Presentation is loading. Please wait.

Presentation is loading. Please wait.

Major projects carried out by Design cell ( July 2015 ) 12/22/20151Design cell IIT,Bombay Aug 2015.

Similar presentations


Presentation on theme: "Major projects carried out by Design cell ( July 2015 ) 12/22/20151Design cell IIT,Bombay Aug 2015."— Presentation transcript:

1 Major projects carried out by Design cell ( July 2015 ) 12/22/20151Design cell IIT,Bombay Aug 2015

2 Works completed Aug 2015 ( Design cell ) 12/22/2015Design cell IIT,Bombay Aug 20152

3 Research Park Main Building Ground Floor Area = 600 sqft Year = July 2015 Project Duration = 2 Months Project Cost = 16 lakhs Rate Per Sqft = 2700 per sqft Work taken up = Civil, interior, electrical furniture & Chairs 12/22/20153Design cell IIT,Bombay Aug 2015

4 CEP Office ( Main Bldg 2 nd floor ) Area = 1200 sqft Year = Aug 2015 Project Duration = 4 Month Project cost = 23.0 lakhs Rate per Sqft = 1900 per sqft Work Taken up = Interior, furniture & Electrical 4Design cell IIT,Bombay Aug 2015

5 Prof.Rajaraman’s PHD Lab Chemical Eng. Dept Area = 425 Sq.ft Year = August 2015 Project Duration = 2 months Project Cost = 10.0 lakhs Work taken up = Civil, Electrical & Furniture 12/22/20155Design cell IIT,Bombay Aug 2015

6 RS Lab Metallurgy Dept.3 rd Floor Area = 400 sqft Year = August 2015 Project Duration = 2 months Project Cost = 8.0 lakhs work Taken up = Civil,Interior,furniture & Electrical 12/22/20156Design cell IIT,Bombay Aug 2015

7 Works in Progress till Aug 2015 ( Through Architect) ) 12/22/2015Design cell IIT,Bombay Nov 20137

8 Bio Lab ( Chemical Dept ) Area = 4500 sqft Project Duration = 4 Months Project Cost = 50 lakhs Project Statue = 100 % complete Work taken up = Civil, interior, electrical furniture 12/22/20158Design cell IIT,Bombay Aug 2015

9 CTARA students lab ( old computer science bldg ) Phase-1 Area = 650 sqft Project Duration = 6 Month Project cost = 40.00 lakhs Project Statue = 95 % complete Work Taken up = Interior, furniture & Electrical 9Design cell IIT,Bombay Aug 2015

10 Electrical Dept Renovation Area = 8500 sqft Completion Period= 9 months Project Status = 95% completed Project cost = 85 lakhs Work taken up = Interior work 12/22/201510Design cell IIT,Bombay Aug 2015

11 Nano (Electrical Annex) 12/22/201511Design cell IIT,Bombay Aug 2015

12 Electrical Engineering Dept Lobby 12/22/201512Design cell IIT,Bombay Aug 2015

13 Civil Dept General space Renovation Area = 6000 sqft Completion period = 9 months Project cost = 1.30 crores Status = 60% complete Work taken up = Interior, furniture, Electrical 12/22/201513Design cell IIT,Bombay Aug 2015

14 Architect Projects to start by Sep 2015 12/22/2015Design cell IIT,Bombay Aug 201514

15 Gulmohar Renovation ( Phase -1 ) Garden Restaurant, Kitchen and Terrace Area = 7000 sqft Project Duration = 6 Month Project cost = 2.5 crores Work Taken up = Civil, Interior, Furniture, landscaping & Electrical 12/22/201515Design cell IIT,Bombay Aug 2015

16 Façade Renovation for Electrical, Civil Mechanical, Metallurgy & Physics Dept. Project Duration = 12 months Project cost = 2.00 crores 12/22/201516Design cell IIT,Bombay Aug 2015

17 Aero Dept Renovation ( Main and Annex ) Project Duration = 2 years ( will be done in phases ) Project cost = 6.00 crores Work Taken up = Civil, Interior, Furniture & Electrical 12/22/201517Design cell IIT,Bombay Aug 2015

18 12/22/2015Design cell IIT,Bombay Aug 1518 Mechanical Engineering Dept Renovation Area = 10000 sqft Project Duration = 2 years ( Work will be carried out in phases ) Project cost = 5.00 crores Work Taken up = Interior, furniture, electrical

19 Jal vihar and Vanvihar Rooms renovation. Project Duration = 1 years ( will be done in phases ) Project cost = 6.00 crores Work Taken up = Civil, Interior, Furniture, Electrical and HVAC 12/22/201519Design cell IIT,Bombay Aug 2015 Mock up Room ( Jalvihar ) 16 rooms Mock up Room ( vanvihar ) 50 rooms

20 12/22/201520Design cell IIT,Bombay Aug 2015

21 12/22/201521Design cell IIT,Bombay Aug 2015

22  Thank you 12/22/2015Design cell IIT,Bombay Nov 201322


Download ppt "Major projects carried out by Design cell ( July 2015 ) 12/22/20151Design cell IIT,Bombay Aug 2015."

Similar presentations


Ads by Google