Presentation is loading. Please wait.

Presentation is loading. Please wait.

Construction OF AMMONIA REMOVAL UPGRADES FOR FIRST BROAD RIVER WWTP

Similar presentations


Presentation on theme: "Construction OF AMMONIA REMOVAL UPGRADES FOR FIRST BROAD RIVER WWTP"— Presentation transcript:

1 Construction OF AMMONIA REMOVAL UPGRADES FOR FIRST BROAD RIVER WWTP
David Hux, City of Shelby; Will Shull, Mary Knosby, and Christopher Crotwell, HDR 2015 NC AWWA WEA Annual Conference November 17, 2015, Raleigh

2 01 04 02 05 03 Topics for Today’s Presentation
Overview of Existing Plant 04 Construction Sequencing 02 Revised Ammonia Permit Limits 05 Summary and Conclusions 03 Ammonia Removal Upgrades Project

3 Overview of Existing Plant
01 Overview of Existing Plant

4 First Broad River WWTP Permitted for 6 mgd
Current avg flows 2.75 mgd prior to new industry ( ) Approx. 3.5 mgd with new industry Originally constructed in 1960’s Trickling Filter Plant Upgraded in 1993 Added polishing activated sludge aeration basins Two 0.75 MG aeration basins Jet pod aeration system Not sized for nitrification

5 First Broad River WWTP Process Flow Diagram
Polishing Aeration Basin

6 Revised Ammonia Permit Limits
02 Revised Ammonia Permit Limits

7 Revised Ammonia Permit Limit
2010 Permit Renewal included revised ammonia permit limits Summer Monthly average NH3-N From 18.5 mg/L to 4.7 mg/L Summer Weekly average NH3-N From 35 mg/L to 14.1 mg/L Based on DWR’s current ammonia policy 1 mg/L summer in-stream NH3-N Permit notes “EPA’s recent proposal have the potential to lower ammonia criteria further” 6-year compliance schedule provided YAD1391A

8 Current Effluent NH3-N Performance
WWTP upgrades required to meet revised ammonia limit

9 NPDES Permit Limit Summary
Parameter Monthly Average Weekly Average Daily Max Flow (mgd) 6.0 - BOD5 (mg/L) 25 37.5 TSS (mg/L) 30 45 Ammonia-N (Summer) (mg/L) 4.7 14.1 Ammonia-N (Winter) (mg/L) 18.5 35 Fecal Coliform 200/100 mL 400/100 mL TRC (mg/L) 28 µg/L pH >6.0 pH < 9.0 standard units Total Nickel 261 µg/L NPDES Permit Limit Summary

10 Ammonia Removal Upgrades Project
03 Ammonia Removal Upgrades Project

11 Project Goals Upgrade biological treatment process
Enhance nitrification to meet more stringent ammonia limits Repair and replace several deficient treatment components Improve treatment reliability Accommodate flows up to the permitted capacity of 6.0 mgd. Meet project schedule requirements for Clean Water State Revolving Fund (CWSRF) program

12 Biological Treatment Process Upgrades
Convert existing process to conventional activated sludge system Decommission trickling filters Add third 0.75 MG aeration basin Replace jet pods with fine bubble diffusers Provide additional blower capacity Add baffles / mixers for pre-anoxic zone For denitrification and alkalinity recovery

13 Construction of Aeration Basin 3
October 2014 September 2015 Add third 0.75 MG aeration basin August 2014 March 2015

14 Construction of Aeration Basin 3
Replace Existing DIP Air Header with Stainless Steel Route Stainless Steel Air Header under Walkway Add third 0.75 MG aeration basin Accounting for the design details (SS Piping) but not overlooking the little details such as providing the City with plenty of walkway access by routing piping under the walkway. Less cluttered.

15 New MLE Process Anoxic / Internal Recycle Discharge / Mixers Aerobic
(Fine Bubble) Aerobic (Fine Bubble) Aerobic (Fine Bubble) Internal Recycle Suction FLOW IR Add third 0.75 MG aeration basin Provide additional blower capacity Add baffles / mixers for pre-anoxic zone For denitrification and alkalinity recovery Zone 1, Cell A Zone 2 Zone 3 Zones 4 & 5

16 Construction Sequencing
04 Construction Sequencing

17 Construction Sequencing
Maintenance of Plant Operation Identity threats to operation Duration Coordination Contingency Plan Communication is vital to success Realize that plant must continue operation and maintain permit limits while getting the job done. All parties present, talk through as if it were happening now. Potential Threats to Operation -Rain (=High Flows), Compost/BFP, Industry (Clearwater) Duration (how long it the shutdown, tie-in expected to take)(how long can the City Manage Coordination Contingency Plan (Pumps, Generator, etc on standby)

18 AB Splitter Box Phasing
PC1 How to install while continuing plant operation? PC2

19 AB Splitter Box Phasing
PC1 TF1 How to install while continuing plant operation? Put trickling filters back into service How is the plant going to react PC2 TF2

20 AB Splitter Box Phasing
PC1 How to install while continuing plant operation? Put trickling filters back into service How is the plant going to react PC2 ABSB

21 WAS Pump Station Conversion
Self-priming centrifugal to non-clog submersible Selective demolition of structure Valve vault installation

22 WAS Pump Station Conversion
Phasing Challenges How can we waste? Temporary bypass? Conflicts with trickling filter Solution Pump to existing thickener with new pumps Similar heads and flow rates to existing system

23 Blower Upgrades Positive displacement to Turblex variable diffuser
More control More efficient Replace ductile iron with stainless steel piping Installed 3 new turblex blowers (2 duty, 1 standby)

24 Blower Upgrades Phasing challenges Phasing Solutions
Existing room full of blowers Keep plant operational Phasing Solutions Route new piping overhead Short coordinated shutdown MOPO led to solution

25 Blower Upgrades Startup challenges Proposed Solutions
Lower flows (less I&I) One AB in operation during retrofit Trouble meeting low air demand Proposed Solutions Waste to atm. via header blow-off valve Incomplete blower function Waste to atm. via AB2 header Noise pollution Waste to AB3 via AB2 header Introduce coarse Bubble but little effect on DO MOPO led to solution

26 Repair and Replacement Upgrades
Replace Influent Screen Recondition Clarifiers No. 1 and 2 and replace drive units, weirs, bridges and scrapers Replace and upgrade RAS pumps Rehab Primary Clarifiers

27 Repair and Replacement Upgrades, Cont’d
Install new 40-ft Gravity Thickener Install new Thickened WAS Pump Station Rehab 26-ft Gravity Thickeners and convert to Belt Filter Press Filtrate EQ Rehab Sludge Holding Tank

28 Summary and Conclusions
05 Summary and Conclusions

29 Summary and Conclusions
Ammonia upgrades provide future flexibility Accounts for future industrial changes Positioned for potentially more stringent effluent NH3-N limit Other upgrades will improve overall process reliability Better process control (ie, RAS / WAS pumping) Equalize side stream flows (filtrate EQ) Communication is vital to a projects success

30 Questions?


Download ppt "Construction OF AMMONIA REMOVAL UPGRADES FOR FIRST BROAD RIVER WWTP"

Similar presentations


Ads by Google