K.Gadow 19.04.2007 CALICE technical review 1 Move to FNL ECAL/HCAL-Movable Table Setup test beam integration to Fermilab MT6-B3/B4.

Similar presentations


Presentation on theme: "K.Gadow 19.04.2007 CALICE technical review 1 Move to FNL ECAL/HCAL-Movable Table Setup test beam integration to Fermilab MT6-B3/B4."— Presentation transcript:

1 K.Gadow 19.04.2007 CALICE technical review 1 Move to FNL ECAL/HCAL-Movable Table Setup test beam integration to Fermilab MT6-B3/B4

2 K.Gadow 19.04.2007 CALICE technical review 2 ECAL/HCAL Movable Table Setup no change in basic dimension

3 K.Gadow 19.04.2007 CALICE technical review 3 Setup in test beam area update beam area ground dimension HCAL Movable Table placed in MTB6-B3 ? ECAL/HCAL Movable Table Control room ?

4 K.Gadow 19.04.2007 CALICE technical review 4 Setup in test beam area inner height ? other equipment ? shielding concrete roof support dump

5 K.Gadow 19.04.2007 CALICE technical review 5 Setup in test beam area one escape route is sufficient ? Escape rote from B4 blocked

6 K.Gadow 19.04.2007 CALICE technical review 6 Setup in test beam area crane height and crane load critical needed hook height over roof 4 m transport weight 15 tons

7 K.Gadow 19.04.2007 CALICE technical review 7 Setup in test beam area total height ~ 4 meter

8 K.Gadow 19.04.2007 CALICE technical review 8 Setup in test beam area permanent closed roof (except openings) installation of Movable Table HCAL and ECAL with “tricks” only installation of HCAL modules in position B3 critical crane needed !

9 K.Gadow 19.04.2007 CALICE technical review 9 Infrastructure at Fermilab (Joe Howell)  Power Conversion –Experiment 2 x 50 Hz 400 VLL 25-32 A –Standard Fermilab 60 HZ, 208v/120v or 480v –Initial checks indicate there is no existing on- site conversion equipment –Continue checking options  Data Transfer –Desire at least 1 Gbit/s Eathernet Link –Erik Ramberg is checking current capacity

10 K.Gadow 19.04.2007 CALICE technical review 10 Operations Readiness Clearance (Joe Howell)  Approval given by the Fermilab Partical Physics Division Head indicating that the experiment is safe to operate  Safety Review Committees –Mechanical and Conventional Safety –Electrical –Fire (and flammable gas)  Documentation Review and Equipment Inspection  Help provided to guide through the process