Download presentation
Presentation is loading. Please wait.
Published byClyde Booker Modified over 9 years ago
1
Report @ CERN- KEK about LHC upgrades programs Lucio Rossi 14 December 2011
2
The path and goals: 3000 fb -1 – L peak < 5 10 34 LRossi@CERN-KEK Dec20112 Rad. damage
3
Tuning of the goal after summer Efficiency is defined as the ratio between the annual luminosity target of 250 fb -1 over the potential luminosity that can be reached with an ideal cycle run time with no stop for 150 days: t run = t lev +t dec +t turn. The turnaround time after a beam dump is taken as 5 hours, t decay is 3 h while t lev depends on the total beam current LRossi@CERN-KEK Dec20113
4
Cycle in the HL-LHC run 20E+34 pile up heat deposition in IR and DS other? pile up heat deposition in IR and DS other? LRossi@CERN-KEK Dec20114
5
Possible evolution toward 3000 fb -1 LRossi@CERN-KEK Dec20115
6
IR Magnets (triplet, D1, D2, MQ4, …) SC Crab Cavities, IR Collimation LRossi@CERN-KEK Dec20116
7
7 Other changes Cryogenics Cryogenics During LS2, a new refrigerator will be installed at P4, to feed RF cavities and restore IR 5L During LS2, a new refrigerator will be installed at P4, to feed RF cavities and restore IR 5L Refrigerator 6.5 kW @ 4.5 K: Refrigerator 6.5 kW @ 4.5 K: 4.5 kW + 0.25 kW (flash) + 0.12 kW (thermal losses line & valve box) + 1.6 kW (contingency 33%) 4.5 kW + 0.25 kW (flash) + 0.12 kW (thermal losses line & valve box) + 1.6 kW (contingency 33%) During LS3 new refrigerators for P1-P5 During LS3 new refrigerators for P1-P5 Warm compressor installed in surface. Warm gas lines in Pit Warm compressor installed in surface. Warm gas lines in Pit Cold boxes installed in underground and surface (if 2 K or 1.8 K options) Cold boxes installed in underground and surface (if 2 K or 1.8 K options) Distribution and transfer lines to equipments (magnets, DFBs, crab-cavities ?, SCL ?, sector powering ?...) Distribution and transfer lines to equipments (magnets, DFBs, crab-cavities ?, SCL ?, sector powering ?...)
8
LRossi@CERN-KEK Dec20118 Other changes (list not exhaustive…) R2E: whatever needed, see from experience frome next years R2E: whatever needed, see from experience frome next years P8 P8 Removal of EPC and DFBX from tunnel to surface via long SC links rated of 0.1-1 GW d.c. Removal of EPC and DFBX from tunnel to surface via long SC links rated of 0.1-1 GW d.c.
9
LRossi@CERN-KEK Dec20119 LIU – LHC Inj Upgrade (R. Garoby) LS2 (2018) and LS3 (2012-23) Linac4 (160 Mev H- vs. 50 MeV H of Linac2) Ready by mid 2014 Connected 2015? Reliability, brilliance… Linac4 (160 Mev H- vs. 50 MeV H of Linac2) Ready by mid 2014 Connected 2015? Reliability, brilliance… PS Booster upgrade: from 1.4 GeV (800 Gev) to 2 GeV to reduce space ahrge at PS injection Intensity gain : +65% Project launched; PS Booster upgrade: from 1.4 GeV (800 Gev) to 2 GeV to reduce space ahrge at PS injection Intensity gain : +65% Project launched; SPS reduction of impedence new optics with low t (26 15 GeV) new 200 MHz cavities reduction e-clouds by vaccum chamber coating (or scrubbing?) SPS reduction of impedence new optics with low t (26 15 GeV) new 200 MHz cavities reduction e-clouds by vaccum chamber coating (or scrubbing?)
10
The HL composition, larger than FP7 HiLumi Collimation Project Matching section and correctors Beam Diagnostics High Field Magnets R&D HE-LHC Studies Hardware Commissioning EuCARD2 WP10 on HTS dipoles LRossi@CERN-KEK Dec201110
11
LRossi@CERN-KEK Dec201111 Budget FP7 HiLumi and HL-LHC Perfect score 15/15, ALL request to EU granted Estimated cost for the the whole HL-LHC over 10 years in M€ (October 2010)
12
LRossi@CERN-KEK Dec201112 3 days Collaboration Meeting at CERN 14-18 Nov (160 people) Collaboration Board members/invited
13
LRossi@CERN-KEK Dec201113
14
Staff HiLumi Design Study, with 377 p-m by US Labs and 159 by KEK (Magnets, CC, AP) 163 FTE-y LRossi@CERN-KEK Dec201114
15
LRossi@CERN-KEK Dec201115 New baseline to follow the new EU strategy for HEP! Goal: HL-LHC approved by 2013 CB of 17 Nov 2011, message from President of Council, Prof. Spiro: PDR needed in preliminary form by Oct 2012, endorsed by SAC and MAC, approved by CERN Mngt for Council and HEP strategy Group (final step : Council Bruxelles June 2013) CB of 17 Nov 2011, message from President of Council, Prof. Spiro: PDR needed in preliminary form by Oct 2012, endorsed by SAC and MAC, approved by CERN Mngt for Council and HEP strategy Group (final step : Council Bruxelles June 2013) Need to fix choice earlier
16
Malta Workshop14-16 October 2010 HE-LHC @ 33 TeV c.o.m LRossi@CERN-KEK Dec201116 Magnet design: very challanging but not impossible. 300 mm inter-beam Multiple powering in the same magnet (and more sectioning for energy) Work for 4 years to assess HTS for 2X20T to open the way to 16.5 T/beam. Otherwise limit field to 15.5 T for 2x13 TeV Higher INJ energy is desirable (2xSPS) The synchrotron light is not a stopper by operating the beam screen at 60 K. The beam stability looks « easier » than LHC thanks to dumping time. Collimation is possibly not more difficult than HL-LHC. Reaching 2x10 34 appears reasonable. The big challenge, after main magnet technology, is beam handling for INJ & beam dump: new kicker technology is needed since we cannot make twice more room for LHC kickers.
17
LRossi@CERN-KEK Dec201117 EC - FP7 EuCARD2 joint research activity WP10 : Future Magnets : 2013-2016. WP10 : Future Magnets : 2013-2016. 5 T HTS Dipole Magnets 40 mm bore Accelerator Quality 5 T HTS Dipole Magnets 40 mm bore Accelerator Quality To be tested as insert in existing 13 T magnet To be tested as insert in existing 13 T magnet KEK and Univ. of Kyoto (and 5 US labs & Univ) declared associate collaborators. Interest in YBCO technology. KEK and Univ. of Kyoto (and 5 US labs & Univ) declared associate collaborators. Interest in YBCO technology. BeneficiaryTotal Person- Months Total Personnel direct costs Total Personnel indirect costs Total Sub- contracting cost Total Consumable and prototype direct costs Total Travel direct costs Total Material and travel indirect costs Total direct costs Toal indirect costs Total costs (direct +indirect) Total EC requested funding CERN120 1,129,740 677,844 - 800,000 71,000 522,600 2,000,740 1,200,444 3,201,183 346,385 CEA54 321,278 202,405 - 160,000 20,000 - 501,278 202,405 703,683 315,805 INPG43 141,384 84,830 - 12,000 8,000 12,000 161,384 96,830 258,214 101,672 INFN39 144,495 86,697 - 130,000 14,000 86,400 288,495 173,097 461,592 181,752 KIT16 94,224 100,800 - 80,000 10,000 - 184,224 100,800 285,024 116,061 SOTON 16 89,680 79,815 - 40,000 10,000 - 139,680 79,815 219,495 87,998 UNIGE 12 109,872 65,923 - 50,000 4,000 32,400 163,872 98,323 262,195 103,239 UT 20 131,580 78,948 - 50,000 8,000 34,800 189,580 113,748 303,328 119,435 BHTS 38 223,782 304,344 - 150,000 4,000 - 377,782 304,344 682,126 238,003 TUT 8 37,757 22,654 - - 12,000 7,200 49,757 29,854 79,612 31,347 DTI 10 66,687 46,681 - 20,000 6,000 - 92,687 46,681 139,368 58,393 TOTAL: 376 2,490,479 1,750,942 - 1,492,000 167,000 695,400 4,149,479 2,446,342 6,595,820 1,700,091
18
What is the possibile for HE-LHC? LRossi@CERN-KEK Dec201118 2005 2010 2015 2020 2025 2030 2035 US 16 T small dipole EuCARD 13 T large dipole+ 18 T small insert US 13 T Quads FP7-HiLumi US NbSn-HTS development 15-20 T dip final proto & Industrialization Final delivery Magnets HE-LHC HE-LHC start-up HE-LHC preliminary study HTS for HE-LHC: yes.or.no LARP 11 T long quad EuCARD R&D Industry contracts, start constrution US basic programs and LARP R&D EU FP6-CARE-NED EuCARD2 full bore dipole HTS 15-20 T R&D dipole models and prototypes
19
LRossi@CERN-KEK Dec201119 HiLumi (and HE) LHC : the best use of the (renovated) existing infrastructure LHeC ?
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.