Department of Energy EVM Update NDIA Program Management Systems Committee August 17, 2005 Mike Donnelly Office of Engineering and Construction Management.

Similar presentations


Presentation on theme: "Department of Energy EVM Update NDIA Program Management Systems Committee August 17, 2005 Mike Donnelly Office of Engineering and Construction Management."— Presentation transcript:

1 Department of Energy EVM Update NDIA Program Management Systems Committee August 17, 2005 Mike Donnelly Office of Engineering and Construction Management

2 EVMS Acceptance Reviews Senior level interest and support –Included in Department’s action plans for President’s Management Agenda Aggressive review schedule –Focus is on contractors managing high risk projects and Management and Operations contractors responsible for multiple projects

3 EVMS Acceptance Reviews DCMA responsible for leading reviews and managing the acceptance process –Review teams comprised of DOE personnel FY05 – 8 reviews scheduled –6 have been completed – two to go FY06 – goal is to complete 12 reviews

4 EVM Challenges Improve review process EVMS surveillance Use of EVM on long term operating projects Standardized Contractor Performance Reports FAR clause implementation EVM staffing and expertise