5/26/2011Tom Herlihy West Newton Street Steam System Upgrade
2
2 Contents 1.Who We Are 2.Why We Are Doing The Work 3.What We Are Doing 4.Where We Are Working 5.When We Are Working There 6.Questions
3
Creative Solutions for our Environment 313,000 Veolia Personnel Delivering Sustainable Solutions in 74 Countries The only company in the world able to cover the entire range of environmental services (NYSE: VE) The standard for water services The standard for waste management and resource recovery The standard for managing safe and sustainable mobility solutions 2010 Revenue $16.2 billion 2010 Revenue $10.1 billion 2010 Revenue $12.4 billion 2010 Revenue $7.7 billion The standard for energy efficient solutions 2010 Global Revenue $46.5 billion 3
4
Veolia Environnement North America The Standard for Integrated Environmental Management Total Revenue: Approximately $4.7 billion Total Employees: Approximately 30,000 No.1 in municipal partnerships & industrial outsourcing Employees: 3,400 Top 1-4 in various categories of waste management Employees: 10,000 Owns largest portfolio of heating and cooling systems in the USA Employees: 625 No.1 in U.S. surface passenger transportation Employees: 16,000 2010 Revenue: $1.0 Billion 2010 Revenue: $1.9 Billion 2010 Revenue: $0.4 Billion 2010 Revenue: $1.3 Billion 4
5
5 Veolia Energy North America Operating Sustainable Energy Systems across the Continental USA
6
24 hour a day presence Energy services support the following systems: o Heating o Air conditioning and refrigeration o Humidification control o Sterilization systems o Food & beverage preparation Energy company of choice for more than 44 million square feet of commercial, institutional and governmental facilities. Boston District Energy System 6
7
Why We Are Doing The Work We invest in our energy infrastructure and seek continuous improvements in our networks’: o Safety o Reliability o Efficiency Expansion joints are a critical component Found a better alternative to existing Bellows material of some joints in the area Approximately 130 expansion joints to be replaced Upgrade in joint quality 7
8
What We Are Doing In Coordination with all Applicable City Agencies Dig an 8x10 excavation Break out concrete Remove the asbestos insulation Cut & weld new expansion joints X-Ray & insulate Replace concrete, backfill & pave 8
9
Where We Are Working West Newton Street Between Tremont Street and Columbus Avenue West Newton Street & Columbus Avenue Columbus Avenue and Southwest Corridor Path Southwest Corridor Path and St. Botolph Street St Botolph Street & Huntington Avenue 9
11
When We Are Working Tremont to Columbus June7 – July 7 West Newton & ColumbusJuly 25 – August 9 Titus Sparrow Park June 28 – July 20 Titus Sparrow to St. BotolphJuly 7 – July 25 St. Botolph to Huntington Av July 15 – August 2 11
12
12 Questions?