D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.

Similar presentations


Presentation on theme: "D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review."— Presentation transcript:

1 D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review (Womersley)

2 D0 PMG 6/15/00 Status Overview  Silicon u Just reported at DOE review

3 D0 PMG 6/15/00 Status Overview  Forward Preshower u Both detectors installed  ICD u North & South Installed  Luminosity monitor u North & South Installed  Fiber tracker u Just reported at DOE review u Some update u Preparing the move to DAB

4 D0 PMG 6/15/00 Fiber Tracker Status  Waveguide QC going well u Final acceptance criteria are still being developed s Likely to accept two bad channels per wavguide (256)  Falling off production schedule u Priming “pipelines”.

5 D0 PMG 6/15/00 Fiber Tracker Status  VLPC Cassettes u Sub-component assembly s 65-80% complete u Final production cassette test/characterization not quite started

6 D0 PMG 6/15/00 Status Overview  Central Muons u Commissioning continues  Forward Muon detectors u Trig Pixels s All octants assembled & tested & starting to move to DAB s HV commissioning complete s VME crate installation started s A layer supports in production u MDTs s A layer octants installed s B octants all parts on hand s C octants: 15 done s C layer supports in production

7 D0 PMG 6/15/00 Status Overview  Trigger & DAQ u progressing – far from critical path  Online u No schedule concerns, not on critical path u Good progress on internal commissioning milestones ( pushing on subsystems) u Supporting silicon 10% test  Solenoid and beam pipe u No changes since last time

8 D0 PMG 6/15/00 Status Overview; Electronics  Electronics u Calorimeter s Preamps 99% complete s BLS delayed – solving coherent noise problem u Muon s PDT electronics - done s Scintillator –Front end Found missing part, done by end of month –Readout card - done s MDT - done s Readout electronics –Readout 100% –Fanout 15%; released for production

9 D0 PMG 6/15/00 Status Overview ; Electronics u Tracking Electronics s Released Si interface card production bid process –Still have final changes to make s Concerned about low mass cable cross talk –Being studied –Understanding how to speed up production – possible $ exposure s Analog Front End boards –Release order for 10 pcs (4 wks) s MCM yields lower than anticipated –Based on small sample –May have $ risk (contracted for 15% loss)

10 D0 PMG 6/15/00 Installation  Installation u Shielding articulated on North Truss u Surveyed A layer chambers u A Pixel sheets being assembled on wall u VLPC cryostat have leaks (near lids) s 2 week delay (remachine) s Anticipate getting in before platform moves u Started cabling s Interface card – sequencer – ok

11 D0 PMG 6/15/00 Summary  Concerns u Silicon continues……. u Waveguides are concern u Use of contingency: we are using it s Both kinds: schedule and funding