Building for Learning Project Photo Progress Report 5 December 2009 – February 2010 Project commencement 21 st September 2009
2
Mid January – more minor demolition and framing
3
Fire services installed and stairway brickwork
4
Hooray - Admin completed!!!!!!
5
Former student work (maths and French) dating back to 1922 found in building cavities from demolition
6
1 st Storey wall frames going up
7
Ground floor ceiling struts and power box installed
8
1 st Storey Wall Framing – well underway
9
While the photos don’t show it – several days of +40c
10
Final part of old roof replaced with addition of new 1 st Storey roof – February 2010 Finally the last of the timber singles!!!
11
With the final part of the roof replaced, the last big cleanup of all the 100+ years of accumulated dust, possum poo, birds nests, etc from the classroom below
12
More scaffolding as the stairway and lift get built.
13
Sisalation being added, under black plastic is plaster boards ready for March construction.
14
Roof, spouts, drainage and sisalation February 2010
15
1 st Floor data, electrical, phone installation Solar panels on roof - February 2010
16
Plumbing, air conditioning February 2010 Kos installing ducting.