December 3, 2015 TOWN OF MILLBURY DPW, MA Robert McNeil, P.E., Director PARE CORPORATION, FOXBORO, MA Allen R. Orsi, P.E., Managing Engineer This project.

Similar presentations


Presentation on theme: "December 3, 2015 TOWN OF MILLBURY DPW, MA Robert McNeil, P.E., Director PARE CORPORATION, FOXBORO, MA Allen R. Orsi, P.E., Managing Engineer This project."— Presentation transcript:

1 December 3, 2015 TOWN OF MILLBURY DPW, MA Robert McNeil, P.E., Director PARE CORPORATION, FOXBORO, MA Allen R. Orsi, P.E., Managing Engineer This project is funded in part by the Massachusetts Executive Office of Energy and Environmental Affairs (www.mass.gov/green)

2  Introduction  Design Overview  Design & Permit Status  Project Schedule  Funding Updates  Questions

3  Valve Replacement Status  Weed Control Drawdown Update

4

5  Use Restriction

6  Invasive Species Educational Signage

7

8

9

10  Jacques Park Site Improvement

11  Design, Permitting, & Bid Phase TaskStatus Finalize Permit ApplicationsDecember 2015 Receive PermitsOngoing – January 2016 Construction Contract AdvertisingJanuary 2016 Contract BiddingFebruary 2016 Bid OpeningMarch 2016 Contract AwardMarch 2016

12  Construction Activity (April thru July) MonthPotential Activity April 2016Mobilization / Start of Site Work Jacques Park Site Work May 2016Excavation / Existing Outlet Demolition Initiate New Outlet Installation Commence Upstream Wall June 2016Continue Upstream Wall Continue Outlet Installation July 2016Continue/Finish Outlet Installation Continue Upstream Wall Initiate Spillway Construction

13  Construction Activity (August thru November) MonthPotential Activity August 2016Continue Spillway Construction Continue Upstream Wall September 2016Continue Spillway Construction Complete Upstream Wall October 2016Complete Spillway Complete downstream slope regrading and drain installation Start Roadway Reconstruction November 2016Complete Roadway Reconstruction Install site amenities

14  Construction Activity (Winter thru Spring ‘17) MonthPotential Activity Winter 2016-2017Site Stabilization Winter Shutdown Spring 2017Construction Punch List Landscaping & Project Completion

15  Ramshorn Pond Elevations MonthPotential Activity April 2016 – July 2016820 July 2016 – October 2016825 (increasing as work progresses) October 2016 – April 2017Normal Winter Drawdown April 2017Restored to Normal