Chapter 7: Monitoring and Controlling the Project 1 Project Management in Practice Prepared by Scott M. Shafer Wake Forest University Mantel, Meredith, Shafer, and Sutton John Wiley and Sons, Inc.
2
Chapter 7: Monitoring and Controlling the Project 2 Chapter 7 Monitoring and Controlling the Project
3
Chapter 7: Monitoring and Controlling the Project 3 Introduction 4 Monitoring and Control are opposite sides of selection and planning –bases for selection dictate what to monitor –plans identify elements to control 4 Monitoring is collection, recording, and reporting of information 4 Control uses monitored information to align actual performance with the plan
4
Chapter 7: Monitoring and Controlling the Project 4 THE PLAN-MONITOR- CONTROL CYCLE
5
Chapter 7: Monitoring and Controlling the Project 5 Plan-Monitor-Control Cycle 4 Closed loop process 4 Planning-monitoring-controlling effort often minimized to spend time on “the real work”
6
Chapter 7: Monitoring and Controlling the Project 6 Figure 7-1 Project Authorization and Expenditure Control System Information Flow
7
Chapter 7: Monitoring and Controlling the Project 7 Designing the Monitoring System 4 Identify special characteristics of performance, cost, and time that need to be controlled –performance characteristics should be set for each level of detail in the project 4 Real-time data should be collected and compared against plans –mechanisms to collect this data must be designed 4 Avoid tendency to focus on easily collected data
8
Chapter 7: Monitoring and Controlling the Project 8 DATA COLLECTION AND REPORTING
9
Chapter 7: Monitoring and Controlling the Project 9 Formats of Data 4 Frequency Counts 4 Raw Numbers 4 Subjective Numeric Ratings 4 Indicators and Surrogates 4 Verbal Characterizations
10
Chapter 7: Monitoring and Controlling the Project 10 Data Analysis 4 Aggregation Techniques 4 Fitting Statistical Distributions 4 Curve Fitting 4 Quality Management Techniques
11
Chapter 7: Monitoring and Controlling the Project 11 Figure 7-2 Number of Bugs per Unit of Test Time
12
Chapter 7: Monitoring and Controlling the Project 12 Figure 7-3 Percent of Specified Performance Met During Successive Repeated Trials
13
Chapter 7: Monitoring and Controlling the Project 13 Figure 7-4 Ratio of Actual Material Cost to Estimated Material Cost
14
Chapter 7: Monitoring and Controlling the Project 14 Reporting 4 Reports –Project Status Reports –Time/Cost Reports –Variance Reports 4 Not all stakeholders need to receive same information 4 Avoid periodic reports 4 Impact of Electronic Media 4 Relationship between project’s information system and overall organization’s information system
15
Chapter 7: Monitoring and Controlling the Project 15 Report Types 4 Routine 4 Exception 4 Special Analysis
16
Chapter 7: Monitoring and Controlling the Project 16 Meeting Guidelines 4 Meetings should be help primarily for group decision making –avoid weekly progress report meetings 4 Distribute written agenda in advance of meeting
17
Chapter 7: Monitoring and Controlling the Project 17 Meeting Guidelines continued 4 Ensure everyone is properly prepared for meeting 4 Chair of meeting should take minutes –avoid attributing remarks to individuals in the minutes 4 Avoid excessive formality 4 If meeting is held to address specific crisis, restrict meeting to this issue alone
18
Chapter 7: Monitoring and Controlling the Project 18 Virtual Reports, Meetings, and Project Management 4 Use of the Internet 4 Use of Software Programs 4 Virtual Project Teams
19
Chapter 7: Monitoring and Controlling the Project 19 EARNED VALUE
20
Chapter 7: Monitoring and Controlling the Project 20 Earned Value 4 Percent of task’s budget actually spent not good indicator of percent completion
21
Chapter 7: Monitoring and Controlling the Project 21 Conventions Used to Estimate Progress on Tasks 4 50-50 –50% complete when task started and other 50% added when task finished 4 100% –100% complete when finished and zero percent before that 4 Ratio of Cost Expended to Cost Budgeted
22
Chapter 7: Monitoring and Controlling the Project 22 Variances 4 Cost/Spending Variance BCWP - ACWP 4 Schedule Variance BCWP - BCWS 4 CPI BCWP/ACWP 4 SPI BCWP/BCWS
23
Chapter 7: Monitoring and Controlling the Project 23 Figure 7-5 Earned Value Chart
24
Chapter 7: Monitoring and Controlling the Project 24 Figure 7-6(a) Positive Schedule Variance, Negative Spending Variance
25
Chapter 7: Monitoring and Controlling the Project 25 Figure 7-6(b) Negative Schedule Variance, Negative Spending Variance
26
Chapter 7: Monitoring and Controlling the Project 26 Figure 7-6(c) Negative Schedule Variance, Positive Spending Variance
27
Chapter 7: Monitoring and Controlling the Project 27 Additional Items of Interest 4 Estimated (Remaining Cost) to Completion ETC = (BAC - BCWP)/CPI 4 (Total Cost) Estimated at Completion EAC = ETC + ACWP
28
Chapter 7: Monitoring and Controlling the Project 28 PROJECT CONTROL
29
Chapter 7: Monitoring and Controlling the Project 29 Background 4 Acts which seek to reduce differences between plan and actuality 4 Difficult Task –human behavior involved –problems rarely clear cut
30
Chapter 7: Monitoring and Controlling the Project 30 Purposed of Control 4 Stewardship of Organizational Assets –physical asset control –human resources –financial control 4 Regulation of Results Through the Alteration of Activities
31
Chapter 7: Monitoring and Controlling the Project 31 DESIGNING THE CONTROL SYSTEM
32
Chapter 7: Monitoring and Controlling the Project 32 Background 4 Purpose is to correct errors, not punish the guilty 4 Investments in control subject to diminishing returns 4 Must consider impact on creativity and innovation 4 Be careful not emphasize short-run results at the expense of long-run objectives 4 Dangers of across the board cuts
33
Chapter 7: Monitoring and Controlling the Project 33 Primary Mechanisms by Which PM Exerts Control 4 Process Reviews 4 Personnel Assignments 4 Resource Allocations
34
Chapter 7: Monitoring and Controlling the Project 34 Components of a Control System 4 Sensor 4 Standard 4 Comparator 4 Decision Maker 4 Effector
35
Chapter 7: Monitoring and Controlling the Project 35 Types of Control Systems 4 Go/No-Go Controls –predetermined standard must be met for permission to be granted to continue 4 Post-Control –done after project completed –purpose is to allow future projects to learn from past project experience
36
Chapter 7: Monitoring and Controlling the Project 36 Figure 7-7 Sample Project Milestone Status Report
37
Chapter 7: Monitoring and Controlling the Project 37 Tools for Control 4 Variance Analysis 4 Trend Projections 4 Earned Value Analysis 4 Critical Ratio
38
Chapter 7: Monitoring and Controlling the Project 38 Figure 7-8 Trend Projection
39
Chapter 7: Monitoring and Controlling the Project 39 Figure 7-9 Critical Ratios with Control Limits
40
Chapter 7: Monitoring and Controlling the Project 40 Figure 7-10 Cost Control Chart
41
Chapter 7: Monitoring and Controlling the Project 41 SCOPE CREEP AND CHANGE CONTROL
42
Chapter 7: Monitoring and Controlling the Project 42 Scope Creep 4 Coping with changes frequently cited by PMs as the single most important problem 4 Common Reasons for Change Requests –Client –Availability of new technologies and materials
43
Chapter 7: Monitoring and Controlling the Project 43 Purpose of Change Control System 4 Review all requested changes 4 Identify impact of change 4 Evaluate advantages and disadvantages of requested change 4 Install process so that individual with authority may accept or reject changes
44
Chapter 7: Monitoring and Controlling the Project 44 Purpose of Change Control System continued 4 Communicate change to concerned parties 4 Ensure changes implemented properly 4 Prepare reports that summarize changes made to date and their impact
45
Chapter 7: Monitoring and Controlling the Project 45 Rules for Controlling Scope Creep 4 Include in contract change control system 4 Require all changes be introduced by a change order 4 Require approval in writing by the client’s agent and senior management 4 Consult with PM prior to preparation of change order 4 Amend master plan to reflect changes
46
Chapter 7: Monitoring and Controlling the Project 46 Copyright Copyright John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that named in Section 117 of the United States Copyright Act without the express written consent of the copyright owner is unlawful. Requests for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. Adopters of the textbook are granted permission to make back-up copies for their own use only, to make copies for distribution to students of the course the textbook is used in, and to modify this material to best suit their instructional needs. Under no circumstances can copies be made for resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein.