Aug 2003 Craig Ogilvie 1 Landscape/Goals for R&D Goal: Barrel+structure ready Summer/Fall 06 (run07) Goal: Endcaps ready Summer/Fall 07 (run08) RIKEN funds available 03, 04, 05 DOE construction funds –goal is FY05
2
Aug 2003 Craig Ogilvie 2 R&D Much ongoing effort, supported by RIKEN, LANL LDRD, ISU university funds, SUNY-SB funds R&D Priorities (FY03/FY04) pixel pilot and signal bus generic Si FEM (pixel, strip, endcap) strip/SVX4 readout ministrip PHX Later FY04 (when device better specified) mechanical support/cooling
3
Aug 2003 Craig Ogilvie 3 Si Strip Electronics (PHX + ministrip), –DOE funds FY03+FY04 –1 st round design finished by April-Jul ’04 –tested by Dec ’04 (SVX4 + strip) system test, starts Sep ’03 –two options for 1 st round of readout card »RIKEN funds+DOE R&D funds early FY04 u keeps on schedule »or wait till we decide between SVX4 and PHX Propose to group –make decision on which strip technology April ’04 –limited knowledge of PHX by then, so if PHX is the decision »fall-back is SVX4
4
Aug 2003 Craig Ogilvie 4 R&D Funds: Proposal ItemJY03JY04FY03 BNL FY03 DOE FY04 DOE FY05 DOE Pixel Pilot50 159045 Pixel Bus50 Pixel FEM/DCM159045 Strip sensors60 Strip ROC+FEM *300100125 mini-strip ROC80125140 mini-strip sensors15 mini-strip pilot/assembly100 mechanical/cooling200150 overhead4?208146 Total4602003480853641 *Strip ROC, contingent on decision, total is $300K less than needed
5
Aug 2003 Craig Ogilvie 5 Backup
6
Aug 2003 Craig Ogilvie 6 PHX Schedule Design specifications completed 10/03 Start design 12/03 Submit prototype 7/04 Prototype testing completed 12/04 Redesign completed for engineering run 1/05 Engineering run back 3/05 Ray Yarema, FNAL, June 9th
7
Aug 2003 Craig Ogilvie 7 PHX Cost Chip design/testing – 2 man-years - $275K (includes all overhead costs) Prototype chip fabrication- $40K (small chip) Test board $5K Engineering run (10-12 wafers) $200K 9 Extra wafers using same masks - $45K Production wafer level testing –engineering, tech time, circuit board, probe card - $60K Contingency tbd Ray Yarema, FNAL, June 9th 20 wafers total FY03-FY04 = 182K, FY04 =
8
Aug 2003 Craig Ogilvie 8 Physics of Strip Decision Occupancy –BNL strips 2 nd layer ~ 10%, mini-strips much less –“10%” needs to be checked (volunteer?) –ramifications »with projective geometry, 3-D hit is ambiguous u stand-alone tracking difficult, but not the main plan »projections from outer detectors (e.g. dch) u more than one hit may associate with same track u DCA ambiguous u envelope calculation ? or requires tracking team ? 3-D position information better with mini-strips –high-pt track rejection? –use with endcap? Heat-load different => thickness? (volunteer?)
9
Aug 2003 Craig Ogilvie 9 Other issues ambiguity may be a concern for proposals/reviewers –unlikely to affect CD0? –need to work on costs, WBS –need mini-strip sensor expert (volunteer?)