Published byWilfred May Modified over 9 years ago
1
Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare
2
Agenda Why Track Progress? Scope of Presentation MS-Project Tracking Fields Other Fields that Affect MS-Project Tracking Calculation Formulas and Options Report Definitions Viewing and Editing Assignment Tracking Fields Project Server Timesheet Tracking Modes
3
Why Track Progress? Monitor Critical Path Budget Status Reporting Forecasting Earned Value Build historical information for future project metrics
4
Scope of Presentation Updating of assignment tracking fields only No direct discussion of task-level tracking field updates No direct discussion of cost Actual Cost and Remaining Cost are byproducts of actual work and fixed work We will discuss Actual Work How do task types affect the calculations? How does an assignment update affect a task with a single assignment? Avoid multiple assignment calculations! Only discuss assignment- level calculations for fields that have both assignment and task levels
5
MS-Project Tracking Fields Assignment-level tracking fields Actual Start Actual Finish Actual Work % Work Complete Remaining Work Timephased Actual Work Task-level tracking fields Includes all assignment-level fields plus duration- based fields %Complete Actual Duration Remaining Duration
6
Other fields that affect assignment-level tracking Scheduled Fields Assignment Level Only Assignment Units Task Level Only Duration Assignment and Task Level Work Start Finish Task Type Fixed Duration Fixed Units Fixed Work Assignment Delay Affects individual assignment start date calculations
7
Calculation Formulas Duration formulas (task level only) % Complete = 100 x (Actual Duration / Duration) Duration = Actual Duration + Remaining Duration Work formulas (task and assignment levels) % Work Complete = 100 x Actual Work / Work Work = Actual Work + Remaining Work Scheduling formula Work = Duration * Units
8
Calculation Options Updating task status updates resource status The default value (checked) is assumed Status Date Determines date that actuals are posted Defaults to today if left NA Useful if you are entering actuals from previous day Can be changed using Project, Project Information New options on the Calculations tab of the Options dialog box Move end of completed parts after status date back to status date And move start of remaining parts back to status date Move start of remaining parts before status date forward to status date And move end of completed parts forward to status date
9
Report Definitions Assignment/ Task Status Started Actual Start <> NA Not Started Actual Start = NA Finished Actual Finish <> NA Not Finished Actual Finish = NA Updated Value Field value that is being updated Scheduled Value Scheduled value of field corresponding to actual field being calculated
10
Viewing and editing assignment tracking fields Standard MS-Project assignment views Task Usage Groups assignments by task and sorts by resource Resource Usage Groups assignments by resource and sorts by task Other methods for updating these fields Assignment Information Dialog Double-click an assignment to see the assignment-specific fields. Assign Resources dialog Task Form
11
Project Server Timesheet Tracking All updates performed at the assignment level Modes Percentage of Work Complete Total Actual Work and Remaining Work Timesheet Calculation: scheduled Work – Actual Work = Remaining Work Timephased Actual Work and Remaining Work Timesheet Calculation: scheduled Work – Actual Work = Remaining Work
12
Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare