Progress on Phase 1 of the Bing Kong Tong Building Renovation April-May 2014
2
Forms and rebar at the front of the building ready to pour for shear walls.
3
Rafters getting reinforced Dry rot and broken rafters were reinforced to carry new roofing material.
4
LVLs (manufactured beams) were added at the rear and front of the building.
5
Concrete was poured into forms at the front and rear for shear wall support.
6
Old front parapet wall going down Main Street for storage at River Storage. It was removed due to dry rot damage.
7
Rebuilding of the new parapet wall to exact dimensions of the original.
8
The new parapet wall being placed
9
Installing insulation
10
Installing insulation prior to roofing