Pradhan Mantri Gram Sadak Yojana
Review Meeting for Bihar, Jharkhand, Odisha & West Bengal at Bhubneshwar 3-4 November, 2015
2
Rural Roads Profile 1 Bihar T- 1,30,642 S- 57,198 34,509 2 Jharkhand
(Length in km) S.No. State (s) Total Rural Road Network Length Total Length completed under PMGSY (Upto Sept.15) 1 Bihar T- 1,30,642 S- 57,198 34,509 2 Jharkhand T-23,903 S-16,379 11,916 3 Odisha T- 2,58,836 S-58,719 33,981 4 West Bengal T- 2,99,209 S-1,15,534 18,538 Source:- MoRTH (2011) T - Total S – Surfaced
3
Physical Target and Achievement (2014-15)
S.No. State (s) Length (Km) - NC + UG Physical Target for Length achieved upto Mar'15 Average Length construction per day 1 2 3 4 5 Bihar (RWD) 2900 9.36 Bihar (NEAs) 217.13 0.59 Jharkhand 703 4.80 Odisha 2400 10.53 West Bengal 1850 6.12
4
Physical Target and Achievement (2015-16 -Upto Sept. 15)
S.No. State (s) Length (Km) - NC + UG Physical Target for Length achieved upto Sept'15 Average Length construction per day 1 2 3 4 5 Bihar (RWD) 3200 8.61 Bihar (NEAs) 19.88 0.11 Jharkhand 1240 612.57 3.35 Odisha 2350 8.71 West Bengal 1500 546.17 2.98
5
Maintenance Status (2014-15 & 2015-16)
(Rs. In Crore) Sr.No. State (s) Year Amount Required as per Contract Amount Credited in SRRDA Account (Upto Sept.15) Amount Utilized % Achievement w.r.t Amount required w.r.t Amount credited 1 Bihar 591.68 402.40 351.05 59% 87% 2 Jharkhand 60.10 60.00 14.97 25% 3 Odisha 124.56 101.00 58.16 47% 58% 4 West Bengal 79.91 34.63 44.41 56% 128%
6
Amount Required as per Contract Amount Credited in SRRDA Account
Statement Showing Maintenance Funds Required/ Received and Expenditure incurred under PMGSY (Upto Sept 15) (Rs. In Crore) S.No STATE (S) Amount Required as per Contract Amount Credited in SRRDA Account (Upto Sept.15) Amount Utilized % Exp. W.r.t Required % Exp. W.r.t Releases 1 Bihar 138.26 59.62 45.68 33% 77% 2 Jharkhand 28.62 0.00 7.3 26% - 3 Odisha 56.79 53.00 34.48 61% 65% 4 West Bengal 41.67 19.81 48% No amount credited in in SRRDA account by Jharkhand and West Bengal.
7
State Policy on Maintenance
States to notify their Rural Roads Maintenance Policies (RRMPs). A Model Policy Framework for Maintenance of Rural Roads along with a Guidance Note has already been circulated to States. So far, only nine States (Assam, Bihar, Chhattisgarh, Himachal Pradesh, Madhya Pradesh,, Rajasthan, Tamil Nadu, Uttar Pradesh and Uttarakhand) have notified such Policies. Jharkhand, Odisha and West Bengal to notify RRMPs.
8
Maintenance Module of OMMAS
Maintenance Sub Module Technical Receipts and Payments Training on “Maintenance Sub Module” concluded in April 2015 (Bihar & Jharkhand have participated).
9
Maintenance Sub Module - Agreement
Physically completed roads available for Maintenance Agreement Provision to continue with Same Contractor or With New Contractor Year wise Maintenance Cost to be provided for the Maintenance Agreement Maintenance Agreement provision for “During Liability Period” and “Post Liability”
10
Maintenance Fund – Receipts and Payments
Pre-requisites SRRDA Bank Account Details of Maintenance Fund Opening Balances, Receipt of Grant, Issue of Authorization to PIU. PIU The Contractor details must be Present in the Contractor Master. The works in the Proposal module must be Sanctioned by MoRD and Physically Completed as per Execution module Agreement details under Maintenance sub-module must be Entered and Finalized. Authorized Signatory details, Bank Details and Cheque book details mandatory Bank Authorization balance required for posting vouchers
11
Maintenance Fund – Receipts and Payments module
Maintenance Fund Accounts module Status as on 30th October, 2015 Sr.No. State (s) Total PIUs No of PIU Online Entry completed by first PIU Entry completed by last PIU 1 Bihar 102 29 March,2011 August,2015 2 Jharkhand 55 5 April,2013 April,2015 3 Odisha 65 56 March,2014 4 West Bengal 32 23 States have to provide – date by which all PIUs would be Online date by which Entries upto September,15 would be completed.
12
Use of Geo-Textiles, Waste Plastic & Cold Mix in roads under PMGSY
Usage of Geo-Textiles, Waste Plastic & Cold Mix in roads particularly rural roads is a proven environment friendly technology for increases durability and reduced maintenance cost of roads. Ministry of Rural Development and Ministry of Textiles have agreed to collaborate in using Geo-Textiles in Rural Roads. Ministry of Textile has designated Centres of Excellence for Geo-Textiles at Ahmedabad, Kolkata and Mumbai. Ministry of Rural Development has issued targets for for use of Waste Plastic & Cold Mix for each State.
13
Status of R&D Sanctions and Progress (2012-13 to 2015-16)
Sr.No. State (s) Sanctioned Completed Total Road Length (in Km) Amount (Rs. In Lakhs) Length 1. Bihar 380.42 19.10 1539.2 2. Jharkhand 84.33 1.00 63.43 3. Odisha 357.83 - 4. West Bengal 98.07 13.42 855.42 Note: As per NRRDA records.
14
Environmental & Social Management Framework (ESMF) and Environmental & Social Standards (ESS)
World Bank’s Environmental & Social Management Framework (ESMF) for its projects is to be replaced by an integrated set of 10 Environmental & Social Standards (ESS). Impact of ESS on – cost of the projects, timelines of the projects and overall project implementation (5 - 7 slides).
15
CBR Digital MAP on OMMAS
To serve as management tool for the States. Digitized block boundaries, district boundaries to be provided. Missing CBR Values, in proposal module to be uploaded. CBR Digital Map feature is available on SRRDA & ITNO login under “ Dashboard” menu.
17
Feedback on PMGSY works received on OMMAS portal
“Meri Sadak – Citizen Feedback System” A new “Citizen Feedback Module” “Meri Sadak” has been created in public domain of OMMAS Homepage for registering feedback and complaints by citizens. To meet the objectives of E-governance and Digital India, a new Mobile App “Meri Sadak” integrated into OMMAS for user friendly and transparent Citizen Feedback and complaint redressal system under PMGSY. The citizens, with the use of this feedback module, can express their concerns related to slow pace, abandoned work, bad quality of PMGSY works.
18
Feedback on PMGSY works received on OMMAS portal under
“Meri Sadak – Citizen Feedback System” State Quality Coordinators (SQCs) will be the ‘Nodal Officer’ to handle feedback module and will dispose off the feedbacks received under “Meri Sadak” of OMMAS portal, online (7 days to 60 days). A SOP (Standard Operating Procedure) has been developed which describes the steps for handling feedbacks submitted by Citizen and uploaded on PMGSY website ( As per timeline for prompt feed back redressal, all feedback should be: Acknowledged within 07 days with interim reply. Redressed within 60 days of receipt in the organization. States may ensure disposal of feedback in time bound manner without compromising on quality aspects.
19
Feedback Received Date Final Reply Submission Date
Feedback Pendency State: Bihar (As on date ) S. No. Complainant Name Feedback Received Date Interim Reply Date Final Reply Submission Date Status 1 Sanjay Rai Final reply awaited 2 Abdullah 3 Ravindra Kumar Reddy 4 Rohit kumar 5 Md Akhlaqur Rahman 6 Dhiraj Ray 7 Chandan kumar - Not replied
20
Feedback Received Date Final Reply Submission Date
Feedback Pendency State: Odisha (As on date ) S. No. Complainant Name Feedback Received Date Interim Reply Date Final Reply Submission Date Status 1 Mirza Sartaz - Not replied
21
Feedback Received Date Final Reply Submission Date
Feedback Pendency State: West Bengal (As on date ) S. No. Complainant Name Feedback Received Date Interim Reply Date Final Reply Submission Date Status 1 Somnath Das - Not replied 2 Rajkiran Baraik 3 Asmita Poddar 4 Md Jasim Uddin 5 Saifuj Jaman
22
Pradhan Mantri Gram Sadak Yojana
REV I EW MEET NG Pradhan Mantri Gram Sadak Yojana Bihar, Jharkhand, Odisha and West Bengal at Bhubneshwar 3-4 November, 2015
23
Compliance of Last Review Meeting held at Guwahati/New Delhi (February/ March, 2015)
24
Action Taken by the States
All participating States during their last RRM has assured for the following:- Deposit 100% funds in the SRRDA Maintenance Account by 31st March, Odisha Odisha would reconcile the data related to eligible unconnected habitations and balance unconnected habitations and upload on OMMAS by 31st March, 2015. Submit Comprehensive Annual Action Plan for “Swatch Bharat Abhiyan” by 30th April, 2015 for the year Reconciliation of Habitation data by 30th April, 2015 – Bihar and West Bengal. Re-checking the value of awarded works entered on OMMAS by 30th April, 2015 – All States. Reconciliation of Habitation data by 31st May, Jharkhand.
25
Trends of Physical Completion of Roads (in km)
B I H A R R W D
26
B I H A R R W D Physical Progress as per OMMAS Total: 12399 34245.05
Year (s) Total No. of Road Works/ Bridges sanctioned Total length of Road Works (in Km) sanctioned Total No. of Road Works / Bridges completed (in Km) constructed No. of Works completed upto Last Review Meeting (March 15) No. of Road works yet to complete 298 861.87 282 819.32 16 671 1531.8 600 1383 597 71 4 53.59 3 38.34 1 271 222 219 49 4576 3658 3583 918 670 430 383 240 1446 760 652 686 4463 619 230 3844 Total: 12399 6574 5949 5825 B I H A R R W D 1055 in-complete road works till is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
27
B I H A R R W D Physical Progress as per OMMAS under WB RRP-II 2013-14
Year (s) Total No. of Road Works/ Bridges sanctioned Total length of Road Works (in Km) sanctioned Total No. of Road Works / Bridges completed (in Km) constructed Works completed upto Last Review Meeting (March 15) No. of Road works yet to complete 956 123 259.97 11 833
28
Trends of Financial Progress ( Release / Expenditure in Rs Crore)
B I H A R R W D
29
Trends of Physical Completion of Roads (in km)
J H A R K H A N D
30
J H A R K H A N D Physical Progress as per OMMAS 3822 15315.42 2276
Year (s) Total No. of Road Works/ Bridges sanctioned Total length of Road Works (in Km) sanctioned Total No. of Road Works / Bridges completed (in Km) constructed Works completed upto Last Review Meeting (March 15) No. of Road works yet to complete 167 897.66 202 201 131 647.24 128 618.74 127 3 102 479.19 94 408.39 93 8 352 298 297 54 666 3093.5 544 539 122 896 633 276 263 415 136 26 279 71 316.44 39 5 32 820 35 97.454 785 Total 3822 2276 1731 1546 J H A R K H A N D 450 in-complete road works till is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
31
J H A R K H A N D World Bank RRP-I – Already completed
World Bank RRP-II – As per OMMAS Year (s) Total No. of Road Works/ Bridges sanctioned Total length of Road Works (in Km) sanctioned Total No. of Road Works / Bridges completed (in Km) constructed Works completed upto Last Review Meeting (March 15) No. of Road works yet to complete 174 696.91 67 280.24 29 107 848 329 860.58 123 519 Total 1022 396 152 626
32
Trends of Financial Progress ( Release /Expenditure in Rs Crore)
No Funds released during J H A R K H A N D
33
Trends of Physical Completion of Roads in km
Odisha Trends of Physical Completion of Roads in km 8,889 road works i/c Bridges completed out of 11,936 and 75% length completed
34
Physical Progress as per OMMAS- Normal
Odisha Physical Progress as per OMMAS- Normal Year (s) Total No. of Road Works sanctioned Total length of Road /LSB Works cleared (in Km) Total No. of LSB Works sanctioned Total No. of Road / LSB Works completed Total length of Road Works constructed (in Km) Works completed upto Last Review Meeting (Feb. 15) No. of Road works yet to complete 521 519 2 571 630 620 616 10 418 406 401 12 486 474 460 443 423 408 20 1689 1568 1521 121 1432 74 1341 1224 165 122 585.69 60 141 418.25 77 41 1283 827 487 456 1334 599 181 735 10.68 27 1.27 114 Total 8929 275 7516 6465 1688 383 in-complete road works till is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
35
Physical Progress as per OMMAS- ADB
Odisha Physical Progress as per OMMAS- ADB Year (s) Total No. of Road Works sanctioned Total length of Road Works cleared (in Km) Total No. of LSB Works sanctioned Total No. of Road Works completed Total length of Road Works constructed (in Km) Works completed upto Last Review Meeting (Feb. 15) No. of Road works yet to complete 261 253 247 8 400 372 370 28 644 560 545 84 284 131 466.97 153 1131 17 78.24 1120 Total 2720 1344 5642.4 1190 1393 120 in-complete road works till is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
36
Trends of Financial Progress ( Release / Expenditure in Rs Crore)
Odisha Trends of Financial Progress ( Release / Expenditure in Rs Crore)
37
Trends of Physical Completion of Roads (in km)
3,580 road works i/c Bridges completed out of 4,982 and 73% length completed W E S T B E N G A L
38
W E S T B E N G A L Normal PMGSY - Physical Progress as per OMMAS
Year (s) Total No. of Road Works/ Bridges sanctioned Total length of Road Works (in Km) sanctioned Total No. of Road Works / Bridges completed (in Km) constructed Works completed upto Last Review Meeting (March 15) No. of Road works yet to complete 170 808.9 212 1124.6 363 149 952.5 230 1645.8 226 225 4 335 306 302 29 482 420 415 62 280 217 208 63 231 120 110 111 1411 827 664 584 467 28 62.69 1 439 Total 4330 3038 2819 1292 W E S T B E N G A L 158 in-complete road works till is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
39
W E S T B E N G A L ADB- Physical Progress as per OMMAS
Year (s) Total No. of Road Works/ Bridges sanctioned Total length of Road Works (in Km) sanctioned Total No. of Road Works / Bridges completed (in Km) constructed Works completed upto Last Review Meeting (March 15) No. of Road works yet to complete 104 792.72 109 908.09 100 807.56 9 127 695.72 120 653.12 7 76 443.49 72 420.26 4 15 82.26 34.13 8 14 84.17 12 75.53 11 2 130 930.08 64 337.54 45 66 637.57 Total 651 479 459 172 W E S T B E N G A L 20 in-complete road works till is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
40
Trends of Financial Progress ( Release /Expenditure in Rs Crore)
W E S T B E N G A L No Funds released during
41
Fund Released by States w.r.t State Share
All Cost in Lakh) Sr. No. State Name State Cost Total Cost Fund Released by State Month Closed 1 Bihar 53,948.67 28,46,902.07 0.00 Mar-15 2 Jharkhand 23,852.04 6,80,526.71 7,782.20 Sep-15 3 Odisha 41,592.52 17,81,815.03 71,061.00 Jun-15 4 West Bengal 11,06,489.66 451,7.6 Aug-15
42
Details of Road works Sanctioned as New Technology (R&D) Projects under PMGSY
1. Details of R&D being presented in the next slides are as per records of NRRDA. However, these details have not been updated by the States on OMMAS. The length and cost of new technology portion is to be updated by the State, which has not been done in most of the cases or incorrect information updated Photographs, performance reports etc. are also to be uploaded for such works. In most of the cases photographs and performance reports are not being uploaded by the States.
43
Details of road works sanctioned as New Technology (R&D)
S.No. State (s) Value (in lakh) Roads Length (in Km) Technology Year of Sanction 1 Bihar 364.44 7.25 Silicon Aggregate 483 380.42 RCCP, Soil Stabilization, Fly Ash, Cold Mix, Cell Filled Total: 484 387.68 2 Jharkhand 442.35 10.13 RBI Grade 81 25 74.20 RI Grade 81 & RCCP 27 84.33
44
Details of road works sanctioned as New Technology (R&D)
# State (s) Nos. of Road Length in Km. Cost in Rs. Lakhs Type Year of Sanction 3 Odisha 2 9.5 500.23 JGT 95 351.70 Cold Mix / Iron Slag/ RCCP Total: 97 361.20 - 4 West Bengal 2 10.5 426.96 JGT 24.38 Cell filled, RBI 20.8 5 24.41 3 16.23 992.91 JGT, Cold Mix 6 40.92 RBI, JGT, Cold Mix Total: 24 137.24
45
Physical and Financial Progress under IAP
46
Habitation Connectivity for the IAP Districts as on September, 2015
S.No. Name of State (s) No. of Districts No. of eligible Habitations under PMGSY No. of Habitations cleared under PMGSY No. of Habitations connected under PMGSY No. of Habitations connected under other schemes, if any 1 Bihar 11 14529 8015 4627 1218 2 Jharkhand 17 9195 6914 3704 661 3 Odisha 18 13121 9067 6301 207 4 West Bengal 03 5963 4239 2702 Total: 49 42808 28235 17334 2086 Physical Progress for the IAP Districts SI. No. Name of State (s) No. of District No. of roads sanctioned No. of road works completed Length of road works sanctioned (in km) Length of roads completed (in km) 1 Bihar 11 5473 3146 (65%) 2 Jharkhand 17 3675 1975 (58%) 3 Odisha 18 7422 5383 (73%) 4 West Bengal 03 1504 751 (57%) Total: 49 18074 11255 (66%)
47
Financial Progress for the IAP Districts as on September, 2015
Sl. No. Name of State (s) No. of Districts Value of Projects cleared (Rs. in Crore) Expenditure incurred (Rs. in Crore) 1 Bihar 11 (63%) 2 Jharkhand 17 (64%) 3 Odisha 18 (75%) 4 West Bengal (50%) Total: 49
48
Maintenance - Financial
49
PC I S U R V E Y Pavement Condition Index [PCI] Data Entered
Pavement Condition Index [PCI] Data Entered % PCI Data Entered State (s) Target for PCI Data to Enter PCI Data Entered for Length with PCI Value Year-wise Length Number of Rural Route Roads Total Length Number of Roads 1 2 3 4 5 Bihar 23,256 74,244 20,178 73,210 14,201 13,295 19,016 18,981 7,717 13,025 44,700 15,485 81% Jharkhand 9,535 41,764 7,504 51,557 11,338 14,031 13,987 8,409 3,792 22,412 6,060 23,085 70% Odisha 18,915 85,427 16,922 1,41,881 24,244 40,792 32,462 26,445 17,939 38,625 49,615 53,640 121% West Bengal 13,056 55,210 3,628 14,445 3,891 5,151 2,713 1,578 1,111 2,307 9,435 2,703 22% Total: PC I S U R V E Y
50
Maintenance - Financial
Year (s) Maintenance Funds Required (As per Contracts) Actual Fund Release to SRRDA Expenditure by SRRDA during the Year % Expenditure w.r.t maintenance funds Required 94.33 56.25 91.60 97% 121.23 102.92 85% 453.42 342.78 305.37 67% (Upto Sept. 15) 138.26 59.62 45.68 33% Total: 807.24 579.88 545.57 68% (Rs. In Crore) B I H A R
51
Maintenance – Financial
Year (s) Maintenance Funds Required (As per Contracts) Actual Fund Release to SRRDA Expenditure by SRRDA during the Year % Expenditure w.r.t maintenance funds Required 20.58 52.00 0.96 5% 25.13 0.00 3.97 16% 31.48 60.00 7.67 24% (Upto Sept. 15) 28.62 7.3 26% Total: 105.81 112.00 19.9 19% (Rs. In Crore) J H A R K H A N D
52
Maintenance – Financial
Rs. In Crores Financial Year(s) Maintenance Funds Required (as per contracts) Actual release to SRRDA Expenditure by SRRDA during the Financial Year % Expenditure w.r.t fund required 40.00 35.48 89% 59.61 41.40 37.15 62% 67.77 48.00 23.68 35% (Upto Sept. 15) 56.79 53.00 34.48 61% Total: 224.17 182.40 130.79 49% O D I S H A
53
Maintenance - Financial
(Rs. In Crore) Financial Year (s) Maintenance Funds Required (As per Contracts) Actual Fund Release to SRRDA Expenditure by SRRDA during the Year % Expenditure w.r.t maintenance funds Required 27.35 83.59 81.14 100% 81.31 29.67 22.66 28% 38.24 34.63 24.59 64% (Upto Sept. 15) 41.67 0.00 19.81 48% Total: 188.57 147.89 148.2 79% W E S T B E N G A L
54
Habitation Eligibility and Data Entry on OMMAS
55
Total Eligible Habitations % of Total Eligible Habitations
Eligible Habitations, Habitations Cleared and Connected (Since commencement – September. 2015) B A S E D O N M P R Total Eligible Habitations 1,78,184 Eligible Habitations of participating States 72,450 % of Total Eligible Habitations 41%
56
Unconnected Habitations Data Bihar
Item 1000+ 500+ 250+ 100+ Total Unconnected Habitations as on 14242 18080 6109 38431 Covered under State Schemes (as reported by the State) 1304 1745 745 3794 Net unconnected eligible habitations 12938 16335 5364 34637 Reported not feasible As per cabinet approval 13048 6506 5250 24804 Already sanctioned 17697 7789 1698 27184 Total number of Unconnected Habitations Entered (as per OMMAS Oct, 2015) 14247 18119 6661 68 39027 Balance Unconnected Habitations (as per OMMAS, Oct, 15) 8730 11762 4481 24973 CN 1 and CN 6 details with maps for 68 Habitations of 100+ are awaited from the State.
57
Unconnected Habitations Data Jharkhand
Item 1000+ 500+ 250+ 100+ Total Unconnected Habitations as on 2637 4327 3042 10006 Covered under State Schemes (as reported by the State) 862 973 412 2247 Net unconnected eligible habitations 1775 3354 2630 7759 Reported not feasible 3 As per cabinet approval 1876 4479 5258 11613* Already sanctioned 1867 3343 3259 8469 Total number of Unconnected Habitations Entered (as per OMMAS Oct, 2015) 1561 3981 4896 10438 Balance Unconnected Habitations (as per OMMAS, Oct, 15) 933 2341 2985 * State need to provide details of the habitations that these (3854) habitations are left out habitations of CN.
58
Unconnected Habitations Data Odisha
Item 1000+ 500+ 250+ Total Unconnected Habitations as on 3703 6715 7921 18339 Covered under State Schemes (as reported by the State) 78 11 124 213 Net unconnected eligible habitations 3625 6704 7797 18126 Reported not feasible 25 As per cabinet approval 3752 7341 11118 22211* Already sanctioned 3627 6009 2724 12360 Total number of Unconnected Habitations Entered (as per OMMAS Oct, 2015) 6741 5751 16195 Balance Unconnected Habitations (as per OMMAS, Oct, 15) 39 335 2056 2430 * State need to provide details of the habitations that these (4085) habitations are left out habitations of CN.
59
Unconnected Habitations Data
West Bengal Unconnected Habitations Data Item 1000+ 500+ 250+ 100+ Total Unconnected Habitations as on 12,790 10,142 2,965 25,897 Covered under State Schemes (as reported by the State) 4,232 3,024 7,256 Net unconnected eligible habitations 8,558 7,118 18,641 Reported not feasible As per cabinet approval 8,051 5,485 286 13,822 Already sanctioned 7,711 4,917 1,879 14,507 Total number of Unconnected Habitations Entered (as per OMMAS Oct, 2015) 181 17,736 Balance Unconnected Habitations (as per OMMAS, Oct, 15) 1,624 2,017 1,074 184* 4,899 * Now eligible as per MoRD’s advisory for 2 blocks in West Bengal
60
Updating of Data on OMMAS
States are requested to update their data on OMMAS particularly relating to habitations, DRRP, Core Network, Year wise sanctioned proposals, R&D, Maintenance, R&P Module etc latest by 31st December, 2015. All physical reports will be dispensed with and all reports will be taken from OMMAS directly. States will have to update their progress latest by 10th of next month on which all these reports will be taken from OMMAS.
61
Details of Awarded Works
In many cases data of awarded works entered by the PIUs does not appear to be realistic as it is more than 100% of the GoI sanctioned cost. Also in some cases the data entered is in Rupees, where as it should have been in Rs. In lakhs. This has been corrected from backend by NRRDA, however, the States need to verify and confirm that the data appearing on OMMAS is correct latest by 15th November, 2015. In many cases the data of award has not been updated on OMMAS. A check is being applied on OMMAS, so that details of award will have to be entered within 10 days from date of award
62
Bihar Jharkhand Odisha West Bengal
Quality Mechanism Bihar Jharkhand Odisha West Bengal Tier I II Tier III Tier
63
Action Taken by the States
All participating States during their last RRM has assured for the following:- Submit plan for pending ATRs 1st April 2013 to 1st April, 2014 to NRRDA, with the aim of reducing ATR pendency to zero.
64
1st tier Inspections accounted from Apr.,2015 to Oct.,2015.
II Tier III Tier 1st tier Inspections accounted from Apr.,2015 to Oct.,2015. (16%) Based on NQM observation
65
1st tier Status of Field Lab 2000-14 16722 5317 4977 1897(38.11%)
II Tier III Tier 1st tier Status of Field Lab State Period Involved Total Sanctioned works In Progress awarded works Packages Involved in awarded works Packages where Field Lab not established(in %) Bihar 16722 5317 4977 1897(38.11%) Jharkhand 4806 1961 1698 1575(92.75%)* Odisha 11371 2579 2205 2195(99.54%)* West Bengal 3983 1344 1333 812(60.91%) Consideration period starting from FY which involves at least one On going Works.
66
Sqm inspection summary Works Inspected in Last three months
Tier I II Tier III Tier 2ND tier Sqm inspection summary State No. Of SQM Empanelled No. Of SQM* Works Inspected in Last three months Works not Inspected Total July Aug. Sept Completed in Completed in Ongoing BR 111 51 605 1127 845 22 7 632 661 JH 60 32 157 168 62 1 3 325 329 OR 54 40 330 236 55 4 9 430 443 WB 49 213 98 151 418 421 * No. of SQMs who have uploaded Inspections in OMMAS during FY
67
Sqm inspection details
Tier I II Tier III Tier 2ND tier Sqm inspection details * Inspections taken in account from 01/04/2015.
68
3RD tier ATR Summary Pending ATR BR 266 140 195 11 101 JH 169 107 123
II Tier III Tier 3RD tier ATR Summary State Completed Ongoing Total Pending ATR Older than 01/10/2014 Older than 01/04/2015 Not Submitted BR 17 249 266 140 195 11 101 JH 14 155 169 107 123 9 85 OR 22 307 329 158 213 15 184 WB 21 150 171 98 113 6 43
69
3RD tier Quality Summary 13% 9% 5%
II Tier III Tier 3RD tier Quality Summary 13% 9% 5% Inspections taken in account from 01/04/2015.
70
Contracting Agencies involved in works inspected by NQMs
(For works awarded since Jan 2014 onwards) State No. of awarded works (in Progress) No. of awarded packages in Progress No of Contractors involved No. of Contractor for which at least One work inspected No. of Contractor whose works not inspected even once BR 776 753 316 21 295 JH 185 169 92 13 79 OR 672 564 346 36 310 WB 115 55 6 49
71
Unsatisfactory Works found by NQM
72
Finance and Accounting Issues
73
Action Taken by the States
All participating States during their last RRM has assured for the following:- Bihar and West Bengal - Submit OMMAS based Audited Balance Sheet of Programme Fund and Admin. Expenses Fund for the year by 30th April, 2015. Odisha - Submit Audit Report by 7th March, Bihar and Jharkhand - Clear all pending final bills by end of June, Odisha - Settle all pending final bills by end of April,
74
Finance & Account for F.Y 2014-15
Bihar Finance & Account for F.Y Submission of Annual Accounts The Balance Sheets of Programme Fund and Administrative Expenses Fund for the Year have not been submitted by the State. The Due date for submission was Action Taken Report of FY Action Taken Report for the year not furnished. ATR of also not furnished. Weaknesses in implementation of OMMAS Month for which entries has been completed in OMMAS (R&P Module) Programme Fund:- Sept. 2015 Administrative Fund:- Sept. 2015 Maintenance Fund:- Sept
75
Pending Financial Completion of Physically Completed Works
Bihar Pending Final Bills 1,837 number of physical completed works pending for financial completion. (i.e % out of 6,697 Physically completed works) Sanction Year Pending Financial Completion of Physically Completed Works 55 90 4 37 554 202 335 560 Total: 1,837
76
Finance & Account for FY 2014-15
Jharkhand Finance & Account for FY Submission of Annual Accounts The Balance Sheets of Programme Fund and Administrative Expenses Fund for the Year have not been submitted by the State. The Due date for submission was Action Taken Report of FY Action Taken Report for the year not furnished. Weaknesses in implementation of OMMAS Month for which entries has been completed in OMMAS (R&P Module) Programme Fund:- March 2015 Administrative Fund:- Aug 2015 Maintenance Fund:- Not Closed
77
Pending Financial Completion of Physically Completed Works
Jharkhand Pending Final Bills 662 number of physical completed works pending for financial completion. (i.e % out of 2,707 Physically completed works) Sanction Year Pending Financial Completion of Physically Completed Works 7 22 15 12 26 47 82 153 259 39 Total: 662
78
Finance & Account for F.Y 2014-15
Odisha Finance & Account for F.Y Submission of Annual Accounts Balance Sheet of Programme Fund received. Balance Sheet of Admin Fund received. Action Taken Report of FY Action Taken Report for the year has been furnished. However the replies have been incorporated in the observations of Balance Sheet of ATR on Ressidual observation of FY raised on not furnished. Observation in Financial Management of FY Excess expenditure of Rs. Rs crore have been met from Security Deposits of Contractors. TDS Rs Cr deducted by Bank on Interest Income : Despite of Exemption from tax DPR advance Rs Lac not adjusted Bank Guarantee Rs Cr expired and not revalidated from contractors.
79
Odisha Stale Cheques : Programme Fund: Rs. 7,00,62,189
Admin. Fund : Rs. 7,26,257 Non submission of Banker Certificate showing for accrued interest Unqualified Audit Opinion given by the Statutory Auditors despite of having various shortcoming in the Audit Report. Weaknesses in implementation in OMMAS Month for which entries has been completed in OMMAS (R&P Module) Programme Fund:- June 2015 Administrative Fund:- Aug 2015 Maintenance Fund:- Not closed
80
Pending Financial Completion of Physically Completed Works
Odisha Pending Final Bills 1,038 number of physical completed works pending for financial completion. (i.e % Out of total 8,865 physically completed works) Sanction Year Pending Financial Completion of Physically Completed Works 5 15 4 37 25 72 94 38 377 319 47 Total: 1,038
81
Finance & Account for F.Y 2014-15
West Bengal Finance & Account for F.Y Submission of Annual Accounts Balance Sheet of Programme Fund received. Balance Sheet of Admin Fund not yet received. Due date for submission was Action Taken Report of FY Action Taken Report for the year on residual point of Programme Fund and on Observation of Admin Fund not received. Observation in Financial Management Deficit Financing : There is a net deficit financing of Rs Cr Discrepancies of fund received in Schedule L1 and UC : Rs Cr Interest shown in Banker Certificate and Schedule of Incidental Fund in Programme Fund differs: Rs Cr
82
West Bengal Stale Cheques : Programme Fund: Rs. 47.52 Lakh
Operation of Two Bank Accounts Outstanding Liabilities : Cr (Including amount payable to State Govt. : Cr) Outstanding Advances : Rs Cr. (Amount recoverable from HIT Rs Lac and from IOC Rs Lac has been pending over the years) Bank Guarantee aggregating to Rs Crore has been expired Weaknesses in implementation in OMMAS Month for which entries has been completed in OMMAS (R&P Module) Programme Fund:- August 2015 Administrative Fund:- Nov 2014 Maintenance Fund:- Not closed
83
Pending Financial Completion of Physically Completed Works
West Bengal Pending Final Bills 361 number of physical completed works pending for financial completion. (i.e % Out of total 3,517 physically completed works) Sanction Year Pending Financial Completion of Physically Completed Works 1 8 4 2 3 20 24 21 17 204 57 Total: 361
84
West Bengal Improvement in Accounting / OMMAS R&P Module
Revoking of month once it is finalized The option of revoking of the month from the State finance login will be disabled by which states are revoking the months even after closure of accounts. E-Payments Currently operation of E-payment is optional for the States. It is advisable to operate the E-payment system for more strengthening the project. TDS deducted by the Bank on interest It has been seen that banks are deducting TDS on interest despite of having exemption certificate. Agencies are advised to take up the matter with banks. As per the Programme Guidelines, Balance Sheet needs to be furnished by States are requested to ensure the compliance. Submission of Balance Sheet of Programme and Admin Fund on time. Unsettled Advances. Internal Audit.
85
Centralized Public Grievance Redressal and Monitoring System (CPGRAMS)
Department of Administrative Reforms and Public Grievances (DARPG) has operational a web-based portal called CPGRAMS, which is accessible through . CPGRAMS is an important tool of Government to strengthen the two- way communication with citizens for effective and time-bound implementation of programme / schemes at the ground level. The citizens, with the use of CPGRAMS portal, can express their concerns related to programme / schemes and administrative activities.
86
Centralized Public Grievance Redressal and Monitoring System (CPGRAMS)
CPGRAMS is also one of the key sectors of Result Framework Document (RFD). As per instructions / Guidelines of DARPG and also indicated in RFD, all grievances should be: Redressed within 60 days of receipt in the organization. The time limit of 60 days applies even if co-ordination with subsidiary offices or another Department/ Organization is involved. The position of Grievances received on CPGRAMS Portal forwarded by Ministry to NRRDA is regularly reviewed.
87
Centralized Public Grievance Redressal and Monitoring System (CPGRAMS)
States may ensure disposal of grievance in time bound manner without compromising on quality aspects. A letter has already been sent to all States / UTs from JS (RC) vide No. P-17025/75/2011-RC dated 20th September, 2013 for timely disposal of the complaints which is also uploaded on PMGSY website ( under circular section.
88
Pending Grievances with Bihar State Poor / substandard work
# Registration Number Name of Complainant Date of Receipt Pendency days (As on ) Nature of grievance 1 PMOPG/W/2015/ Sh. Rajnish kumar 321 Poor / substandard work 2 PMOPG/D/2015/ Sh. Gaya prasad 82
89
Pending Grievances with Jharkhand State
# Registration Number Name of Complainant Date of Receipt Pendency days (As on ) Nature of grievance Status 1 PMOPG/D/2015/73965 Ms. Malati Singh 198 Irregularity & corruption in planning of Rural Roads Interim reply submitted by State & requested NRRDA (P-III Division) on dated for further direction 2 PMOPG/E/2015/ Sh. Pranab kumar mandal 89 Labour Issues - Contractual Employees No Grievances pending in Odisha and West Bengal
90
Officers trained under various Training Programmes during 2015-16 (Upto September, 2015)
Name of State (s) Officers Nominated Officers Attended Bihar 67 39 Jharkhand 30 18 Odisha 110 108 West Bengal 124 116 Total: 331 281
91
Status of Clearances since Inception – Sept, 2015
92
B I H A R Year (s) Date Phase Value in Crores No of Roads
No of Bridges Length in Km 26-Feb-01 Phase-I 149.89 298 811.66 02-Jul-02 Phase-II 302.98 666 NEAs Phase-III-VI (Batch-I) 3509 15-Oct-07 Missing Links of I & II (P-1) 267.66 162 620.17 08-Feb-08 Phase-VI (Batch-II) 256.63 109 605.81 30-Jun-08 Phase-VII (P-1) 705 05-Sep-08 Phase-VII (P-2) 1025 04-Nov-08 Missing Links of I & II (P-2) 264.55 166 563.45 27-Jan-09 Phase-VIII 1681 17-Feb-09 125.92 71 238.52 19-Feb-09 Phase-IX 905 25-Nov-11 Phase-X 915.07 647 23-Jan-12 33.05 23 0.83 08-Jun-12 Phase-XI 1350 96 21-Nov-13 Phase-XII (WBRRP_II) 910 46 Phase-XIII 1457 143 07-Feb. 14 Phase X 2796 67 Total: 16457 375 B I H A R
93
J H A R K H A N D Year (s) Date Phase Value in Crores No of Roads
No of Bridges Length in Km 26-Feb-01 Phase-I 105.92 168 900.75 26-May-01 Phase-II 230.26 202 1200.2 22-Dec-03 Phase-III 135.92 131 651.92 Tranchi-I 29.15 26 130.07 09-Mar-06 Phase-IV 113.78 102 479.39 17-Dec-07 Phase-V 499.49 353 1679.8 07-Aug-08 Tranchi-II 44.90 33 150.62 30-Oct-08 Phase-VI 928.22 636 2971.7 21-Aug-09 Phase-VII 280.20 279 1026.4 03-Mar-10 Phase-VIII 601.87 656 4 2255.2 23-May-11 Phase-IX 635.19 531 49 2006.2 02-Mar-12 Phase-X 68.00 9 1 103.48 27-Apr-12 404.12 291 10 1109.2 15-Oct-12 186.54 56 26-Mar-13 Phase-XI 773 108 2428.1 26-Aug-13 Phase-XII 30.01 19 56.08 13-Feb.-14 Phase XII (B-II) 710 91 Total: 4919 319 J H A R K H A N D
94
Phase-XII (Batch-III)
Year (s) Date Phase Value in Crores No of Roads No of Bridges Length in Km 26-Feb-01 Phase-I 170.88 521 26-May-01 Phase-II 350.00 571 10-Nov-03 Phase-III 183.56 347 998.02 10-Mar-04 Phase-III (Addl.) 257.37 283 1013.9 02-Mar-05 Phase-IV 398.72 418 16-Aug-05 Batch I 349.46 257 1189.1 Phase-V 531.00 483 03-Oct-06 Batch II 513.81 400 Phase-VI 579.84 443 08-Nov-07 Phase-VII 1689 14-Nov-08 Batch III 611.40 310 Phase-VIII 87.04 31 05-Feb-09 1123 17-Feb-09 106.33 43 27-Feb-09 Batch IV 522.58 334 Phase-VIII (Addl.) 851.43 309 11-Mar-11 Phase-IX 402.56 122 60 585.68 15-Nov-11 Phase-X 993.80 602 28-Nov-11 RRSP Tranche-I 472.75 284 1052.2 23-Mar-12 Phase-XI 681 21-Sep-12 Phase-XII (Batch-I) 823 19-Feb-13 Phase-XII (Batch-II) 947.89 511 23-Aug-13 Phase-XII (Batch-III) 483.31 141 RRSP Tranche-II 584.64 343 03-Jan-14 ADB RCIP Tr. III 788 17 Total: 11642 292 O D I S H A
95
W E S T B E N G A L Year (s) Date Phase Value in Crores No of Roads
Length in Km 26-Feb-01 Phase-I 140.04 174 826.32 22-Oct-01 Phase-II 305.48 213 30-Jun-03 Phase-III 278.31 208 955.64 30-Jan-04 Phase-III (Addl.) 320.97 159 01-Apr-05 Phase-IV 311.90 152 975.53 16-Aug-05 Batch I 313.71 132 999.32 08-May-06 Phase-V 657.78 236 20-Sep-07 Batch II 329.71 109 908.10 Phase-VI 790.25 335 26-Feb-09 Phase-VII 869.44 463 27-Feb-09 Batch III 302.10 127 696.27 38.68 19 112.30 13-Sep-10 Batch III (Part-II) 214.84 76 443.49 Phase-VIII 502.57 280 18-Nov-11 Phase-IX 612.34 247 07-Dec-12 Phase-X 1425 30-Jul-13 Phase-XI Batch-I 523.61 150 08-Aug-13 Phase-XI Batch-II 821.65 447 31-Mar-15 ADB 328.58 637.57 Total: 5028 W E S T B E N G A L
96
GIS System Web GIS is the combination of WEB & Geographic Information System which facilitates the sharing, communication, interoperability, collaboration, and integration of geospatial information on the Web . The system aims to establish computerized data base for core rural road network through development of web based GIS. This system in integration with OMMAS will support development of an online reporting module on rural road works thereby establishing a comprehensive planning, management, reporting system covering both construction and maintenance works.
97
GIS Implementation The system will help to monitor progress of the PMGSY on GIS maps in conjunction with OMMAS data and will include: Showing connectivity status of the habitation/tourist places/ Panchayat HQs on a GIS map Physical and financial progress Quality of the roads (NQM/SQM) Roads under/ due for maintenance Spatial Queries Road Queries • Road type (e.g. NH,SH etc.) • Road Ownership (PWD, Irrigation etc.) • Stream( PMGSY, World Bank etc.) • Through routes/Link routes
98
SRS & Implementation Progress
System Requirement Study (SRS) was assigned to CDAC & their report was accepted. Based on this report it was decided to Implement GIS system in all PMGSY states. The project will be implemented in two phases as indicated below: Phase – I will comprise of procurement & installation of hardware & software at central level in NRRDA, as part of Web GIS system & integration of data from the states of Rajasthan, HP, Gujarat, Maharashtra, Punjab & Uttarakhand. Phase – II will integrate all the remaining participating & non participating states into the Web GIS system progressively as & when they finalize / update their database.
99
Plan of action C-DAC will provide the hardware i.e. Web GIS server & operating software centrally at NRRDA. States included in phase –I i.e. Punjab, Rajasthan, Himachal Pradesh, Gujarat, Maharashtra and Uttarakhand are to prepare or update the spatial database on priority as per SRS and C-DAC specifications circulated to them. This is to be submitted to C-DAC for integration with the OMMAS system. The spatial database will be uploaded in the server for which C-DAC has defined the system & the integration process in the SRS specification.
100
Present Status Memorandum of Understanding (MOU) with CDAC has been signed for “Implementation of Web based GIS system in all PMGSY states”. The states have been issued advisory on dated to prepare the database in accordance with SRS & system specification given by CDAC as indicated below : To initiate action to prepare / upgrade the data base. States included in Phase –I i.e. Punjab, Rajasthan, Himachal Pradesh, Gujarat, Maharashtra and Uttarakhand need to do it promptly. To assess whether they require SRIS system, as suggested by C-DAC for their State. This should be considered appropriately taking view of the fact that certain states have already developed standalone GIS System. To assess their requirement of preparing / upgrading the database & requirement of SRIS, make a cost assessment for the same and project it to NRRDA for allotment of funds. All the states are requested to expedite this process.
101
Project Flowchart
102
Thank You
103
Trends of Physical Completion of Roads (in km)
N E A C P W D
104
Trends of Physical Completion of Roads (in km)
NE A N B C C
105
Trends of Physical Completion of Roads (in km)
NE A I R C O N
106
Trends of Physical Completion of Roads (in km)
N E A N H P C
107
Trends of Physical Completion of Roads (in km)
N E A N P C C
108
Trends of Financial Progress ( Release / Expenditure in Rs Crore)
B I H A R N E A