Presentation is loading. Please wait.

Presentation is loading. Please wait.

Surface Ship Maintenance and Modernization

Similar presentations


Presentation on theme: "Surface Ship Maintenance and Modernization"— Presentation transcript:

1 Surface Ship Maintenance and Modernization
Third Party Planning Contract Implementation

2 Third Party Planning Agenda
Contract Strategy Services Available Ship Class / Homeport Breakdown Contract Status Update Contract Structure Contract Management Process and Deliverables Ship Check Management Long Lead Time Material Support Induction Schedule Implementation POA&M, Successes, and Challenges Paul Murphy MACMO slide Morgan MACMO milestones slide ADD MSRA/ABR slides into backup

3 Third Party Planning Contract Strategy
Assistant Secretary of the Navy for Research, Development & Acquisition (ASN-RDA) advocated for greater competition when contracting for depot level maintenance and modernization execution This direction led to the development of three National contracts which are being solicited and awarded for advanced planning services* CG 47 and DDG 51 Class LSD 41/49 and LPD 17 Class LHA 6 and LHD 1 Class *DDG 1000 Class, LCS Class, PC 1 Class, and MCM 1 Class not in contract scope Contracts awarded and administered by NAVSEA HQ Strategy Supports Pivot to Firm Fixed Price Execution Contracts

4 Third Party Planning Services Available
CNO CMAV EM CM Execute CMP assessments Validate shipboard equipment configuration Document assessment results Support tailored to RMC requirements Assessment Execution Clarify 2-kilos received using ship checks and interface with RMCs Continually develop 4E compliant work specifications Develop CNO availability work package analysis for use by RMCs Provide technical support to local RMCs during the solicitation process Planning Support Identify, procure, and ship long lead time material Provide support for provisioning of engineering and technical data, configuration management ILS Support Support RMCs in addressing technical scope and cost estimates documented in original work item CFRs Support RMCs in developing growth RCCs and new work items Execution Support Analyze availability execution RCCs to support improvements to Master Specification Catalog templates and incorporating lessons learned Feedback Analysis

5 Strategy supports expiration of existing MSMO contracts
Third Party Planning Ship Class/Homeport Breakdown Everett MSMO Expiration Date DDG 51 - Sep 15 (D) DDG 51 – Sep 16 (ND) Phased implementation plan 2015 – begin CNO availability planning 2016 – begin CM/EM planning Norfolk MSMO Expiration Dates CG 47 - Sep 15 LSD 41/49 - Sep 15 DDG 51 - Dec 15 (ND) DDG 51 - Mar 16 (D) LHD 1 - May 16 LPD 17 – Sep 16 (TSMO) LPD 19 /24 – Sep 17 San Diego MSMO Expiration Dates LPD 17 - Jun 15 DDG 51 - Sep 15 CG Sep 16 LSD 41/49 - Sep 17 LHA 6/LHD 1 - Sep 18 Strategy supports expiration of existing MSMO contracts

6 CRUDES and LPD/LSD contracts awarded to Q.E.D. Systems Incorporated
Third Party Planning Contracts Status Update Contract Development Milestones CG/DDG RFP Released September 2014 CG/DDG Proposals Received 20 October 2014 CG/DDG Contract Award 09 February 2015 First Ship: CG 60 – USS NORMANDY (Avail Start: 23 February 2016) LSD/LPD RFP Release 17 November 2014 LSD/LPD Proposals Received 06 January 2015 LSD/LPD Contract Award 27 May 2015 First Ship: LPD 18 – USS NEW ORLEANS (Avail Start: 12 December 2016) LHA/LHD RFP Release 03 December 2015 LHA/LHD Proposals Received 27 January 2016 LHA/LHD Notional Contract Award 10 May 2016 First Ship: LHD 5 – USS BATAAN (Avail Start: 27 November 2017) CRUDES and LPD/LSD contracts awarded to Q.E.D. Systems Incorporated

7 Contract structure does not utilize Award Fee Boards
Third Party Planning Contract Structure Contract Type - Cost Plus Fixed Fee Level of Effort for services provided One base year, two option years, two award term years Maximum Fixed Fee of 6% Performance Incentive Fee Maximum Incentive Fee of 5% Predetermined, objective, formula based evaluation factors 12 month performance evaluation period Government can unilaterally change evaluation factors Contract structure does not utilize Award Fee Boards

8 Third Party Planning Contract Management
COR Responsibilities Overall Technical and Fiscal Management ACOR Responsibilities Assist COR with performance incentive management Manage TI technical performance across ports Drive feedback and institutionalize lessons learned TPOC/APM Responsibilities TI Origination – define RMC port level requirements TI Technical Compliance – Interface with MTs to monitor and document quality of planning services provided Contract Oversight Team RMC SURFMEPP SEA 21 SEA02 PCO COR ACOR TPOC/APM Contract Funding Continuous funding flow is a prerequisite Hull level estimates developed annually for next fiscal year planning requirements Incremental funding provided by TYCOM to NAVSEA on a quarterly basis Funding required to authorize Technical Instructions

9 Minimal legacy planning process changes
Third Party Planning Process and Deliverables All planning IAW JFMM Maximize use of local planning personnel New RMC C300 function: Advance Planning Manager/Technical Point of Contact CNO Availability Planning Work Specification Development Cost Estimates Engineering Issues Work Specification Review/Approval Face to Face Specification Reviews Work Package Development Progress Reporting/Meeting Attendance Work Package Integration Work Package Turnover Support during Solicitation Process CM / EM Planning EM work specifications have a mandatory 24 hour turnaround Minimal legacy planning process changes

10 Continuous planning ship checks utilizing local personnel
Third Party Planning Ship Check Management Planning floor has 14 calendar days to seek clarification or reject 2 Kilos assigned for planning Ship checks will be conducted: ideally, on the vessel in homeport on a “sister ship” of same class when authorized by RMC PM out of homeport, when necessary All ship checks will be coordinated with the RMC PM All ship checks will be executed utilizing a ship check template and results documented for Government review Completion of a ship check will be annotated on the standard cost estimating form associated with the work specification All travel in support of ship checks must be authorized by the Government Continuous planning ship checks utilizing local personnel

11 Third Party Planning Long Lead Time Material Support
LLTM is defined as material with a procurement lead time greater than 30 days prior to start of an availability 3PP will identify and document LLTM on Work Items during work specification development RMC PM concurs with LLTM identification and determines whether 3PP needs to procure Procuring Contracting Officer (PCO) issues a contract modification for purchase of LLTM When directed by COR/ACOR, 3PP will transfer LLTM to executing shipyard

12 3PP will warehouse materials that it procures.
Third Party Planning Long Lead Time Material Support FLEET provides quarterly funding to NAVSEA 02 for LLTM. Technical Instructions will track the cost of ILS support associated with the labor hours for procurement and inventory. 3PP provides a monthly report that lists all LLTM identified for an availability with details concerning its procurement, shipping and receipt status. 3PP will warehouse materials that it procures. SIs (Provisioning Technical Documentation (PTD)) and (Technical Manual Contract Requirement (TMCR) for New Technical Manuals for Commercial Equipment/Component)

13 Flexibility to meet NAVSEA/TYCOM/RMC planning requirements
Third Party Planning Contract Management Technical Instruction – provides clarification of services being procured Number of work specifications Meeting attendance Planning Milestones Planning POCs Types of Technical Instructions (TI) CNO Availability Planning CMAV/EM/CM Planning LLTM Procurement Labor Base Year Period of Performance (POP) = 12 months from contract award TI POP within CLIN POP TI developed by RMC, approved by COR, released by PCO Flexibility to meet NAVSEA/TYCOM/RMC planning requirements

14 Third Party Planning CNSL - CRUDES Induction Schedule
Ship Ship Name Avail Type FY Start Planning (A-540) Avail Start Date NSA CG 0060 NORMANDY SRA4-1 2016 9/1/2014 2/23/2016 SPORT DDG 0096 BAINBRIDGE SRA2-1 1/18/2015 7/11/2016 CG 0064 GETTYSBURG SSRA1 2/8/2015 8/1/2016 DDG 0061 RAMAGE ESRA 3/22/2015 9/12/2016 DDG 0066 GONZALEZ EDSRA 4/5/2015 9/26/2016 DDG 0107 GRAVELY SRA1-2 DDG 0084 BULKELEY SRA2-2 2017 4/26/2015 10/17/2016 CG 0069 VICKSBURG 7/12/2015 1/2/2017 CG 0068 ANZIO ICMAV 10/4/2015 3/27/2017 DDG 0094 NITZE 11/1/2015 4/24/2017 DDG 0055 STOUT SRA3-2 11/22/2015 5/15/2017 DDG 0087 MASON 12/20/2015 6/12/2017 DDG 0103 TRUXTUN DSRA1 3/20/2016 9/11/2017 Schedule Reflects CNO Availabilities Inducted Through 2QTR FY16

15 Schedule Reflects CNO Availabilities Inducted Through 3QTR FY16
Third Party Planning CNSL – LPD/LSD Induction Schedule Ship Ship Name Avail Type FY Start Planning A-540 Avail Start Date NSA LSD 0046 TORTUGA SSRA1 2017 7/19/2015 1/9/2017 SPORT LSD 0041 WHIDBEY ISLAND PMA3-3 8/18/2015 2/8/2017 LPD 0017 SAN ANTONIO DPMA 9/13/2015 3/6/2017 MODPRD 2018 5/8/2016 10/30/2017 LPD 0019 MESA VERDE 5/22/2016 11/13/2017 Schedule Reflects CNO Availabilities Inducted Through 3QTR FY16

16 Third Party Planning CNSP - CRUDES Induction Schedule
Ship Ship Name Avail Type FY Start Planning (A-540) Avail Start Date NSA DDG 0101 GRIDLEY DSRA1 2016 3/22/2015 9/12/2016 SPUGET DDG 0106 STOCKDALE SSD CG 0053 MOBILE BAY SRA3-2 2017 4/26/2015 10/17/2016 DDG 0111 SPRUANCE SRA1-2 8/23/2015 2/13/2017 DDG 0073 DECATUR SRA2-1 9/13/2015 3/6/2017 CG 0073 PORT ROYAL ICMAV 10/10/2015 4/2/2017 CG 0065 CHOSIN SSRA1 1/17/2016 7/10/2017 Schedule Reflects CNO Availabilities Inducted Through 2QTR FY16

17 Schedule Reflects CNO Availabilities Inducted Through 3QTR FY16
Third Party Planning CNSP – LPD/LSD Induction Schedule Ship Ship Name Avail Type FY Start Planning A-540 Avail Start Date NSA LPD 0018 NEW ORLEANS DSRA1 2017 6/14/2015 12/5/2016 SSD LPD 0025 SOMERSET SRA1-1 2/21/2016 8/14/2017 Schedule Reflects CNO Availabilities Inducted Through 3QTR FY16

18 Repeat RMC Information Sessions/TI Management Training in Dec15
Third Party Planning Implementation Plan – POA&M # TASK DESCRIPTION RESPONSIBLE DATE 1 Conduct process Table Top exercise in Norfolk SURFMEPP 05AUG2014 2 Conduct process Table Top exercise in San Diego 19AUG2014 3 Conduct Funding Flow / COR workshop #1 SEA 21 / SEA 02 11SEP2014 4 Conduct Funding Flow / COR workshop #2 SEA 21/ SEA 02 19SEP2014 5 Conduct Funding Flow / COR workshop #3 09OCT2014 6 Conduct Mock Availability Exercise #1 with RMCs CNRMC 17OCT2014 7 Finalize SEA 21 / CNRMC integrated FTE requirement SURFMEPP / CNRMC 8 Review model with Fleet / OPNAV at STAR Board F2F SEA 21 / CNRMC 30OCT2014 9 OPNAV validate and load into model OPNAV N43 15NOV2014 10 Conduct Mock Availability Exercise #2 with RMCs 16DEC2014 11 Conduct TI Management Training at MARMC SEA21/SEA02 15FEB2015 12 Brief MARMC WFO/ENGINEERING Personnel SEA21/CNRMC 13 Brief CNSL N43 Staff/Port Engineers 14 Conduct TI Management Training at SWRMC 18MAR2015 15 Brief SWRMC WFO/Engineering Personnel 17MAR2015 16 Brief CNSP N43 Staff/Port Engineers 17 Conduct TI Management Training at NWRMC 18 Brief NWRMC WFO/Engineering Personnel 19MAR2015 19 Paul Murphy MACMO slide Morgan MACMO milestones slide ADD MSRA/ABR slides into backup Repeat RMC Information Sessions/TI Management Training in Dec15

19 Repeat RMC Information Sessions/TI Management Training in Dec15
Third Party Planning Implementation Plan – POA&M # TASK DESCRIPTION RESPONSIBLE DATE 20 Conduct Mock Availability Exercise #3 with RMCs CNRMC 14APR2015 21 Brief MARMC WFO/ENGINEERING Personnel SEA21/CNRMC 25JUN2015 22 Brief CNSL N43 Staff/Port Engineers 23 Conduct TI Management Training at MARMC 18AUG2015 24 Brief SWRMC WFO/Engineering Personnel SEA21/SEA02 14JUL2015 25 Brief CNSP N43 Staff/Port Engineers 26 Conduct TI Management Training at SWRMC 15JUL2015 27 Brief NWRMC WFO/Engineering Personnel 16JUL2015 28 Brief Port Engineers at FMMS 02SEP2015 29 Codify LLTM Procurement Process 30SEP2015 30 Codify TI Origination/Revision Process 31 Codify TI Funding Process 32 Codify RMC TPOC/GAPM Roles & Responsibilities Paul Murphy MACMO slide Morgan MACMO milestones slide ADD MSRA/ABR slides into backup Repeat RMC Information Sessions/TI Management Training in Dec15

20 Third Party Planning Implementation Successes
Conducted onsite implementation briefs in MARMC, SWRMC and NWRMC AORs. Issued 31 Technical Instructions to support: planning of CNO availabilities, LLTM procurement and meeting attendance requirements. (22 CRUDES, 9 LPD/LSD) 15 CNO TIs for CRUDES & LPD/LSD issued: 1884 Work Notifications submitted (73% on WIs) 584 Work Items developed (35% passed to Government Review) Examples: USS NORMANDY 258 WNs assigned to QED 256 WNs being planned on 157 WIs 125 WIs in Government Review USS STOCKDALE 200 WNs assigned to QED 185 WNs being planned on 74 WIs 31 WIs in Government Review

21 Questions?

22 Back Up Slides

23 Third Party Planning Performance Incentive Fee
Accuracy of the work specification Based on seven objective attributes: Location of work Identification References Requirements - phraseology Chronology Tests and Inspections Reports Utilize the existing JFMM specification review process Accuracy is determined on initial Government review of specification No “attribute” errors allowed - validated by the RMC Project Manager Fee calculated using TOTAL number of work specifications developed IAW - JFMM Vol. VII Chap. 4 Append. E 90% accuracy rate required to start earning incentive fee

24 Third Party Planning Performance Incentive Fee
Master Specifications Catalog (MSC) Improvement Fee based on number of template recommendations submitted Changes recommended must result in reduction of RCCs during execution Recommendations must be supported by trend analysis from execution of at least two availabilities Recommendations affecting multiple ship class standard work templates increases fee earned Utilize existing JFMM process for submitting MSC feedback Submit to RMC Standards Coordinator Forward to MSCMO and ACOR Continuously improve and reuse planning products to drive standardization

25 Technical Instruction (TI) Purpose
Specific to the requirements of the Third Party Planning (3PP) Contract Must be within the scope of the contract and Performance Work Statement (PWS) Does not change the PWS or amend the contractual requirements Identifies and provides funding requirements to the 3PP activity Used to invoke optional PWS paragraphs to specific needs of the Maintenance Team Assessment support required during planning period Availability execution support related to Ship Building Specialist (SBS) requirements CFR/RCC processing Used to clarify milestone or other performance requirements Tasking to the Third Party Planning activity is governed by the Technical Instruction. The Technical Instruction provides the mechanism for the Maintenance Team to refine the planning requirements identified in the contract Statement Of Work. The TI cannot be used to change statement of work requirements, only to clarify or provide more specific information related to the planning effort. The TI must be in place prior to the Project Manager providing any tasking by Tasking memo to the planning activity. TI References: Department of Defense COR Handbook, March 22, 2012, Director, Defense procurement and Acquisition Policy NAVSEA Instruction E Contracting Officer’s Representative SUPSHIP Operations Manual, Chapter 3, Contracting and Contract Administration Delegation of Contracting Officer Authority, NAVSEAINST D, Ser 02/035, 3 MAR 04

26 Technical Instruction (TI) Requirements
Base year period of performance (POP) covers 12 months from date of award CG/DDG base year POP: 2/9/2015 to 2/8/2016 LPD/LSD base year POP: 6/1/2015 to 5/31/2016 TI POP must fall within contract year POP Three main TI requirements CNO Availability: By ship, by availability CM/EM Availabilities: By port, by class Long Lead Time Material (LLTM): By port, by class

27 CNO Periods of Performance Example
BASE YEAR OPTION YEAR 1 BULKELEY 2/8/2016 4/26/2015 CLIN Period of Performance 2/9/2015 NORMANDY 2/12/2015 NITZE 11/1/2015 2/9 - 2/8/2017 2/9 - 2/23/2016 TI ISSUE 2/9 – 10/17/2016 TI ISSUE 2/9 - 2/8/2017 TI ISSUE CLINS Change CLIN 0001, 0002, etc. CLIN 1100, 2100, etc. Technical Instructions will only cover the planning requirements necessary during the associated CLIN POP Multiple Technical Instructions may be required for a specific CNO availability Technical Instructions POP must fall within associated CLIN POP

28 Third Party Planning Implementation Challenges
Milestones: JFMM requires update to reflect new contract strategy requirements Different milestone definitions and intervals across RMCs impacts planning and clear expectations of the Third Party Planner 3PP Process Standardization across RMCs: Document , train, and verify to ensure R&Rs are understood Performance Incentives – Work Spec FPY/MSC Feedback LLTM Procurement TI Origination/Revision TPOC/GAPM Roles and Responsibilities TI Annual/IncrementalFunding 3PP Product Standardization across RMCs: CDRL A001 Work Item IGE content CDRL A005 Integration Schedule/Turnover Book Modernization Funding: Multiple funding lines ( ) per hull to fund each specific alteration creates undue burden on BFMs/SEA 02 and the contractor for financial tracking/management. Performance Issues - NMD: Multiple planning reports not functional (Composite Work Package, Departure Report, etc.) TI numbering is too generic - tracking multiple availabilities across RMCs problematic 3PP cannot apply MD rate to work item estimates at availability level 3PP cannot access CSWT IGE – must develop estimate from scratch (NMD role issue)


Download ppt "Surface Ship Maintenance and Modernization"

Similar presentations


Ads by Google