Download presentation
Presentation is loading. Please wait.
Published byStephanie Hodge Modified over 9 years ago
1
Presented by Matt McClymonds
2
Project Essentials ◦ Project Objective Prepare the campus for a new telephone system ◦ External Conditions Converged networks require more bandwidth Campus facilities are more like Quonset huts than structured buildings Campus on top of an active volcano Logistics will be difficult at best. ◦ Situations Existing cabling will not support future growth ◦ Scope/Extent Three new data drops at every work area outlet Three new patch panels to quickly troubleshoot issues Physically secure enclosure to minimize people “helping” ◦ Form of Project’s Output Physical infrastructure that will scale over the next 10 years
3
Planning Issues ◦ Known asbestos ◦ Tight timeframe to completion from project start to completion ◦ Material logistical challenges Shipping material Federal Express does not deliver at customer’s location ◦ Limited budget
4
Fundamentals (Installation) ◦ A – Activities ◦ B – Resources ◦ C – Schedule
5
Planning Schedule ◦ Site Survey ◦ List of Material Development ◦ Scope Development ◦ Project Charter Development ◦ Scope sign off by customer
6
Fundamental “A” - Activities ◦ HARD – Physical, Tangible, Factual, “Product” The customer wants to upgrade with a new horizontal cabling plant. ◦ Soft – Mental, Procedural, Operational, “Process” Government contract so change orders will be slow and not well received. ◦ Sensitive – Emotional, Personal, User, “Producer” The customer wants to have the least amount of maintenance to the physical infrastructure as possible and is willing to overbuild to accomplish maximum flexibility.
7
Considerations: ◦ Existing situations Reasonable cable plant with minimum number of work area outlets. ◦ Short-term situations Current cabling would work, but would not be scalable. ◦ Long-term situations A new cable plant will enable future growth by providing more outlets and increased network speeds. ◦ External Logistics will be difficult getting material from the mainland to the customer’s location. ◦ Internal Change orders must be kept to a minimum due to this project being the contracting officer’s representative’s first contract.
8
Fundamental “B” - Resources HARD – Physical, Tangible, Factual, “Product” ◦ Copper cabling will be installed external to the facility due to the nature of the structures. Soft – Mental, Procedural, Operational, “Process” ◦ Some buildings will have tremendous moving challenges due to the amount of paperwork stored on site. Sensitive – Emotional, Personal, User, “Producer” ◦ Employees will be displaced for days while the cabling crew installs new cabling and removes old cabling.
9
Considerations: ◦ Existing situations Lots of moving required to get to the work area outlets. ◦ Short-term situations New carpet will be going into one of the buildings. ◦ Long-term situations All buildings require fiber optic backbone to ensure long term data rates. ◦ External Campus is on top of an active volcano. ◦ Internal One building has known asbestos issues and will require a specialty contractor to complete any core drilling.
10
Design Considerations ◦ Inclusions How to develop cabling pathway Flush mount versus wall mount terminations What products to recommend Filling penetrations (weather, critters) Risk management plan Develop project charter to ensure accurate scope Iterative process with the customer ◦ Exclusions Need to plan for zero change orders (mitigate risk) Customer does not want any electrical work associated with this scope. (grounding/UPS)
11
Descriptions of Alternatives ◦ Plan A – walk away from this project (current system will support 90% of the migration) ◦ Plan B – Promote installing the last 10% of the customer’s requirements. ◦ Plan C – Develop a plan with all the bells and whistles but may be a cost issue. ◦ Plan D – Create a balance of all the known issues to meet customer and business needs.
12
Plan A ◦ No Risk ◦ No Reward ◦ No Revenue Plan B ◦ Small project running new cables to support new phones ◦ Very Little Risk ◦ Can be accomplished with local resources Plan C ◦ Recommend fiber to the desktop. ◦ Recommend solid pathway ◦ Basket tray/conduit ◦ Recommend Cat6a ◦ Recommend Power Outlet Units Plan D ◦ Recommend fiber for the Outside plant only ◦ Recommend J-hooks under the buildings ◦ Recommend Cat6 ◦ Attempt to capture power requirements in a follow on project
13
Project Plan and Schedule
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.