1. 2 ONGOING PROJECT -1-ROB AT PARAPPANANGADI-PROGRESS GRAPH-28.09.12 3.

Similar presentations


Presentation on theme: "1. 2 ONGOING PROJECT -1-ROB AT PARAPPANANGADI-PROGRESS GRAPH-28.09.12 3."— Presentation transcript:

1 1

2 2

3 ONGOING PROJECT -1-ROB AT PARAPPANANGADI-PROGRESS GRAPH-28.09.12 3

4 ONGOING PROJECT-1-PROGRESS PHOTOS-ROB AT PARAPPANANGADI-28.09.12 4

5 5 PARAPPANANGADI ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-calicut Side30 0 000 2Pile-NH Side33 0 000 3Pile-calicut Side(Railway)10 0 000 4Pile-NH Side (Railway)10 0 000 5Pile cap-calicut Side10 0 000 6Pile cap-NH Side11 0 000 7Pile cap-calicut Side (Railway)220 000 8Pile cap-NH Side (Railway)220 000 9Pier-Calicut Side10 0 000 Pier-NH Side11 0 000 Pier-Calicut Side (Railway)220 000 12Pier-NH Side (Railway)220 000 13Pier Cap-Calicut Side10 0 000 14Pier Cap-NH Side11 0 000 15Pier Cap-Calicut Side (Railway)220 000 16Pier Cap-NH Side (Railway)220 000 17Girder-Calicut Side10 0 000 18Girder-NH Side11 0 110 19Girder-Calicut Side (Railway)202 110 20Girder-NH Side (Railway)101 000 21Deck Slab-Calicut Side10 0 000 22Deck Slab-NH Side11 0 110 23Deck Slab-Calicut Side (Railway)202 000 24Deck Slab-NH Side (Railway)101 000 25Handrails & Kerb-Calicut side100% 0% 10% 0% 26Handrails & KerbNH side100% 0% 27Handrails & Kerb-Calicut side (Railway)0% 28Handrails & KerbNH side (Railway)0% 29RE Wall-Calicutside100% 0% 30RE Wall-NH side100% 0% 31RC Wall-Calicut side100% 0% 32RC Wall-NH side100% 0% 33Road work-WBM-Calicutside100%0%100% 30%0%30% 34Road Work-WBM-NH side100% 0% 35Road work-Calicutside (Railway)0% 36Road Work-NH side (Railway)0% 37Dirt wall AP2100% 0% 38Dirt wall AP1100% 0% 39Painting100% 0% 40Expansion joint21 0 000 41Miscellaneous works100% 0%

6 ONGOING PROJECT -2-ROB AT SULTANPET-PALAKKAD TOWN- PROGRESS GRAPH-28.09.12 6

7 ONGOING PROJECT -2-ROB AT SULTANPET-PALAKKAD TOWN- THIRD ARM-PROGRESS GRAPH-28.09.12 7

8 ONGOING PROJECT-2-PROGRESS PHOTOS-ROB AT SULTANPET- PALAKKAD TOWN-28.09.12 8

9 9 SULTANPET ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1PCC for Raft MOYAN Side330 000 2PCC for Raft Palakkad side110 000 3Raft Palakkad Side110 000 4Raft Moyans Side330 000 5Pile - Bus Stand side12102 12102 6Pile Cap- Bus Stand side303 202 7Pier- Bus Stand side303 000 8Pier Palakkad Side110 000 9Pier Moyans side330 000 10Pier Cap- Bus Stand side303 000 11Pier Cap Palakkad Side110 000 12Pier Cap Moyans side330 000 13Girder- Bus Stand side404 101 14Girder-Land Span-Palakkad Side220 000 15Girder-Land Span-Moyans Side440 000 16Deck Slab- Bus Stand side404 000 17Deck Slab-Land Span-Palakkad Side220 000 18Deck Slab-Land Span-Moyans Side440 000 19Girder-Railway span633 101 20Deck Slab-Railway Span633 000 21Bowstring girder220 000 22Casting of Bow arch bem220 000 23Casting of cross girders (RP4-RP5)13 0 000 24Casting Bracings-RP4-RP5550 000 25RE/R WALL PALAKKAD SIDE100% 0% 26RE/R WALL MOYAN SCHOOL SIDE100% 0% 27HR/FP/KERB Pkd SIDE100% 0% 28HR/FP/KERB Moyen's SIDE100% 0% 29HR/FP/KERB RAILWAY SPAN100% 0% 30Expansion Joint-Land span725 000 31BC/PAINTING100%75%25% 0% 32Road works-Moyans side100% 0% 33Road works-Pkd side100% 0%

10 ONGOING PROJECT -3-ROB AT KOILANDY-PROGRESS GRAPH- 28.09.12 10

11 ONGOING PROJECT-3-PROGRESS PHOTOS-ROB AT KOILANDY- 28.09.12 11

12 12 KOILANDY ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-Muthambi Side27 0 000 2Pile-Thamarachery Side33 0 000 3Pile-NH Side33 0 000 4Pile cap-Muthambi Side990 000 5Pile cap-Thamarachery Side11 0 000 6Pile cap-NH Side11 0 000 7Pier-Muthambi Side990 000 8Pier-Thamarachery Side11 0 000 9Pier-NH Side11 0 000 10Pier Cap-Muthambi Side990 000 11Pier Cap-Thamarachery Side11 0 000 12Pier Cap-NH Side1091 101 13Girder-Muthambi Side990 000 14Girder-Thamarachery Side10 0 000 15Girder-NH Side1082 211 16Deck Slab-Muthambi Side990 110 17Deck Slab-Thamarachery Side10 0 110 18Deck Slab-NH Side1082 202 7Handrails & Kerb-NH side972 000 8Handrails & Kerb-Baluchery side1055 550 9Handrails & Kerb-Muthambi side1046 000 13RC Wall-NH side100%90%10% 100% 0% 14RC Wall-Baluchery side100%50% 100%50% 15RCWall-Muthambi side100%0%100% 25%0%25% 16Expansion Joint-NH side1239 000 17Expansion Joint-Baluchery side1147 541 18Expansion Joint-Muthambi side972 000 19Road work-NH side100%0%100% 0% 20Road Work-Baluchery side100%0%100% 0% 21Road Work-Muthambi side100%0%100% 0%

13 ONGOING PROJECT -4-ROB AT CHERUVATHUR-PROGRESS GRAPH-28.09.12 13

14 ONGOING PROJECT-4-PROGRESS PHOTOS-ROB AT CHERUVATHUR-28.09.12 14

15 15 CHERUVATHUR ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-Cheruvathur side27 0 0 2Pile-Padanna side24 0 0 3Pilecap-Cheruvathurside990 0 4Pilecap-Padanna side880 0 5Pier-Cheruvathur side990 0 6Pier-Padanna side880 0 7Piercap-Cheruvathur side990 0 8Piercap-Padanna side880 0 9Girders-Cheruvathur side981 0 10Girder-Padanna Side871 0 11Deck Slab-Cheruvathur side981 0 12Deckslab-Padanna Side871 0 13Handrails on Cheruvathur side100%90%10% 0% Adjacent span to be done 14 Kerb-Cheruvathur side100% 0% 15Handrails on Padanna side100%90%10% 0% Adjacent span to be done 16Kerbs - Padanna side100% 0% 17Handrail on Approch portion-Cheruvathur side100% 0% 100% 0% 18Handrail on Approch portion-Padanna side100% 0% 100% 0% 19Expansion joint-Cheruvathur side1073 000 Adjacent span,Approach to be done 20Expansion joint-Padanna side963 000 Adjacent span,Approach to be done 21RE Panel Erection - Cheruvathur side100% 0% 15% 0% 22Retaining Wall -Cheruvathur side100% 0% 23RE Panel Erection - padanna side100%0%100% 24Retaining Wall Padanna side100% 0% 5% 0% 25Road work Cheruvathur side100%0%100% 30%0%30% 26Road work Padanna side100%0%100% 0%

16 ONGOING PROJECT -5-ROB AT DEVADHAR-PROGRESS GRAPH- 28.09.12 16

17 ONGOING PROJECT-5-PROGRESS PHOTOS-ROB AT DEVADHAR- 28.09.12 17

18 18 DEVDAR ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-calicut Side48 0 000 2Pile-Thirur Side24 0 000 3Pile cap-calicut Side12 0 000 4Pile cap-Thirur Side660 000 5Pier-Calicut Side12 0 000 6Pier-Thirur Side660 000 7Pier Cap-Calicut Side12 0 000 8Pier Cap-Thirur Side660 000 9Girder-Calicut Side12111 110 10Girder-Thirur Side651 110 11Deck Slab-Calicut Side12111 330 12Deck Slab-Thirur Side642 101 13Handrails -Calicut side1284 532 14Handrails -Thirur side606 000 13 Kerb-Calicut side12102 220 14 KerbThirur side642 000 15RC Wall-Calicut side100%65%35% 0% 16RC Wall-Thirur side100%95%5% 25%20%5% 17Expansion Joint-Calicut side1367 440 18Expansion Joint-Thirur side716 01 19Road work-Calicutside100%0%100% 0% 20Road Work-Thirur side100%0%100% 0%

19 ONGOING PROJECT -6-ROB AT THIRUNNAVAYA-PROGRESS GRAPH-28.09.12 19

20 ONGOING PROJECT-6-PROGRESS PHOTOS-ROB AT THIRUNNAVAYA-28.09.12 20

21 21 THIRUNAVAYA ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-kanjipura Side30 0 2Pile-kuttipuram Side33 0 3Pile cap-kanjipura Side10 0 4Pile cap-kuttipuram Side11 0 5Pier-kanjipura Side10 0 6Pier-kuttipuram Side11 0 7Pier Cap-kanjipura Side10 0 0 8Pier Cap-kuttipuram Side11 0 0 9Girder-kanjipura Side990 0 10Girder-kuttipuram Side1064 220 11Deck Slab-kanjipura Side990 0 12Deck Slab-kuttipuram Side1064 220 13Handrails on kanjipura side954 220 14 Kerb-kanjipura side981 000 15Handrails on kuttipuram side100 0 16Kerb kuttipuram side1055 220 17RC Wall-kanjipura side100%0%100% 18RC Wall-kuttipuram side100%26%74% 19Expansion Joint-kanjipura side100 440 20Expansion Joint-kuttipuram side120 21Road work-kanjipuraside100%0%100% 22Road Work-kuttipuram side100%0%100%

22 ONGOING PROJECT -7-ROB AT PONNURUNNI-PROGRESS GRAPH- 28.09.12 22

23 ONGOING PROJECT-7-PROGRESS PHOTOS-ROB AT PONNURUNNI-28.09.12 23

24 24 PONNURUNNI ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done- Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1 PILE Palarivattom side(Approach portion)31 0 0 2PILE Palarivattom side(railway portion)660 0 3PILE vytilla side(Approach portion)42 0 0 4PILE vytilla side(railway portion)660 0 5 PILE CAP Palarivattom side(Approach portion)880 0 6 PILE CAP Palarivattomside(railway portion)110 110 7PILE CAP vytilla side(Approach portion)990 0 8PILE CAP vytilla side(railway portion)101 000 9 PIER Palarivattom side(Approach portion)880 0 10PIER Palarivattomside(railway portion)101 0 11PIER Vytilla side(Approach portion)990 0 12PIER vytilla side(railway portion)101 0 13 PIER CAP Palarivattom side(Approach portion)880 0 14 PIER CAP Palarivattomside(railway portion)110 0 15PIER CAP Vytilla side(Approach portion)990 0 16PIER CAP vytilla side(railway portion)101 0 17 GIRDER Palarivattom side(Approach portion)871 000 18GIRDER Vytilla side(Approach portion)972 101 Including Soild slab 19 DECK SLAB Palarivattom side(Approach portion)871 110 20 DECK SLAB Vytilla side(Approach portion)972 000 Including Soild slab 21RE Wall Panel351 0 0 22RE Wall Panel erection Palarivattam side100%16%84% 0%1 23Pile Load Test on RP2110 000 24Dirt wall20.71.3 0.70 25Expansion joint20713 431 26Handrail19811 532

25 ONGOING PROJECT -8-ROB AT ANAYARA-PROGRESS GRAPH- 28.09.12 25

26 ONGOING PROJECT-8-PROGRESS PHOTOS-ROB AT ANAYARA- 28.09.12 26

27 27 ANAYARA ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-Pettah Side12 0 000 2Pile-Anayara Side12 0 000 3Pile cap-Pettah Side440 000 4Pile cap-Anayara Side440 000 5Pier-Pettah Side440 000 6Pier-Anayara Side440 000 7Pier Cap-Pettah Side440 000 8Pier Cap-Anayara Side440 000 9Girder-Pettah Side431 110 10Girder-Anayara Side431 0 11Deck Slab-Pettah Side422 110 12Deck Slab-Anayara Side431 0 13Handrails & Kerb-Pettahside100%0%100% 0% 14Handrails & KerbAnayara side100%0%100% 0%100% 15RE panel casting100% 0% 16RE Wall-Pettah side100%88%12% 0% 17RE Wall-Anayara side100% 0% 18RC Wall-Pettahside100% 0% 19RC Wall-Anayara side100% 0% 20Expansion Joint-Pettahside100%0%100% 0% 21Expansion Joint-Anayara side100%0%100% 0% 22Road work-Pettah side100%25%75% 0% 23Road Work-Anayara side100%25%75% 0%

28 ONGOING PROJECT -9-ROB AT KORATTYANGADI-PROGRESS GRAPH-28.9.12 28

29 ONGOING PROJECT-9-PROGRESS PHOTOS-ROB AT KORATTYANGADI -28.09.12 29

30 30 KORATTYANGADI ROB-PROJECT STATUS REPORT AS ON KORATTY 2012 Si NoActivity Description Total Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1 Pile (approach portion)20 0 2 Pile (Railway portion)18 0 4 Pile cap (approach portion)550 5 Pile cap (Railway portion)440 7 Pier (approach portion)550 8 Pier (Railway portion)440 9 Pier cap (approach portion)550 11 Pier cap (Railway portion)440 12 Approach SPAN DECK 550 14Railway Span Deck 303 15Re wall towards NH side100%95% 5% 16 R0AD WORK100%50% 17Kerb/handrail (approach portion)N.H side100%90%10% 0%10%

31 ONGOING PROJECT -10-RIVER BRIDGE ACROSS THOOTHAPUZHA CONNECTING EDAPPALAM AND MOORKKANAD-PROGRESS GRAPH-28.09.12 31

32 ONGOING PROJECT-10-RIVER BRIDGE ACROSS THOOTHAPUZHA CONNECTING EDAPPALAM AND MOORKKANAD-PROGRESS PHOTOS -28.09.12 32

33 33 EDAPPALAM-MORRKKANAD RIVER BRIDGE-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile48 0 2Pilecap11 0 3Pier11 0 4Piercap11 0 0 7Girders1073 000 8Deckslab1073 110 9 Handrails & footpath slab casting100%0%100% 10Retaining Wall Edapalam side100% 0% 10% 0% 11Retaining Wall Moorkanad side100%25%75% 0%25%-25% 12 Drain Works Moorkanad side100%0%100% 0%100% 13Expansion Joint110 312 14Road work Edapalam side100%0%100% 15Road work Moorkanad side100%0%100%

34 ONGOING PROJECT-11-RIVER BRIDGE ACROSS PERIYAR CONNECTING STATIONKADAVU & VALIYAPAZHAMPILLITHURUTHU-PROGRESS GRAPH -28.09.12 34

35 ONGOING PROJECT-11-RIVER BRIDGE ACROSS PERIYAR CONNECTING STATIONKADAVU & VALIYAPAZHAMPILLITHURUTHU-PROGRESS PHOTOS -28.09.12 35

36 36 STATIONKADAVU RIVER BRIDGE-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity Description Total Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done- Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile791465 15213 2Pilecap120 000 3Pier120 000 4Piercap120 000 7Girders110 000 8Deckslab110 000 9 Handrails & footpath slab casting100%0%100% 000 10 Retaining Wall Paliyam side100%0%100% 000 11 Retaining Wall Thrissur side100%0%100% 000 12Road work Paliyam side100%0%100% 000 13Road work Thrissur side100%0%100% 0%

37 37 THANK YOU