IPA, component I: Transition assistance and institutional building Programming process for 2009 Sarajevo, 24.02.2009. BOSNA I HERCEGOVINA Council of Ministers.

Similar presentations


Presentation on theme: "IPA, component I: Transition assistance and institutional building Programming process for 2009 Sarajevo, 24.02.2009. BOSNA I HERCEGOVINA Council of Ministers."— Presentation transcript:

1 IPA, component I: Transition assistance and institutional building Programming process for 2009 Sarajevo, 24.02.2009. BOSNA I HERCEGOVINA Council of Ministers Directorate for European Integration

2 IPA, component I: Programming process for 2009 I.Key actors and bodies II.Key phases of the programming process and current situation III.Consultation process in Bosnia and Herzegovina

3  EC/DEC: Final authority for assessment and making decisions for financing project proposals  NIPAC - responsible for carrying out programming process for IPA 2009 on behalf of Bosnia and Herzegovina  DEI - NIPAC office (administrative and technical support to NIPAC):  SPOs: Representative of the state line ministry/institution for certain program/project area  EC/DEC: Final authority for assessment and making decisions for financing project proposals  NIPAC - responsible for carrying out programming process for IPA 2009 on behalf of Bosnia and Herzegovina  DEI - NIPAC office (administrative and technical support to NIPAC):  SPOs: Representative of the state line ministry/institution for certain program/project area I - IPA, component I: Key actors of the programming process for 2009

4  Programming management committee (PMC)‏ - DEI + DEC + NIPAC - manages the process: safety mechanism  Project programming committee (PPC)‏ - SPO + TM (DEI) + TM (DEC)‏ - manages the process of drafting the individual project proposal I - IPA, component I: Key bodies for implementation of the programming process for 2009

5 IPA, component I: Programming process for 2009  DEI prepaired Guidelines for IPA 2009 Programming Process  CoM addopted the document on 03. December 2008.  NIPAC and DEI organized the meeting with SPO-s on 15. December 2008. – launching of the Programming Process (IPA 2009 devided into 2 parts)

6 IPA, component I: Programming process for 2009  16. January 2009. SPO-s submitted the Project Ideas  Preliminary list of Project Ideas created  The List presented to IPA Coordination Committee (NIPACs advisory body)

7 IPA, component I: Programming process for 2009  End of January – NIPAC created priority list (4 Infrastructure projects + 15 TAIB projects)  13. February 2009. PMC decision on Infrastructure projects to be financed (4 Projects)  TAIB list not approved by Brussels  End of March 2009. – deadline for submission of PFs to DEC

8 IPA, component I: Programming process for 2009  During the Programming Process SPOs consulted institutions of RS, FBiH and BD through the network of entity programmers and entity coordinators  Around 60 institutions were consulted

9 IPA, component I: Programming process for 2009 Thank you for your attention