AMS-02 Integration Cables Status and Electrical Integrated Testing Status Tim Urban / ESCG January 10, 2007 Alpha Magnetic Spectrometer
2
Integration Cables Status Electrical Integrated Testing Status: I/F Design Description: Power and Data Interfaces for Integrated AMS-02 Payload Testing Upcoming Tests: Pad Ops Preliminary Interface Test (POPIT) PDS EM Power Quality Test (PQT) January 10, 2007T. J. Urban / ESCG2 Alpha Magnetic Spectrometer Integration Cables and Electrical Integrated Testing Status Presentation Outline
3
Design: The integration cables design and drafting are complete. The cables are summarized in the table on the next page. The lengths of 6 cables are being updated based upon their redesign so that they may be used as test cables (discussed later). Of twenty different cable designs, four are complete through cable drawing checking. The remaining checking will be completed January 19, 2007. The cable drawings will be released at JSC when they complete checking. Procurement: All materials required for flight cable fabrication have been ordered. 88% of these materials have been received and are in bonded storage. The remainder of these materials are due by end of Jan ‘07 (1 item in Feb). All fabrication tools have been ordered and received. January 10, 2007T. J. Urban / ESCG3 Alpha Magnetic Spectrometer JSC Provided Integration Cables Design, Fabrication and Delivery Status
4
January 10, 2007T. J. Urban / ESCG4 Alpha Magnetic Spectrometer JSC Provided Integration Cables Design, Fabrication and Delivery Status Cable Summary
5
Fabrication: The estimate for JSC cable fabrication labor is complete. JSC work will begin this month, and be complete by the end of April ’07. Four cable designs (total qty. 6) will be completely fabricated at JSC. Six cable designs (total qty. 12) will be 67% fabricated at JSC, with the remaining 33% completed at CERN in August ’07. Ten cable designs (total qty. 18) will be 67% fabricated at JSC, with the remaining 33% completed at KSC in February ’09. JSC cable fabrication tech. will perform cable completion at CERN & KSC. Delivery: Thirteen cable designs (total qty. 25) delivered to CERN in July ’07. Two AFD cable designs (total qty. 4) delivered to Shuttle FCE later in ’07. Five cable designs (total qty. 7) delivered to KSC in December ‘08. January 10, 2007T. J. Urban / ESCG5 Alpha Magnetic Spectrometer JSC Provided Integration Cables Design, Fabrication and Delivery Status
6
Miscellaneous: During CERN payload pre-integration and integration, UUSS and LUSS real estate required for subsequent KSC work should be marked and reserved: Integration cable routing Hardware installation: EVA Connector Panel, ROEU PDA, PVGF JSC ESCG (D. Nguyen) to continue working closely with AMS-02 cable routing modeling team. JSC ESCG to provide EVA rated cable labels for use by AMS-02 at CERN (4 week delivery ARO – purchased next week). MIT (X. Cai) will use existing 1553 cables in upcoming J-Crate ESS to verify 1553 RT stub length of 25 feet is acceptable at hot and cold temperatures. (design validation) The modified PVGF cable harness will be designed to include the fuse required to protect the SSRMS wiring from over-current / over-temperature from AMS-02 heaters powered during SSRMS operations. January 10, 2007T. J. Urban / ESCG6 Alpha Magnetic Spectrometer JSC Provided Integration Cables Design, Fabrication and Delivery Status
7
Interface Design Description January 10, 2007T. J. Urban / ESCG7 Alpha Magnetic Spectrometer Electrical Integrated Testing Status
8
T. J. Urban / ESCG8January 10, 2007 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description Payload Integration Cable Schematic
9
For payload testing: The payload flight model Interface Panel A will be used to provide GSE cable interface capabilities for STS power and data services. A new non-flight Test Connector Panel (TCP) will be used to provide GSE cable interface capabilities for ISS power and data services. This scheme will be used at: Europe: Functional, beam, TVT and EMI Tests KSC: Post-delivery functional. Interface Panel A connector savers will be used until ROEU ODA GSE is available. TCP will be used for all ground tests prior to installation of EVA Connector Panel / UMA and ACASS UMA is available. January 10, 2007T. J. Urban / ESCG9 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description
10
Interface Panel A Concept: GSE connector savers will be installed on all Interface Panel A flight connectors. For the power connections (5 of 6), GSE cables will be mated directly to the connector savers. For the sixth connection, 1553 & RS-422 data, a connector-saver to Trompeter adaptor (channel quantity TBC) will be utilized so that CERN GSE data cables will be simple, existing twin-ax cables. January 10, 2007T. J. Urban / ESCG10 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description
11
Test Connector Panel Concept: A non-flight test connector panel will be mounted to the UUSS (forward & starboard) to connect the GSE provided “ISS” power and data services to the PDS and J-Crate. This requires 6 flight cables to have new, interim, test cable configuration designs: -305 and -307 [test] instead of -301 and -303 [flight]. The test configuration cables will be fully assembled at JSC, then delivered to CERN (July ’07). The payload PDS, J-Crate and JPD connectors will be “FLIGHT” routed and connected to boxes at CERN – never to be disturbed. The other ends of these cables, with extra length coiled, will be attached to the Test Connector Panel. At KSC, the TCP will be removed and the -305/-307 cables will be re-routed and re-configured to the -301/-303 cables at the flight EVA Connector Panel. January 10, 2007T. J. Urban / ESCG11 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description
12
Test Connector Panel Concept (continued): The GSE power connections (2 of 6) at the TCP will be made via simple GSE connectors/cables. The GSE data connections (4 of 6) at the TCP will be made via circular connector to Trompeter or ST fiber connectors. This will allow the CERN GSE cables to be simple, existing twin-ax or ST fiber cables. January 10, 2007T. J. Urban / ESCG12 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description
13
GSE & Test Cable & Adaptor Schematic 13
14
Text Connector Panel Concept & Routing Test Connector Panel Test Cable Routing 14
15
JSC ESCG: Provide Test cables and Adaptors 6 test cables – quantity 1 each Adaptor, circular to 8 channel twin-ax – quantity 2 Adaptor, circular to 2 channel twin-ax – quantity 3 Adaptor, circular to 4 channel fiber ST – quantity 2 Loop-back connector, sub-miniature D 9 pin – quantity 3 Design Procurement of materials Fabrication Provide 6 connector savers for Interface Panel A – quantity 1 each Provide mating connectors for 7 other GSE cables – quantity 2 each Loan tools required for assembly of these 7 GSE cables January 10, 2007T. J. Urban / ESCG15 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description Responsibilities and Actions
16
CERN / MIT: Provide Trompeter twin-ax and fiber ST GSE cables. Provide cables and chamber feed-throughs required for interfacing GSE cables / adaptors during payload TVT and EMI tests. Assemble 7 GSE cables – quantity 2 each. THE DATE ALL ITEMS ARE NEEDED IS TBD (probably 3 rd quarter 2007). January 10, 2007T. J. Urban / ESCG16 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description Responsibilities and Actions (continued)
17
Pad Operations Preliminary Interface Test January 10, 2007T. J. Urban / ESCG17 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests
18
Purpose: Pin to pin verification of AMS-02 payload to AMS-02 GSE data channels via the STS Mobile Launch Platform (MLP) and T0 Umbilical wiring. Transmission signal quality evaluation. “Stake a claim” on required KSC MLP GSE cables and equipment. Where: KSC: MLP in Vertical Assembly Building (no Orbiter). When: April 2007, one week Who: PADSOFT: Dennett ESCG: Urban and D. Nguyen MIT: Lebedev, Koutsenko, Cai T. J. Urban / ESCG18January 10, 2007 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests Pad Operations Preliminary Interface Test
19
T. J. Urban / ESCG19January 10, 2007 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests - POPIT 1553 Communications Test Configuration 1
20
T. J. Urban / ESCG20January 10, 2007 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests - POPIT 1553 Communications Test Configuration 2
21
T. J. Urban / ESCG21January 10, 2007 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests - POPIT RS-422 Communications Test
22
ESCG / Urban to compile and distribute required materials list: ESCG: Cables to be designed & fabricated and materials procurement KSC: MLP and T0 Test cables and test equipment STS / USA: Test PDIP CERN / MIT: Computers Software (1553) – changes recommended by PADSOFT in test plan, will be forwarded by ESCG / Urban. PADSOFT: RS-422 Software Items must be ready for shipment by end of March ‘07. This test will require KSC Test Readiness Review (March ’07). Other issues: KSC access and Visas January 10, 2007T. J. Urban / ESCG22 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests - POPIT Responsibilities and Actions
23
PDS EM Power Quality Test January 10, 2007T. J. Urban / ESCG23 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests
24
Purpose: Characterize PDS EM performance under load, and its affect on STS and ISS input power, as a design validation test. To include (from P. Lipoma): Electrical Power Characteristics Steady State Voltage Ripple Characteristics Transient Voltages Normal Voltage Range Electrical Power Interface Power Bus Isolation RPC Soft Start/Stop Compatibility Surge Current Reverse Energy Other RPC Characteristics Complex Load Impedance Large Signal Stability Electrical Power Constraints T. J. Urban / ESCG24January 10, 2007 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests PDS EM Power Quality Test
25
Where: JSC: Electrical Power Systems Laboratory (EPSL) When: June 2007, one week Who: JSC: EPSL staff ESCG: Urban, Lipoma and D. Nguyen MIT: Koutsenko, Koulemzine, Capell or Lebedev CGS: Alia T. J. Urban / ESCG25January 10, 2007 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests PDS EM Power Quality Test
26
T. J. Urban / ESCG26January 10, 2007 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests Block Diagram
27
Responsibilities and Actions : ESCG coordination with JSC EPSL, including test plan and test procedures. EPSL will provide test facility, input 120 VDC, and test equipment. List of items to be provided by CGS: Payload simulating load Special test equipment Cables List of items to be provided by CERN / MIT: PDS EM Computer and CAN software Cables Date equipment should be ready to ship is the end of May ’07. Other issues: JSC access and Visas January 10, 2007T. J. Urban / ESCG27 Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests PDS EM Power Quality Test