Folie 1 Financing Concentrating Solar Power - Subsidy or Investment? Franz Trieb Stuttgart, 15.06.2010
2
Folie 2 A Strategy for CSP Finance
3
Folie 3 DLR 2009 Challenge 1: Investment replaces fuel consumption Fuel
4
Folie 4 www.oilnergy.com Challenge 2: Known immediate cost but unknown future savings
5
Folie 5 Challenge 3: Fix Cost but Non-Fix Revenue German power market during the first week-end of October 2009
6
Folie 6 Challenge 4: Initial Cost Levels above Market Price Ragwitz 2009
7
Folie 7 1.Long-term investment (20-40 years) not only for the power plants but also for their „fuels“. 2.Unknown future savings compared to volatile and unpredictable conventional fuel prices. 3.Known long-term cost but unknown long-term revenues if electricity output is fluctuating and sold at spot markets. 4.Additional cost of early plants cannot be recovered under conventional market conditions and less if competitors are subsidized. Pioneers are punished by market forces because markets are adapted to conventional power schemes. Investment Challenges
8
Folie 8 Model Case Power Park:
9
Folie 9
10
Folie 10 Model Case Cost Structure
11
Folie 11 10008246 39000 95000 240000 417500 595000 772500 950000 CSP Required Tariff Model
12
Folie 12 B Break Even with Average Cost
13
Folie 13 B B1 B2 B3 Break Even with different load segments
14
Folie 14 Case 1: 100% Substitution in peak and medium load segment by CSP
15
Folie 15 a b c Case 1: 100% Substitution in peak and medium load segment by CSP
16
Folie 16 Calculation of Annual Solar Share in the Initial Phase
17
Folie 17 1st Step: The Load Curve is devided into Peak, Medium and Base Load
18
Folie 18 In higher time resolution it looks like this for a summer week
19
Folie 19 Solar Peak Load
20
Folie 20 2nd Step: The peak segment is separated and then, the lower part is covered by CSP (solar or hybrid), while the upper part (residual capacity) is covered by conventional peaking plants
21
Folie 21 In higher time resolution it looks like this for a summer week
22
Folie 22 3rd Step: Medium Load is separated and the lower part covered by CSP
23
Folie 23 In higher time resolution it looks like this for a summer week
24
Folie 24 4th Step: Base Load is separated and the lower part covered by CSP
25
Folie 25 In higher time resolution it looks like this for a summer week
26
Folie 26 Calculation of Annual Solar Share Summary
27
Folie 27
28
Folie 28 a b c Case 2: Partial Substitution of Fuel by CSP