Metropolitan Council Environmental Services Proposed 2010-2015 Capital Program and the 2010 Capital Budget Presented to The Environment Committee August 11, 2009 Bryce Pickart Assistant General Manager A Clean Water Agency
2
Definitions Capital Improvement Program (CIP) Capital Improvement Program (CIP) 6-Year Plan 6-Year Plan Authorized Capital Program Authorized Capital Program Multi-Year Authorization Capital Budget Capital Budget Annual Appropriation
3
Proposed Schedule Capital Finance Plan Aug 25th Public Hearing and Adoption Nov, 2009 Aug 11th Capital Program and Budget Sep, 2009 Incorporate into the Unified Capital Improvement Program and Unified Capital Budget
4
Capital Improvement Program Expense History 1970 thru 2008 Average is $114 million 2009 Dollars
5
Capital Investment Drivers Growth (defer as much as possible) -Development along Transportation Corridors -Rural Growth Centers Rehabilitation -Infrastructure maintenance -Infiltration/Inflow reduction Quality -Energy Reduction -Water Quality Improvements
7
Capital Project Identification Condition Assessment ProgramCondition Assessment Program Capacity/Growth AnalysisCapacity/Growth Analysis New Permits and RegulationsNew Permits and Regulations Infrastructure Projects (Roads, Transit, Utilities, Stadiums, et. al.)Infrastructure Projects (Roads, Transit, Utilities, Stadiums, et. al.) Regional Wastewater System PlanRegional Wastewater System Plan Local Comprehensive PlansLocal Comprehensive Plans
8
Capital Program Strategy 1. Meet our commitments 2. Take advantage of opportunities 3. Focus on rehabilitation (high risk of delay) 4. Defer growth projects
9
High Priority Projects Commitments Policy/System Statements/Comp Plans Regulations/Permits Safety and Security Opportunities Coordination with Infrastructure Projects Energy Conservation/Recovery Wastewater Re-use High Risk Of Delay Probability and Severity of Failure
10
Growth Projects Being Delayed Plant projects deferred to 2014 Blue Lake Plant Expansion Empire Plant Solids Hastings Plant Metro Plant Solids Interceptor projects deferred several years Northeast Area Northwest Area Southeast Anoka County Projects being implemented 1-2 years later than planned Victoria Area Richfield Area Chaska Lift Station Golden Valley Interceptor East Bethel Water Reclamation New Germany WWTP
11
Capital Improvement Program Expenditures by Year ($ millions) 2010-2015 Total = $754 Million
12
Capital Improvement Program Cost Breakdown by Project Type Total Program 2010 - 2015 $754 million
13
Capital Improvement Program Comparison with previous years 2009 2008
14
Authorized Capital Program Requests One New Project Adjustments to Existing Projects Deletion of Completed Projects
15
New Project Metro Plant Nutrient Removal Request authorization for Preliminary Engineering Request $2,000,000 LakePepin TMDL Lake Pepin TMDL Public Hearing is Planned for Fall 2009
16
Metro Plant Rehabilitation and Facilities Improvements Request $69,000,000 Request $69,000,000 Adjustments to Existing Projects
17
Blue Lake Plant Improvements Request ($34,000,000) Request ($34,000,000) Adjustments to Existing Projects
18
Maple Grove Brooklyn Park Adjustments to Existing Projects Elm Creek Interceptor Request $3,000,000 Request $3,000,000 Replenish Funds Used in Conjunction with the Trunk Highway 610 Extension Project
19
Adjustments to Existing Projects Golden Valley Area Improvements Request $1,000,000
20
Adjustments to Existing Projects Hopkins System Improvements Request $27,000,000
21
Interceptor Rehabilitation - Trenchless Construction funding needed for Phase 3 Adjustments to Existing Projects Request $4,000,000 Request $4,000,000
22
Lift Station Improvements Construction funding for 4 of the project’s lift stations Adjustments to Existing Projects Request $28,500,000 Request $28,500,000 L7 L30 L35 L66 Savage Mounds View Mahtomedi Crystal
23
Adjustments to Existing Projects Elko-New Market Interceptor Request ($7,000,000)
24
Summary of Adjustments $69,000,000-$34,000,000$3,000,000$1,000,000$27,000,000$4,000,000$28,500,000-$7,000,000 Metro Rehab. & Facilities Improvements Blue Lake Plant Improvements Elm Creek Interceptor Golden Valley Area Improvements Hopkins System Improvements Interceptor Rehabilitation – Trenchless Lift Station Improvements Elko-New Market Interceptor Existing Projects Adjustment $91,500,000 Subtotal Authorization Adjustments:
25
Deletion of Completed Projects 7 Projects $211,900,000 Projects will be completed in 2009 MWWTP Electrical Cable ReplacementMWWTP Electrical Cable Replacement MWWTP Solids – Odor Control, Centrifuge, Sludge StorageMWWTP Solids – Odor Control, Centrifuge, Sludge Storage Empire Plant Service Area CapacityEmpire Plant Service Area Capacity Dayton-Champlin InterceptorDayton-Champlin Interceptor Interceptor System Standby Power ImprovementsInterceptor System Standby Power Improvements Riverview Siphon (SP-230)Riverview Siphon (SP-230) Wastewater Facilities Security ImprovementsWastewater Facilities Security Improvements
26
Proposed Authorized Capital Program Summary 2009 Program New Project Adjustments$1,139,000,0002,000,00091,500,000 Completed Projects (211,900,000) (211,900,000) 2010 Program $1,020,600,000
27
Expenditures ($ millions) Proposed Authorized Capital Program 2010 Program $1,021 Pre-20092009Projected 2010 - 2015 $264$95$662
28
Proposed 2010 Capital Budget Projected 2009 Expenditures $100 Million 2010 Capital Budget $158 Million
29
Proposed Schedule Capital Finance Plan Aug 25th Public Hearing and Adoption Nov, 2009 Aug 11th Capital Program and Budget Sep, 2009 Incorporate into the Unified Capital Improvement Program and Unified Capital Budget