November 17, 2015 Application of ASTM’s Greener Cleanup Guide to a Superfund Site in Oregon Results and Take-Home Lessons Beth Sheldrake, Manager, Superfund Program, EPA Region 10. Michael E. Miller, Principal Environmental Chemist, CDM Smith.
2
Striving for Greener Cleanups Policies (August 2009) OSWER Principles for Greener Cleanup National Superfund Green Remediation Strategy Region 10 Clean and Green Policy Tools Best Management Practice (BMP) Fact Sheets (2008 – 2013) ASTM’s Standard Guide for Greener Cleanups (November 2013) 2
3
EPA Leading by Example Options for EPA-lead Sites: Include reference to Regional “Clean and Green” policy in bid documents EPA applies ASTM guide and identifies BMPs in bid documents EPA asks bidders to identify BMPs EPA asks bidders to apply ASTM guide BMPs after winning bid, before construction 3
4
Application of ASTM Standard Guide Applicability to the Site – Opportunity Assessment Rate of Return – BMP Prioritization High Priority – High footprint reduction and high implementability Medium Priority – High footprint reduction and low implementability or low footprint and high implementability Low Priority – Low footprint reduction and low implementability 4
5
North Ridge Estates Site: BMP Evaluation
6
North Ridge Estates Site South-central Oregon, high desert Residential subdivision, 3 mi north of Klamath Falls 6
7
Topography 7
8
Site History 1940s military barracks Improper building demolition during residential development Asbestos containing materials (ACM) waste piles, burial pits, surface/sub-surface dispersal 1993: began building houses 1994-2002: properties sold to homeowners 2003-2011: emergency removals ACM Re-exposure by frost heaving & erosion Not a permanent solution ~ 300,000 cubic yards asbestos contaminated soil remain 8
9
Remedial Action Objectives Mitigate direct contact and inhalation of asbestos fibers. Control migration and spread of asbestos. Selected Remedy Excavation & consolidation of ACM in on-site repositories Building interior cleaning Post-excavation capping 9
10
Best Management Practice (BMP) Selection Purpose: minimize impacts 160 + BMPs – complete list in ASTM Standard 30 BMPs applicable to asbestos dig & haul Equipment and fuel Materials use 16 final BMPs for possible incorporation into remedial design 10
11
Greatest Impacts from Remedy Implementation Fuel consumption Earth moving Transportation Material use Backfill Revegetation Equipment Residential houses Recovered materials Site preparation 11
12
BMPs: Diesel Emission Control Technology EPA Off-Highway Emission Standards 12
13
BMPs: Diesel Non-road Construction Equipment Engines must meet at least EPA Tier 2 non-road emission standards Year 1: ≥ 25% of the equipment Meet Tier 4, or Retro-fit for 85% reduction in PM emissions Years 2 and 3: ≥ 50% of the equip. Meet Tier 4, or Retro-fit for 85% reduction in PM emissions End of project 13
14
Diesel On-road Vehicles At least 90% of diesel on-road vehicles : Engines that meet EPA 2007 on-road emissions stds., or Emission control technology to reduce PM emissions by at least 85% + Idling reduction plan for all diesel vehicles 14
15
BMPs: Materials BMPImplementationMetrics Use recycled contentCrush concrete barracks foundations for use as marker barrier Amount re-used vs. non re-used concrete Biodegradable, recycled seed matting StrawTrack and report Compost instead of chemical fertilizers Plant material, manure, or biosolids Tons of compost Use equipment and products that can be re-used or recycled Select equipment that can be re-used. Recycle waste. Track waste streams 15
16
BMPs: Site Preparation/Land Restoration BMPImplementationMetrics Revegetate quickly & with native species Plant at the end of each field season Track and report Native, drought resistant plant cover. Preserve biodiversity/ecosystem services. Native seed mixtures% planting with native seeds On-site or nearby sources of backfill Local borrow sourceTrack and report 16
17
More BMPs BMPImplementationMetrics Reuse existing buildingsUse an abandoned house for office & storage. Redevelopment includes cleaning & reselling abandoned houses. Built into design Reuse/recycle recovered materials Recycle scrap metal, fuel, lubricants & removed trees. Crushed concrete foundations for marker barrier. Track and report 17
18
BMP Evaluation: Conclusions Recognize benefits of env. footprint reduction Review entire BMP list Identify most applicable & most effective Thereby shrink the remedy’s footprint One or two BMPs do not a green remediation make! 18