Substation L1/ Booster Substation Y-BE2 Update #3 August 15,2012
2
Status of Procurement Substation L1 Transformer fully tested Delivery expected in 1-2 weeks Pictures of completed substation will be sent prior to shipment Booster Transformer Y-BE2 RFP placed early August All proposals due by 8/31/2012 Temporary Wiring 350 MCM cable is hung and wired for temporary panel board Other temporary wiring will begin towards the end of August Panelboard 1 assembled 1 needs to be assembled
3
Status of Procurement (Cont.) Safety Switches Delivered Temporary installation will begin late August Cable Supports Delivered Installation will occur late August to early September Junction Box Built Will be shipped with substation
4
Substation Pictures
5
Substation Enclosure
6
Project Schedule September 17-28 General Cleanup 2-3 weeks prior to shutdown of substation Temporary electrical power will be completed the weekend prior (September 15 th ) It could take riggers several days to remove and install substations Small clearances Large weights Discussions are underway to move forward with cutting a hole in LINAC’s roof Contractors will be in this week to give a cost estimate
7
Temporary Power Plan “Siphon” power from panel DHP-L2-2 Circuit #1 Cable will be run on temporary supports 4 conductor 350 mcm cable is heavy (~7 lbs./ft.) and will need an open area to lay Some cable will be put on the floor but will be covered by a cable bridge Setup 2 temporary panel board(s) Run cable to individual loads DHP panels, MCC loads DHP panels will have potential hazards removed (mains, MCC, etc.) 13.8 kV lines will be disconnected MCC loads will have configuration control locks We will check current prior to using any MCC loads to ensure they will not trip off during operation Power will be provided 24 hours a day
8
Installation Costs 1 Crew of Riggers (4-6 men) Could be as much as $30k Will remain unknown until a finalized roof plan is put in place 2 Week of Electricians $100/manhour x 2 electricians x 80 hours = $16,000 Cable 2/0 - $3,500 2 – $3,700 House Power $4,200 for panelboard $2,000 for assembly Miscellaneous Stock purchases $2,100 Total Cost : $31,500 -> excluding rigging and roof Previous Estimate: $23,000 -> excluding rigging and roof Increase can be attributed to increased electrician time and panelboard cost
9
Future Create Site Wide Monitoring Network PIP Project HQ PIP Project ???? Note: CG-1 has been moved from PIP schedule, and will now be handled by headquarters
10
Booster Y-BE2 Update Replaced bad transformer Working well Decreased noise Less heat New transformer RFP Estimated cost of $150k Expect bids by end of August Procurement will begin within 30 days of receiving bids Will likely be much quicker Install Early next year Several days