Download presentation
Presentation is loading. Please wait.
Published byHilary Kevin Holland Modified over 8 years ago
1
Load Management Projects at the Department of Water Affairs through an Integrated Systems Approach Chris Scheepers 15 August 2012
2
The Need for Water... South Africa is divided into 19 water catchment areas. Water is transferred to different areas and national key important instances. Usutu-Vaal water scheme Water needed for: Agriculture Municipalities Power stations Chemical processes (Sasol) Mines
3
Usutu-Vaal Government Water Scheme (GWS) Standerton Secunda Matla PS
4
Pump Stations Naauwpoort (Witbank); Rietfontein (Secunda); Grootfontein (Charl Cilliers); Grootdraai and Tutuka (Standerton); Geelhoudboom; (Between Morgenstond- and Heyshope dam) and Heyshope (Piet Retief). Clients/Destinations Duvha P/S (if needed) Matla P/S (Kriel P/S) Sasol and Rietfontein dam Tutuka P/S and Grootfontein weir Grootdraai- and Morgenstond dam Geelhoutboom pump station Usutu-Vaal GWS Pump Station and Clients
5
Usutu-Vaal GWS Layout: Grootdraai (GD) Dam Supply Grootdraai backup supply: Heyshope- and Geelhoutboom pump stations Pump when GD is below minimum operating level (80%). Usually during the winter/dry seasons.
6
Usutu-Vaal GWS Layout: Client Supply Installed Capacity Tutuka (4x 1405 kW) Grootdraai (4x 1650 kW) Grootfontein (1x 2200 kW and 4x 2150kW) Rietfontein (4x 3050 kW) Target savings 3.80 MW 3.15 MW 3.20 MW
7
Usutu-Vaal GWS: Previous Control Philosophy Relay logic control panels were used. Limited remote control. Limited condition monitoring available. Limited monitoring of dam/reservoir levels. Time of use (TOU) not taken into account. No data trending was available.
8
Upgrade pumps to enable automatic control. Upgrade centralise SCADA & include a REMS Install additional communication infrastructure. Monitor dam levels – GSM modems. Control system to optimise load shifting potential. Load Shift Project: Usutu-Vaal GWS – Scope of Work Upgrades on Grootdraai, Grootfontein and Rietfontein:
9
Usutu-Vaal GWS: New Control Philosophy PLC panels allowed for remote control. Previous control philosophy was used. Pump station control updated – communication between pumps. Detailed conditioned monitoring. Dam levels monitoring by GSM modems. Integrated control philosophy between the pump stations.
10
Usutu-Vaal GWS: Introduced SCADA New SCADA with condition monitoring.
11
Usutu-Vaal GWS: Integration of pump stations Grootdraai (GD) pump into Vlakfontein Canal to Grootfontein: 24 hours with 1 GD pump 11-12` hours with 2 GD pumps Grootfontein pump water from forebay to Knoppiesfontein towers. Water may not be spilled at the Grootfontein weir. 41 km Vlakfontein canal
12
Usutu-Vaal GWS: Grootdraai Pump Station Results Grootdraai pumps stopped at the following times: 07h00 to 09h00 – To ensure water ‘shortage’ at Grootfontein. 18h00 to 20h00 – Evening load shift. Note: Tutuka pumps only stopped during evening peak. Achieved load shift (3 months): 3.8 MW 103% performance. (Load shift for Grootdraai and Tutuka)
13
Usutu-Vaal GWS: Grootfontein Pump Station Results The Grootfontein pumps were stopped: From 06h00 due to evening load shift at Grootdraai. 18h00 and 20h00 – Evening load shift. Achieved load shift (3 months): 3.2 MW 107% performance.
14
Usutu-Vaal GWS: Rietfontein Pump Station Results The Rietfontein pumps were only stopped during: 18h00 and 20h00 – Evening load shift. Achieved load shift (3 months): 6.34 MW 198% performance.
15
Conclusion Large electrical loads were shifted out of the evening peak. (Average 3 month total of 13.4 MW) The supply to the clients was not compromised. The control philosophy was revised and updated. The control between pump stations was successfully integrated. Advanced condition monitoring are done by the SCADA. Control allows for most efficient pump combinations to be operated. Remote access is possible for maintenance, control and support. Pumps were refurbished - not included in the initial contract.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.