Presentation is loading. Please wait.

Presentation is loading. Please wait.

7th CWRF 2012 Workshop - BNL, May 7-11, 2012

Similar presentations


Presentation on theme: "7th CWRF 2012 Workshop - BNL, May 7-11, 2012"— Presentation transcript:

1 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
The Lessons Learned Commissioning a New Klystron & Current Status of the ALS Storage Ring RF System Upgrade So Far ! Kenneth Baptiste Group Members: S. Kwiatkowski (Group Leader) J. Julian, M. Vinco Lawrence Berkeley National Laboratory 1 1

2 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Outline Scope, Schedule & Status of the SRRF Upgrade Lessons Learned Waveguide Coupler Calibration, Klystron Flange, Adequate Test Load Mod-Anode PS Ripple Cathode HVPS Turn-On Transient Electrostatic Shielding Filament PS Stability Mod-Anode Voltage Control during Cathode HVPS Fast Fault (Crowbar) Klystron Recovery - HV Conditioning First 2 Months of Operation 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 2

3 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Upgrade Scope Phase I: a. Order 3 Thales 300kW klystron, install & operate 1, install 1 off- line, 1 spare b. Run Philips 330kW klystron until Dec. 2012 c. 2nd 6 week installation shutdown (Jan. 3 – Feb ) d. Run 1st Thales klystron for 500mA User Op’s until 1st Qtr 2013 e. Beginning in Spring 2012 disassemble Philips klystron & assemble 2nd Thales klystron off-line Phase II: a. Order a new HVTR/PS to modify HVPS to b. ~8 week installation shutdown (1st Qtr 2013) c. Replace Crowbar/Filter cabinet with new HV Disconnect Switch/Filter cabinet d. Replace 3-4 ILC’s with PLC control system e. Run either Thales klystron for 500mA User Op’s until 1 Qtr 2014 Phase III: a. Modify waveguide distribution (1 klystron per cavity, full power klystron test, either klystron driving both cavities) b. Install new digital Low Level RF system c. Install new RF Signal Diagnostic System 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 3 3

4 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Existing SR RF System 80W 300 kW 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 4

5 SRRF Upgrade, when Completed
7th CWRF 2012 Workshop - BNL, May 7-11, 2012 5

6 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
RF Upgrade Layout Klystron Site #2 Circulator Cav 1 & HOM Filter Cav 2 & HOM Filter CirculatorLoad Klystron Site #1 HV Dis-Con SW & Filter Magic-T & Switches Test Load Operating Options: Kly #1 to Cav 1 (to 200kW) Kly #1 to both Cavs (300 kW) Kly #2 to Cav 2 (to 200kW) Kly #2 to both Cavs (300 kW) Either Kly to Testload (300 kW) 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 6

7 Upgrade Schedule Shutdown Shutdown Shutdown TBD Shutdown TBD Phase I
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q Order new Klystrons Phase I Install 1st Klystron Test Kly’s 1 & 2 Run on Existing Philips Klystron Run new Kly #1 Phase II Replace Crowbar-Filter w/HV Dis-Con Sw-Filter Design, Build & Test HV Dis-Con Sw/Filter Cabinet Addition of Insertion Device(s) Shutdown Shutdown Shutdown TBD Shutdown TBD Order new HVTR/PS Modify HVPS Phase III Modify Waveguide Install new LLRF Design, Build & Test Low Level RF & Controls Test Kly3 Run on Two new Klystrons 7 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 7 7

8 Phase I - Status (Completed)
Mod-Anode Cabinet Klystron Site #2 Completed PLC IP PS Drv Amp Foc PS 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 8 8

9 Phase II - Status (in progress)
Klystron Site #1 Filter, HV Dis-Con SW & MA Cabinets Filter Cabinet 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 9

10 Phase II - Status (in progress)
IGBT Module 4kV, 40A See Presentation this afternoon... High Voltage Power Supply for the ALS Storage Ring RF system-Disconnect Switch Status Slawomir Kwiatkowski Filter Cabinet HV Dis-Con Switch Cabinet (24 modules) HVTR/PS Replacement 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 10

11 Phase III – (in conversation) Low Level RF Plan
Signal Conditioning Onboard – driven by packaging Offboard – modularity, keep close to cavity Larry Doolittle: Engineer Low Level RF Controls Flexible Platform BPM RF Phase & Amp Monitors Feedback Systems Why Digital? No drift Perfect calibration Can be accurately simulated/modeled Can add remote control & diag Extra features are cheap, don’t compromise reliability Why NOT Digital? Adds >150 ns latency, can effect closed loop dynamics >-150dBc/Hz added noise, ADC Recent Experience APEX VHF Gun RF 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 11

12 Commissioning New Klystron
Lessons Learned 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 12

13 Klystron Output Flange 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Waveguide Klystron Output Flange Klystron Output Flange Spec’d flange type Wrong flange delivered Sent drawings to manufacturer Spacer 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 13

14 Waveguide Coupler Calibration & Test Load
We have (2) 225kW Waveguide Water Wedge Loads Circulator Reject and Magic-T Reject Placed short on Output Port 1 of Magic-T Placed 45° section and short on Output Port 2 of Magic-T The problems Could not increase the cooling flow high enough as we have reduced flow for normal op’s (~40kW dissipated). VSWR effected as cooling flow increases. Could not get to saturated power. FWD & REV Power Coupler Spec’d coupling factors 0.4dB error I didn’t check before installing WR1800 Wedge Water Load 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 14

15 Waveguide Kly Flange, F/R Cplr, Test Load
Lessons Learned Waveguide – The problem with standards is that there are too many to choose from! CHECK, DOUBLE CHECK and the CHECK AGAIN! FWD/REV Power Coupler – CHECK, DOUBLE CHECK and the CHECK AGAIN! Test Load - If you want to check a new amplifier after delivery and installation make sure you have a rock-solid full power test load. 50Ω ,Stable Match, Adequately Cooled for Full CW power test. You don’t want any worries about the load when you’re testing new amplifier. 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 15

16 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Mod-Anode HV PS Ripple Vk = -54kV, Ik = 9A RFΦ = 9.25°/A Va, 2.5kV/A Va, 270V/° Vk = -50kV, Ik = 7.3A RFΦ = 8.25°/A Va, 2.7kV/A Va, 330V/° Design Goal = <0.1° Va-ripple < 27Vpp Thales TH2161L Va = 30 kV, Vripple = 120Vpp !! Va = 20 kV, Vripple = 120Vpp !! Cap Charger as DC HVPS 12.5mA App Note 505 Switching Freq = 40kHz 1st Filter Design Lessons Learned 1. The regulator for the constant current source contributes low freq ripple (a few kHz). Not mentioned in Manufacturer Data Sheet or App Note. 2. Va <22kV Not Good for User Beam Operations. 3. Fortunate, since Va in range of 24kV – 35kV for User Beam Operations. 4. Need a better filter for 70kHz. 2st Filter Design, 50kΩ Power Supply 12.6nF 4.2nF 15MΩ Va = 30 kV, Vripple = 10Vpp 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 16

17 Cathode HVPS Turn-On Transient
Turn-On Conditions Klystron connected HVTR/PS input = 2.5kVAC HVTR/PS output = -48kV 25ms -28kV after 250ms Vk Icap IPS HVTR – 12 Pulse Rectifier – L/C Filter 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 17

18 Electrostatic Shielding 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Mod-Anode Hot Deck Open Frame Hot Deck for visibility & maint Suseptable to E-Fields, Installed shielding panels Initially installed partially shielded cables Replaced with shielded cables Unshielded MA HVPS Enable Divider Replaced with compensated divider PLC FOX MA PS Fil PS 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 18

19 Electrostatic Interference
Filament PS – Configurable Linear PS Output Over-Voltage Protection Disabled & replaced functionality w/PLC Output Over-Current Protection Disabled & replaced functionality w/Fuse & PLC Current Mode Control Op-Amp Connected Op-Amp inputs to defined V had unconnected inputs per to properly disable factory config instructions Delayed Interference Remains Plan to switch to Current Mode Control ATE 15-50M 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 19

20 Electrostatic Shielding 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Lessons Learned Transient due to HVPS Turn-On – Though I was aware of this transient, I didn’t fully appreciate its affect and thought the initial shielding of the electronics and commercial ps was good enough. If we could afford it, I would change the front-end of our HVPS to have a soft-start. Electrostatic Interference/Shielding – I tried to save a few k$ by making a HV Divider and I routed cables away from high E-Field regions. In the end, this cost us over a week in commissioning time! If I could do this again I would schedule transient test time on new electronics prior to connecting Klystron. 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 20

21 Mod-Anode Voltage Control During Cathode HVPS Crowbar
Initial Issue: MA PS Enable Voltage Divider Interference After ~20 hrs of RF testing with intermittent divider decided to disconnect & rely on PLC only. Estimated turn off would be 2-3 PLC scan periods (~75ms) Had a vacuum event in klystron which triggered a Crowbar of Cathode HVPS. Had 2 more vacuum events in klystron at HV turn-on. MA interception? Consulted with Thales Field Engineer who offered several solutions Hot Deck + Va = 10 kV, Cath HVPS Crowbar MA PS Enable via PLC & HV Div, w/Clamp Diode, < 1us delay Va = 10 kV, Cath. HVPS Crowbar, MA PS Enable via PLC only ~100ms delay, plus ~800ms decay Va = 10 kV, Cath HVPS Crowbar, MA PS Enable via HV Dic only ~1ms delay, plus ~800ms decay Filament Power Supply Va = 10 kV, Cath HVPS Crowbar, MA PS Enable via PLC & HV Div, w/Clamp Diode, < 1us delay Va = 10 kV, HV Turn-On, MA PS Enable via HV Div only ~1ms delay Va = 10 kV, HV Turn-On, MA PS Enable via PLC only ~80ms delay PLC - MA Power Supply 50kΩ 20kΩ + 12.6nF 4.2nF - 15MΩ Intrlk MA PS Enable Divider - Cathode Power Supply Replaced F.O Cables + 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 21

22 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Klystron Recovery HV Conditioning Klystron Re-connected (MA tied to Cathode) HV Conditioned, checked vacuum Significant outgassing observed HV Conditioned for ~60 hrs Several On/Off cycles to condition Klystron Dis-connected from Cath HVPS, MA HVPS & Fil. Hi-potted 3-4 hrs, checked vacuum No problems observed Ran Filament PS Initial turn-on vacuum current spike 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 22

23 Va Control during Vk Crowbar
Lessons Learned Va Control – Incorrectly “Thought” PLC was adequate and MA HVPS would pull down voltage when PS is disabled. It couldn’t, it had no means to accomplish this. Need to measure and “KNOW” before proceeding with “I THINK...” no matter how much pressure you’re under. Try to listen to other people and understand what they are saying. Its hard because you are so intent on solving “your” problem. HV Conditioning Have good vacuum monitoring of your Klystron as this enables one to carefully re-condition. Have patience 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 23

24 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Operation since Feb. 14, 2012 Hours on the Klystron Black Heat 339 (half of nominal filament current) Standby (nominal filament current) HV 2022 Transmit 1823 Klystron Operating Parameters Vk = -50.4kV Ik = 9.25A Va = 31.8kV Ia = 3.3mA Eff = 56.8% Gain = 40.3dB μP = 1.60 Beam Losses SRRF Faults 6 Crowbar Conduction issues Magic-T Arc Fast Vacuum Valve RF Intrlk (MPS) VVT Fan Spurious Crowbar HV SW Hi-potting -> Spurious Crowbar 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 24

25 7th CWRF 2012 Workshop - BNL, May 7-11, 2012
Thank you Acknowledgments: Max Vinco Slawomir Kwiatkowski Jim Julian Danny Holstein (Thales) 7th CWRF 2012 Workshop - BNL, May 7-11, 2012 25


Download ppt "7th CWRF 2012 Workshop - BNL, May 7-11, 2012"

Similar presentations


Ads by Google