Download presentation
Presentation is loading. Please wait.
1
Commissioning and preliminary results
ELENA ION SOURCE Commissioning and preliminary results Ana Megia. CERN. September 2015
2
Ana Megia. CERN. September 2015
3
Ana Megia. CERN. September 2015
ELENA Ion Source Design H+/H- production +/-100 kV Bias voltage Tungsten filament Decapole magnet Magnetic filter Pulsed extraction Currents of tens of µA Ana Megia. CERN. September 2015
4
Ana Megia. CERN. September 2015
High voltage Electronic signals Fiber optics Computer com. HIGH VOLTAGE AREA HIGH VOLTAGE CABINET GROUND CABINET PC Pepper-pot CONTROL UNIT CONTROL UNIT WS PC CT Puller Source MAINS FILAMENT PS - + PULSE GEN. Stepper motor trigger Measurement trigger Screen e- TTL to FO ARC PS - + QUADRUPOLE PSs WS measurement Calib. signal Current meas. Cam. Quadrup. PULLER PS 220V/400Hz conv. HIGH VOLTAGE PS (+/-100kv) PC Main trigger PC WS CONTROL PICOSCOPE Ana Megia. CERN. September 2015
5
Source characterization
Ana Megia. CERN. September 2015
6
Ana Megia. CERN. September 2015
Raw data Wire scanners Pepper-pot Current transformer Ana Megia. CERN. September 2015
7
Ana Megia. CERN. September 2015
Where to begin? H+/H- Arc voltage Arc current Gas flow Source voltage Puller voltage Quadrupole settings Ana Megia. CERN. September 2015
8
Ana Megia. CERN. September 2015
Wire Scanner analysis Pepper-pot analysis Ana Megia. CERN. September 2015
9
Ana Megia. CERN. September 2015
Results comparison (EIS-NP-SC-014) WIRE SCANNER PEPPER POT Ana Megia. CERN. September 2015
10
Ana Megia. CERN. September 2015
Results comparison (EIS-NP-SC-014) WIRE SCANNER PEPPER POT Ana Megia. CERN. September 2015
11
Ana Megia. CERN. September 2015
Results comparison (EIS-PP-SC-004) Ana Megia. CERN. September 2015
12
Ana Megia. CERN. September 2015
Results comparison (EIS-PP-SC-004) WIRE SCANNER PEPPER POT Ana Megia. CERN. September 2015
13
Ana Megia. CERN. September 2015
Results comparison (EIS-PP-SC-004) WIRE SCANNER PEPPER POT Ana Megia. CERN. September 2015
14
Ana Megia. CERN. September 2015
Results comparison (EIS-NP-SC-037) Ana Megia. CERN. September 2015
15
Ana Megia. CERN. September 2015
Results comparison (EIS-NP-SC-037) WIRE SCANNER PEPPER POT Ana Megia. CERN. September 2015
16
Ana Megia. CERN. September 2015
Results comparison (EIS-NP-SC-037) WIRE SCANNER PEPPER POT Ana Megia. CERN. September 2015
17
Source re-installation
Ana Megia. CERN. September 2015
18
Ana Megia. CERN. September 2015
19
Ana Megia. CERN. September 2015
20
Ana Megia. CERN. September 2015
What’s next? Regarding previous measurements: Improve the ellipse fitting. Analysis of all results. Is it possible to get better RMS Emittance values?? Determine new interesting points to be measured. Analyze Pepper-pot images for all the measurement points. Ideas are welcome. Waiting for some parts from Jülich (HV cables & safety hood). September 2015 Measurement plan for the source and the ion switch (Daniel Barna) Timing and Oasis. Integration of the source in the AD control system? Regarding source future operation: Ana Megia. CERN. September 2015
21
Ana Megia. CERN. September 2015
Timing Ana Megia. CERN. September 2015
22
? OPTION I: LOCAL CONTROL (€) OPTION II: REMOTE CONTROL (€€€) 5000 €
PICOSCOPE CURRENT TRANS. CONTROL UNIT PULLER PS PULLER Trigger cable PULSE GEN. WS STEPPER MOTOR WS CONTROL WS MEAS. Local control of the source parameters OPTION II: REMOTE CONTROL (€€€) ? PICOSCOPE CURRENT TRANS. Trigger cable CONTROL UNIT PULLER PS PULLER PS Serial cable CONTROL TEST STAND WS STEPPER MOTOR Ethernet 5000 € WS CONTROL 1805 € WS MEAS. Source parameters controlled from the control room by remote desktop app Ana Megia. CERN. September 2015
23
Ana Megia. CERN. September 2015
OPTION III:LOCAL CONTROL PREPARED FOR FUTURE REMOTE CONTROL (€€) PICOSCOPE CURRENT TRANS. Trigger cable CONTROL UNIT PULLER PS PULLER Serial cable PULSE GEN. Ethernet WS STEPPER MOTOR 1805 € WS CONTROL WS MEAS. Source parameters controlled from the control room by remote desktop app OPTION IV: INTEGRATION OF THE SOURCE (€€€€) OPTION II + man power Ana Megia. CERN. September 2015
24
Ana Megia. CERN. September 2015
QUESTIONS FROM TIMING TEAM Will the source be always operated in pulsed mode? If so, which are the maximum and minimum frequency and pulse length? Once the commissioning is finished and ELENA is connected to the AD ring, will the source need to be synchronized with the AD beam? Ana Megia. CERN. September 2015
25
Ana Megia. CERN. September 2015
Oasis Ana Megia. CERN. September 2015
26
Extraction pulse trigger
PICOSCOPE OASIS Picoscope trigger Main trigger CT calibration signal CT calibration signal Ion current Ion current Extraction pulse trigger Wire scanner signal Ana Megia. CERN. September 2015
27
Comments… Cable request deadline 25th September !
Ana Megia. CERN. September 2015
28
Ana Megia. CERN. September 2015
29
Ana Megia. CERN. September 2015
H- preliminary results Ana Megia. CERN. September 2015
30
Ana Megia. CERN. September 2015
H+ preliminary results Ana Megia. CERN. September 2015
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.