Download presentation
Presentation is loading. Please wait.
Published bySophie West Modified over 9 years ago
1
MEM 612 Project Management Chapter 5 Scheduling the Project
2
MEM 612 Project Management PERT AND CPM NETWORKS
3
MEM 612 Project Management History Late 1950s –Program Evaluation and Review Technique (PERT) U.S. Navy, Booz-Allen Hamilton, and Lockeheed Aircraft Probabilistic activity durations –Critical Path Method (CPM) Dupont De Nemours Inc. Deterministic activity durations
4
MEM 612 Project Management The Language of PERT/CPM Activity –task or set of tasks –use resources Event –state resulting from completion of one or more activities –consume no resources or time –predecessor activities must be completed
5
MEM 612 Project Management The Language of PERT/CPM continued Milestones –events that mark significant progress Network –diagram of nodes and arcs –used to illustrate technological relationships Path –series of connected activities between two events
6
MEM 612 Project Management The Language of PERT/CPM concluded Critical Path –set of activities on a path that if delayed will delay completion of project Critical Time –time required to complete all activities on the critical path
7
MEM 612 Project Management Building the Network AOA Network AON Network
8
MEM 612 Project Management Table 5-1 A Sample Set of Project Activities and Precedences
9
MEM 612 Project Management Figure 5-1 Stage 1 of a Sample AON Network
10
MEM 612 Project Management Figure 5-2 Stage 2 of a Sample AON Network
11
MEM 612 Project Management Figure 5-3 A Completed Sample AON Network
12
MEM 612 Project Management Figure 5-4 Stage 1 of a Sample AOA Network
13
MEM 612 Project Management Figure 5-5 Stage 2 of a Sample AOA Network
14
MEM 612 Project Management Figure 5-6a A Completed Sample AOA Network
15
MEM 612 Project Management Figure 5-6b A Completed Sample AOA Network Showing the Use of a Dummy Task
16
MEM 612 Project Management Table 5-2 A Sample Problem for Finding the Critical Path and Critical Time
17
MEM 612 Project Management Figure 5-7 Stage 1 of a Sample Network
18
MEM 612 Project Management Figure 5-8 A Complete Network
19
MEM 612 Project Management Figure 5-9 Information Contents in an AON Node
20
MEM 612 Project Management Figure 5-10 The Critical Path and Time for Sample Project
21
MEM 612 Project Management Calculating Activity Slack Slack or Float LST - EST = LFT - EFT = Slack
22
MEM 612 Project Management PROJECT UNCERTAINTY AND RISK MANAGEMENT
23
MEM 612 Project Management Calculating Probabilistic Activity Times Three Time Estimates a.k.a 3-point estimation or beta distribution PERT technique to measure 3 values of estimates: –pessimistic (a) – min reasonable period of time –most likely (m) – time required for completion –optimistic (b) – max reasonable period of time
24
MEM 612 Project Management Figure 5-13 The Statistical Distribution of all Possible Times for an Activity
25
MEM 612 Project Management Activity Expected Time and Variance
26
MEM 612 Project Management Example: Optimistic (a) = 10 days Most likely (m) = 13 days Pessimistic (b) = 25 days T E = [10 + 4(13) + 25] / 6 = 14.5 = 15 days σ 2 = [(25 – 10) / 6] 2 = 6.25 σ = 2.5 days
27
MEM 612 Project Management
28
95 Percent Level Task will be a or lower 5 percent of the time Task will be b or greater 5 percent of the time
29
MEM 612 Project Management 90 Percent Level Task will be a or lower 10 percent of the time Task will be b or greater 10 percent of the time
30
MEM 612 Project Management 95 Percent Level (Alternative Interpretation) Task will be between a and b 95 percent of the time
31
MEM 612 Project Management 90 Percent Level (Alternative Interpretation) Task will be between a and b 90 percent of the time
32
MEM 612 Project Management Figure 5-14 An AON Network
33
MEM 612 Project Management The Probability of Completing the Project on Time =NORMDIST(D, , ,TRUE)
34
MEM 612 Project Management Figure 5-18 The Statistical Distribution of Completion Times of the Path a-b-d-g-h
35
MEM 612 Project Management Selecting Risk and Finding D NORMINV(probability, , ,TRUE)
36
MEM 612 Project Management SIMULATION
37
MEM 612 Project Management Traditional Statistics Versus Simulation Similarities –must enumerate alternate paths Differences –simulation does not require assumption of path independence
38
MEM 612 Project Management THE GANNT CHART
39
MEM 612 Project Management Figure 5-23 A Gantt Chart of a Sample Project
40
MEM 612 Project Management Figure 5-14 An AON Network
41
MEM 612 Project Management Figure 5-24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFT
42
MEM 612 Project Management Figure 5-25 A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource Requirements
43
MEM 612 Project Management Figure 5-26 A Progress Report on a Day Care Project Showing Actual Progress Versus Baseline
44
MEM 612 Project Management EXTENSIONS TO PERT/CPM
45
MEM 612 Project Management Precedence Diagramming Finish-to-start linkage Start-to-start linkage Finish-to-finish linkage Start-to-finish linkage
46
MEM 612 Project Management Figure 5-27 Precedence Diagramming Conventions
47
MEM 612 Project Management Other Methods Graphical Evaluation and Review Technique (GERT) –combines flowgraphs, probabilistic networks, and decision trees –allows loops back to earlier events and probabilistic branching
48
MEM 612 Project Management Copyright Copyright John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in Section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information herein.
49
MEM 612 Project Management QUIZ
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.