Dam #2 Braddock Dam
3
The Lower Mon Project Braddock Dam Demolition of Old Dam #2
4
The Lower Mon Project Charleroi Locks Independent Value Engineering Study Project Status
5
The Lower Mon Project Charleroi Locks Independent Value Engineering Study Best Value Trade-Off Evaluation
6
The Lower Mon Project Charleroi Locks Independent Value Engineering Study Final Recommendation ● The Evaluation Team and the PRB acknowledged the potential cost savings of $25M was very speculative, due to the preliminary nature of the VE design. ● The PRB concluded that the risks associated with the long term operability, maintainability, and navigation safety of the VE to be unacceptable, regardless of the potential cost savings.
7
The Lower Mon Project Charleroi Locks Project Status ● Right Bank Work Features - Ongoing ● River Chamber Demolition – Ongoing ● New River Wall Construction – Advertise April 26, 2004 ● Waterways Site Visit – April 22, 2004
8
Lower Monongahela River Project Efficient & Constrained Funding Streams
9
Lower Monongahela River Project Current Schedule ($30 M / Year)
10
Lower Monongahela River Project Impacts of Constrained Funding Completion of Charleroi Locks is delayed 6 years Risk of failure at L/D 3 increases significantly; major rehabilitation may be required to extend project life until 2016 when Dam 3 is removed. Increased O&M costs to maintain depreciated lock operating equipment at Locks 3 & 4 Total benefits foregone with FY-05 constrained schedule are estimated at $1.2 billion.
11
Lower Monongahela River Project Additional O&M Requirements Locks 3 & 4 (Normal Maintenance Schedule) 2007Repair Valves & Gate Miter Sills $2.0 M 2010Lock Gate Replacement or Rehab $1.5 M 2017Repair Valves & Gate Miter Sills $2.2 M Total (Each Project) $5.7 M Dam 3 Significant potential for foundation failure without major Rehabilitation. Pool 3 could be lost, resulting in significant impacts to Locks 4 stability, Municipal water intakes, and private facilities.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.