Download presentation
Presentation is loading. Please wait.
Published byTracey Flowers Modified over 9 years ago
1
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 Project Scheduling IENG 321 IENG 321
2
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 2 Outline What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks Precedence Diagramming Method PERT and CPM Methods Use of Project Concepts
3
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 3 What is a “Project”? Distinguishing characteristics of projects Example
4
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 4 Examples of Projects (Table 14.1)
5
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 5 Objectives and Tradeoffs Meet the specifications Stay within the budget
6
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 6 Project Management Activities and Decisions Planning Scheduling Project Control
7
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 7 Planning Identify the project customer Establish the end product or service Set project objectives Estimate total resources and time required Decide on the form of project organization Make key personnel appointments Define major tasks required Establish a budget
8
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 8 Scheduling Develop a detailed work-breakdown structure Estimated time required for each task Sequence tasks in proper order Develop a start/stop time for each task Develop detailed budget for each task Assign people to tasks
9
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 9 Control Monitor actual time, cost, and performance Compare planned to actual figures Determine whether corrective action is needed Evaluate alternative corrective actions Take appropriate corrective action
10
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 10 Gantt Chart Project Example (Figure 14.1) Week
11
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 11 Network Project Chart (Figure 14.2) Start 410 Dig basement Pour footing Lay block foundation Install main floor Erect frame Finish below- grade work Secure outside sheathing Install roof boards Install windows 12356 7 8 9 Finish rough-in frame
12
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 12 Constant-Time Networks Activity times assumed to be constant “Dummy” activities Notations used in calculating start and finish times: –ES(a) =Early Start of activity a –EF(a) =Early Finish of activity a –LS(a) =Late Start of activity a –LF(a) =Late Finish of activity a
13
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 13 Network Diagram (Figure 14.3) 1 2 4 3 3 4 5 6 1 Event Activity 2
14
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 14 Dummy Activity Situations (Figure 14.4a) F H G E a. Activities F and G have the same predecessor (E) and the same successor (H)
15
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 15 Dummy Activity Situations (Figure 14.4b) E A B C D b. Activity A and B have a common predecessor (E), but they have different predecessors (C and D)
16
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 16 Dummy Activity Situations (Figure 14.4c) C D I K J c. Activities C and D have a common successor (K), but different successors (I and J)
17
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 17 Calculating ES, EF, LS, LF, and Completion Time ES (a) = 0 for the starting activity EF (a) = ES (a) + t (a)* ES (a) = max [EF (all predecessors of a)] Project completion time = max [EF(all ending activities)] * t (a) denotes the duration of activity a LF (a) = min [LS (all successors of a)] LS (a) = LF - t(a)* Forward Pass: Backward pass:
18
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 18 Slack Times Total Slack Time (TST): LS (a) - ES (a) - EF (a)= LF(a) - EF(a) LS (a) - ES (a) - EF (a)= LF(a) - EF(a) Free Slack Time (FST) min [ES (all successors of a)] - EF (a)
19
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 19 Activity Start and Finish Times (Figure 14.5) 1 2 4 3 [ES, EF] [LS, LF] [0, 3] 3 [0, 3] [3, 8] 5 [3, 8] [5, 7] 2 [6, 8] [0, 4] 4 [2, 6] [3, 5] 2 [4, 6]
20
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 20 Activity Times (Table 14.3)
21
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 21 PDM Network (Figure 14.6) Activity 1-2 Activity 2-4 Activity 2-3 Activity 3-4 Activity 1-3
22
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 22 PDM Time Schedule (Figure 14.7) 012345678 2-4 1-2 2-3 1-33-4 Project Completion
23
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 23 PDM Precedence Relationship AB Finish to Start Job B can start no sooner than 3 days after Job A is completed. FS = 3 AB Start to Start Job B can start no sooner than 2 days after Job A has started. SS = 2 AB Finish to Finish Job B can finish no sooner than 4 days after Job A was finished. FF = 4 AB Start to Finish Job B can finish no sooner than 6 days after Job A has started. SF = 6
24
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 24 Cement Floor Example (Figure 14.9) Install forms Pour cement FF = 0 SS = 1
25
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 25 Time-Cost Relationship in CPM Crash Cost Cost Normal Cost Crash Time Normal Time
26
Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 26 Use of Project Management Concepts Scheduling is only part of a complete approach to project management Tradeoffs between sophistication and cost of methods Choice between PERT, CPM, and PDM Project management software
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.