Major projects carried out by Design cell ( July 2015 ) 12/22/20151Design cell IIT,Bombay Aug 2015
2
Works completed Aug 2015 ( Design cell ) 12/22/2015Design cell IIT,Bombay Aug 20152
3
Research Park Main Building Ground Floor Area = 600 sqft Year = July 2015 Project Duration = 2 Months Project Cost = 16 lakhs Rate Per Sqft = 2700 per sqft Work taken up = Civil, interior, electrical furniture & Chairs 12/22/20153Design cell IIT,Bombay Aug 2015
4
CEP Office ( Main Bldg 2 nd floor ) Area = 1200 sqft Year = Aug 2015 Project Duration = 4 Month Project cost = 23.0 lakhs Rate per Sqft = 1900 per sqft Work Taken up = Interior, furniture & Electrical 4Design cell IIT,Bombay Aug 2015
5
Prof.Rajaraman’s PHD Lab Chemical Eng. Dept Area = 425 Sq.ft Year = August 2015 Project Duration = 2 months Project Cost = 10.0 lakhs Work taken up = Civil, Electrical & Furniture 12/22/20155Design cell IIT,Bombay Aug 2015
6
RS Lab Metallurgy Dept.3 rd Floor Area = 400 sqft Year = August 2015 Project Duration = 2 months Project Cost = 8.0 lakhs work Taken up = Civil,Interior,furniture & Electrical 12/22/20156Design cell IIT,Bombay Aug 2015
7
Works in Progress till Aug 2015 ( Through Architect) ) 12/22/2015Design cell IIT,Bombay Nov 20137
8
Bio Lab ( Chemical Dept ) Area = 4500 sqft Project Duration = 4 Months Project Cost = 50 lakhs Project Statue = 100 % complete Work taken up = Civil, interior, electrical furniture 12/22/20158Design cell IIT,Bombay Aug 2015
9
CTARA students lab ( old computer science bldg ) Phase-1 Area = 650 sqft Project Duration = 6 Month Project cost = 40.00 lakhs Project Statue = 95 % complete Work Taken up = Interior, furniture & Electrical 9Design cell IIT,Bombay Aug 2015
10
Electrical Dept Renovation Area = 8500 sqft Completion Period= 9 months Project Status = 95% completed Project cost = 85 lakhs Work taken up = Interior work 12/22/201510Design cell IIT,Bombay Aug 2015
11
Nano (Electrical Annex) 12/22/201511Design cell IIT,Bombay Aug 2015
12
Electrical Engineering Dept Lobby 12/22/201512Design cell IIT,Bombay Aug 2015
13
Civil Dept General space Renovation Area = 6000 sqft Completion period = 9 months Project cost = 1.30 crores Status = 60% complete Work taken up = Interior, furniture, Electrical 12/22/201513Design cell IIT,Bombay Aug 2015
14
Architect Projects to start by Sep 2015 12/22/2015Design cell IIT,Bombay Aug 201514
15
Gulmohar Renovation ( Phase -1 ) Garden Restaurant, Kitchen and Terrace Area = 7000 sqft Project Duration = 6 Month Project cost = 2.5 crores Work Taken up = Civil, Interior, Furniture, landscaping & Electrical 12/22/201515Design cell IIT,Bombay Aug 2015
16
Façade Renovation for Electrical, Civil Mechanical, Metallurgy & Physics Dept. Project Duration = 12 months Project cost = 2.00 crores 12/22/201516Design cell IIT,Bombay Aug 2015
17
Aero Dept Renovation ( Main and Annex ) Project Duration = 2 years ( will be done in phases ) Project cost = 6.00 crores Work Taken up = Civil, Interior, Furniture & Electrical 12/22/201517Design cell IIT,Bombay Aug 2015
18
12/22/2015Design cell IIT,Bombay Aug 1518 Mechanical Engineering Dept Renovation Area = 10000 sqft Project Duration = 2 years ( Work will be carried out in phases ) Project cost = 5.00 crores Work Taken up = Interior, furniture, electrical
19
Jal vihar and Vanvihar Rooms renovation. Project Duration = 1 years ( will be done in phases ) Project cost = 6.00 crores Work Taken up = Civil, Interior, Furniture, Electrical and HVAC 12/22/201519Design cell IIT,Bombay Aug 2015 Mock up Room ( Jalvihar ) 16 rooms Mock up Room ( vanvihar ) 50 rooms
20
12/22/201520Design cell IIT,Bombay Aug 2015
21
12/22/201521Design cell IIT,Bombay Aug 2015
22
Thank you 12/22/2015Design cell IIT,Bombay Nov 201322
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.